3983-3985 N ALTA MESA DR 91604

Certificate Information: 3983-3985 N ALTA MESA DR 91604

Application / Permit
22014-10000-04167
Plan Check / Job No.
B22LA16487
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan An existing garage (234 sq.ft.) in one story single family dwelling was converted to a JADU PER STATE LAW
Permit Issued
Issued on 3/28/2023
Issuing Office
Current Status
CofO Issued on 1/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/1/2022 APPLICANT
Assigned to Plan Check Engineer 9/8/2022 KHUONG TRUONG
Corrections Issued 9/8/2022 KHUONG TRUONG
Applicant returned to address corrections 11/10/2022 KHUONG TRUONG
Applicant returned to address corrections 1/26/2023 KHUONG TRUONG
Plan Check Approved 3/22/2023 KHUONG TRUONG
Issued 3/28/2023 APPLICANT
CofO in Progress 10/24/2023 CHRISTOPHE COCHRAN
Permit Finaled 1/17/2024 RUBEN SALAS
CofO Issued 1/17/2024 RUBEN SALAS
Permit Finaled 1/17/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 11/9/2022 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 11/9/2022 LEE GUILBEAUX
Sewer availability Cleared 11/9/2022 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 11/9/2022 LEE GUILBEAUX
Specific Plan Cleared 1/24/2023 OLGA AYALA
Grading Pre-Inspection Cleared 1/25/2023 KIRK LINKLATER

Contact Information

Contractor Owner-Builder       ,
Engineer Xiao,, Qiang; Lic. No.: S5289 1520 BROOKHOLLOW #45      SANTA ANA, CA 92705

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/23/2023 Corrections Issued CHRISTOPHE COCHRAN
PLUMBING-Rough 5/23/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
Footing/Foundation/Slab 7/18/2023 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 8/9/2023 Partial Approval CHRISTOPHE COCHRAN
ELECTRICAL-Rough 8/9/2023 Approved CHRISTOPHE COCHRAN
Green Building Rough 8/9/2023 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 8/9/2023 Corrections Issued CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 8/17/2023 Approved CHRISTOPHE COCHRAN
Insulation 8/17/2023 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 8/17/2023 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 8/17/2023 Approved CHRISTOPHE COCHRAN
Drywall Nailing 8/23/2023 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 8/23/2023 Approved CHRISTOPHE COCHRAN
Final 10/6/2023 Corrections Issued CHRISTOPHE COCHRAN
Green Building Final 10/6/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 10/6/2023 SGSOV Approved CHRISTOPHE COCHRAN
Smoke Detectors 10/6/2023 Approved CHRISTOPHE COCHRAN
Final 10/24/2023 OK to Issue CofO CHRISTOPHE COCHRAN
Green Building Final 10/24/2023 Approved CHRISTOPHE COCHRAN