6208 E STRICKLAND AVE 90042
Certificate Information: 6208 E STRICKLAND AVE 90042
- Application / Permit
- 22014-10000-04149
- Plan Check / Job No.
- B22LA16418
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: INTERIOR REMODEL AND ADDITION TO (E) 1-STORY SINGLE FAMILY DWELLING TO CREATE A 2-STORY SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 3/9/2023
- Issuing Office
- Current Status
- Issued on 3/9/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/18/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/2/2022 | DANIEL YIP |
| Corrections Issued | 9/7/2022 | DANIEL YIP |
| Quality Review Completed | 9/8/2022 | GARO TELMI |
| Applicant returned to address corrections | 11/21/2022 | DANIEL YIP |
| Applicant returned to address corrections | 1/12/2023 | DANIEL YIP |
| Applicant returned to address corrections | 3/2/2023 | DANIEL YIP |
| Plan Check Approved | 3/9/2023 | DANIEL YIP |
| Issued | 3/9/2023 | APPLICANT |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 1/9/2023 | CINDY QI |
| BHO/Hillside ordinance | Cleared | 1/9/2023 | CINDY QI |
| BHO/Hillside ordinance | Cleared | 1/9/2023 | CINDY QI |
| BHO/Hillside ordinance | Cleared | 1/9/2023 | CINDY QI |
| BHO/Hillside ordinance | Cleared | 1/9/2023 | CINDY QI |
| Sewer availability | Cleared | 1/9/2023 | CINDY QI |
| GPI Written Notices | Cleared | 1/11/2023 | DANIEL YIP |
| Grading Pre-Inspection | Cleared | 1/11/2023 | DANIEL YIP |
| Eng Process Fee Ord 176,300 | Cleared | 1/12/2023 | CINDY QI |
| Hydrant and Access approval | Cleared | 1/27/2023 | KURT CORRAL |
| Roof/Waste drainage to street | Cleared | 3/3/2023 | TREVOR QUAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/10/2023 | Conditional Approval | AMY COLIN |
| Deputy Other (see comments) | 5/10/2023 | Conditional Approval | AMY COLIN |
| Excavation/Setback/Form/Re-Bar | 7/14/2023 | Corrections Issued | AMY COLIN |
| Excavation/Setback/Form/Re-Bar | 7/20/2023 | Corrections Issued | AMY COLIN |
| Footing/Foundation/Slab | 7/20/2023 | Conditional Approval | AMY COLIN |
| PLUMBING-Rough | 7/20/2023 | Partial Approval | AMY COLIN |
| Drywall Nailing | 8/2/2023 | Partial Approval | AMY COLIN |
| Floor/Roof Diaphrgm/Shear Wall | 8/2/2023 | Partial Approval | AMY COLIN |
| Interior/Exterior Lathing | 8/2/2023 | Partial Approval | AMY COLIN |
| Floor/Roof Diaphrgm/Shear Wall | 8/15/2023 | Partial Approval | AMY COLIN |
| BUILDING-Rough-Frame | 9/6/2023 | Corrections Issued | AMY COLIN |
| ELECTRICAL-Rough | 9/6/2023 | Corrections Issued | AMY COLIN |
| PLUMBING-Rough | 9/6/2023 | Corrections Issued | AMY COLIN |
| ELECTRICAL-Rough | 9/13/2023 | Approved | AMY COLIN |
| Insulation | 9/13/2023 | Approved | AMY COLIN |
| Interior/Exterior Lathing | 9/13/2023 | Approved | AMY COLIN |
| PLUMBING-Rough | 9/13/2023 | Approved | AMY COLIN |
| Drywall Nailing | 9/28/2023 | No Access for Inspection | ROY SPAULDING |
| Green Building Rough | 9/28/2023 | No Access for Inspection | ROY SPAULDING |
| Drywall Nailing | 10/4/2023 | Partial Approval | ROY SPAULDING |
| Green Building Rough | 10/4/2023 | Corrections Issued | ROY SPAULDING |
| BUILDING-Rough-Frame | 2/23/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Drywall Nailing | 2/23/2024 | Conditional Approval | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 2/23/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Final | 2/23/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 2/23/2024 | Approved | ALIZAH MAYAGOITIA |
| Green Building Final | 2/23/2024 | Approved | ALIZAH MAYAGOITIA |
| Green Building Rough | 2/23/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 2/23/2024 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 2/23/2024 | SGSOV Not Ready | ALIZAH MAYAGOITIA |
| Smoke Detectors | 2/23/2024 | Approved | ALIZAH MAYAGOITIA |
| Verify Sprinkler Sign Off | 2/23/2024 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 4/5/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Drywall Nailing | 4/5/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Final | 4/5/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Green Building Rough | 4/5/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 4/5/2024 | SGSOV Not Ready | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 4/24/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Drywall Nailing | 4/24/2024 | Approved | ALIZAH MAYAGOITIA |
| Final | 4/24/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Rough | 4/24/2024 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 4/24/2024 | SGSOV Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 5/14/2024 | Approved | ALIZAH MAYAGOITIA |
| Final | 5/14/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |