4261 E SAN RAFAEL AVE 90042
Certificate Information: 4261 E SAN RAFAEL AVE 90042
- Application / Permit
- 22014-10000-04154
- Plan Check / Job No.
- B22LA16440
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: INTER REMODEL, EXTERIOR REMODEL, REMOVE SUNSHAE AND 196 SF ADDITION TO (E) 1-STORY SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 7/22/2024
- Issuing Office
- Current Status
- CofO Issued on 6/4/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/17/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/1/2022 | DANIEL YIP |
| Corrections Issued | 9/2/2022 | DANIEL YIP |
| Quality Review Completed | 9/9/2022 | PRANITA SHAH |
| Plan Check Approved | 11/8/2022 | DANIEL YIP |
| Issued | 7/22/2024 | APPLICANT |
| CofO in Progress | 6/3/2026 | OSVALDO PARAMO |
| Permit Finaled | 6/4/2026 | DEROLD HAUFF |
| CofO Issued | 6/4/2026 | DEROLD HAUFF |
| Permit Finaled | 6/4/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 9/2/2022 | DANIEL YIP |
| BHO/Hillside ordinance | Cleared | 9/20/2022 | CINDY QI |
| BHO/Hillside ordinance | Cleared | 9/20/2022 | CINDY QI |
| BHO/Hillside ordinance | Cleared | 9/20/2022 | CINDY QI |
| BHO/Hillside ordinance | Cleared | 9/20/2022 | CINDY QI |
| BHO/Hillside ordinance | Cleared | 9/20/2022 | CINDY QI |
| Roof/Waste drainage to street | Cleared | 9/20/2022 | CINDY QI |
| Specific Plan | Cleared | 10/20/2022 | OLGA RUANO |
| Eng Process Fee Ord 176,300 | Cleared | 10/24/2022 | CINDY QI |
Contact Information
| Contractor | Stafford C J Construction; Lic. No.: 1047841-B | , |
| Engineer | Mohammadi,, Saeid; Lic. No.: C82330 | 17412 VENTUTRA BLVD 21 ENCINO, CA 91316 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/29/2024 | Partial Inspection | OSVALDO PARAMO |
| Deputy Drilled-In Anchors | 8/9/2024 | Conditional Approval | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 8/9/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 8/13/2024 | Partial Approval | OSVALDO PARAMO |
| Deputy Reinf. Concrete | 8/14/2024 | Conditional Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 8/28/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Green Building Rough | 8/28/2024 | Approved | LUIS CASTRO |
| Deputy Drilled-In Anchors | 9/27/2024 | Conditional Approval | OSVALDO PARAMO |
| Footing/Foundation/Slab | 10/1/2024 | Approved | OSVALDO PARAMO |
| Pre-Inspection | 12/10/2024 | Approved | ROY SPAULDING |
| Pre-Inspection | 4/3/2025 | Partial Inspection | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 5/6/2025 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Rough | 5/6/2025 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 5/6/2025 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 5/8/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 6/2/2025 | Approved | REGINA MENDEZ |
| Pre-Inspection | 6/4/2025 | Approved | ALIZAH MAYAGOITIA |
| Insulation | 6/10/2025 | Approved | ALIZAH MAYAGOITIA |
| Drywall Nailing | 6/20/2025 | Approved | REGINA MENDEZ |
| Interior/Exterior Lathing | 7/21/2025 | Corrections Issued | ANTHONY RAMOS |
| Shower Pan | 7/21/2025 | Approved | ANTHONY RAMOS |
| Interior/Exterior Lathing | 7/31/2025 | Corrections Issued | GEM DE OCAMPO |
| Special/Order Compliance | 8/25/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Deputy Drilled-In Anchors | 9/25/2025 | Conditional Approval | GEM DE OCAMPO |
| BUILDING-Rough-Frame | 3/25/2026 | Approved | ALIZAH MAYAGOITIA |
| Final | 3/25/2026 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Green Building Final | 3/25/2026 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 3/25/2026 | SGSOV Not Ready | ALIZAH MAYAGOITIA |
| Smoke Detectors | 3/25/2026 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Final | 3/31/2026 | Corrections Issued | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 3/31/2026 | SGSOV Approved | ALIZAH MAYAGOITIA |
| Smoke Detectors | 3/31/2026 | Approved | ALIZAH MAYAGOITIA |
| Final | 5/27/2026 | OK to Issue CofO | OSVALDO PARAMO |