147 N WINDSOR BLVD 90004
Certificate Information: 147 N WINDSOR BLVD 90004
- Application / Permit
- 22014-10000-04164
- Plan Check / Job No.
- B22LA16476
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) ADDITION AND RENOVATION TO (E) SFD: 1st floor - enclosed existing cover porch for new dining room, enlarge existing breakfast area add new cover porch; 2nd floor - remodel exisiting bedroom, add new w-i-c and m-bath.
- Permit Issued
- Issued on 8/30/2023
- Issuing Office
- Current Status
- CofO Issued on 12/23/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/17/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/1/2022 | SAM CHANG |
| Corrections Issued | 9/9/2022 | SAM CHANG |
| Quality Review Completed | 9/14/2022 | KEN GILL |
| Building Plans Picked Up | 9/16/2022 | APPLICANT |
| Applicant returned to address corrections | 8/24/2023 | SAM CHANG |
| Plan Check Approved | 8/30/2023 | SAM CHANG |
| Issued | 8/30/2023 | APPLICANT |
| CofO in Progress | 12/18/2024 | JEFFREY MEAD |
| Permit Finaled | 12/23/2024 | DEROLD HAUFF |
| CofO Issued | 12/23/2024 | DEROLD HAUFF |
| Permit Finaled | 12/23/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/2/2023 | AMAAN MALIK |
| Sewer availability | Cleared | 3/2/2023 | AMAAN MALIK |
| Low Impact Development | Cleared | 7/27/2023 | MARTIN FRAGOSO |
| HPOZ | Cleared | 8/10/2023 | DAMIAN GATTO |
| Roof/Waste drainage to street | Cleared | 8/10/2023 | JEREMY CHOK |
| ZI | Cleared | 8/10/2023 | DAMIAN GATTO |
| Green Code | Cleared | 8/24/2023 | SAM CHANG |
Contact Information
| Contractor | Simply The Best; Lic. No.: 532135-B | 6517 LINDENHURST AVENUE LOS ANGELES, CA 90048 |
| Engineer | Nastarin,, Hooman; Lic. No.: C62199 | 554 S SAN VICNETE BLVD 202 LOS ANGELES, CA 90048 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/28/2023 | Corrections Issued | JEFFREY MEAD |
| Deputy Other (see comments) | 12/29/2023 | Approved | JEFFREY MEAD |
| Excavation/Setback/Form/Re-Bar | 12/29/2023 | Partial Approval | JEFFREY MEAD |
| Footing/Foundation/Slab | 12/29/2023 | Corrections Issued | JEFFREY MEAD |
| Deputy Reinf. Concrete | 1/2/2024 | Partial Approval | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 2/14/2024 | Partial Approval | STUART CHAPMAN |
| BUILDING-Rough-Frame | 4/11/2024 | Not Ready for Inspection | JEFFREY MEAD |
| Excavation/Setback/Form/Re-Bar | 4/11/2024 | Approved | JEFFREY MEAD |
| Green Building Rough | 4/11/2024 | Not Ready for Inspection | JEFFREY MEAD |
| HVAC-Rough | 4/11/2024 | Partial Approval | JEFFREY MEAD |
| PLUMBING-Rough | 4/11/2024 | Approved | JEFFREY MEAD |
| Wood Frame | 4/11/2024 | Not Ready for Inspection | JEFFREY MEAD |
| ELECTRICAL-Rough | 4/26/2024 | Approved | JEFFREY MEAD |
| HVAC-Rough | 4/26/2024 | Partial Approval | JEFFREY MEAD |
| BUILDING-Rough-Frame | 4/29/2024 | Approved | JEFFREY MEAD |
| Green Building Rough | 4/29/2024 | Approved | JEFFREY MEAD |
| HVAC-Rough | 5/22/2024 | Approved | JEFFREY MEAD |
| Insulation | 5/22/2024 | Approved | JEFFREY MEAD |
| Drywall Nailing | 5/29/2024 | Approved | JEFFREY MEAD |
| Shower Pan | 5/31/2024 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 6/11/2024 | Partial Approval | JEFFREY MEAD |
| Interior/Exterior Lathing | 6/13/2024 | Approved | JEFFREY MEAD |
| Final | 9/23/2024 | Corrections Issued | JEFFREY MEAD |
| Footing/Foundation/Slab | 9/23/2024 | Approved | JEFFREY MEAD |
| Green Building Final | 9/23/2024 | Approved | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 9/23/2024 | SGSOV Approved | JEFFREY MEAD |
| Smoke Detectors | 9/23/2024 | Approved | JEFFREY MEAD |
| Final | 11/25/2024 | Corrections Issued | JEFFREY MEAD |
| Final | 12/17/2024 | OK to Issue CofO | JEFFREY MEAD |