624 W 90TH ST 90044

Certificate Information: 624 W 90TH ST 90044

Application / Permit
22014-10000-04148
Plan Check / Job No.
B22LA16405
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO (E) SFD at REAR
Permit Issued
Issued on 11/15/2022
Issuing Office
Metro
Current Status
CofO Issued on 4/24/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/17/2022 APPLICANT
Assigned to Plan Check Engineer 8/17/2022 MINA HABILI
Corrections Issued 8/17/2022 MINA HABILI
Applicant returned to address corrections 9/2/2022 DANIEL SANJUAN
Plan Check Approved 11/15/2022 SHANGQIN XIE
Issued 11/15/2022 APPLICANT
CofO in Progress 3/5/2024 MICHAEL LEWIS
CofO in Progress 3/5/2024 MICHAEL LEWIS
CofO in Progress 4/19/2024 MICHAEL LEWIS
CofO Issued 4/24/2024 DEROLD HAUFF
Permit Finaled 4/24/2024 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 8/30/2022 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 9/2/2022 AMAAN MALIK
Community Plan Implem. Overlay Cleared 10/25/2022 RAFAEL FONTES

Contact Information

Contractor Right Choice Home Remodeling Inc The; Lic. No.: 1066456-B 15315 MAGNOLIA BLVD #429      SHERMAN OAKS, CA 91403

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/16/2022 Not Ready for Inspection HORACE FULTZ
PLUMBING-Rough 12/16/2022 Partial Approval HORACE FULTZ
Footing/Foundation/Slab 12/29/2022 No Access for Inspection HORACE FULTZ
Reinforced Concrete Frame 12/29/2022 No Access for Inspection HORACE FULTZ
BUILDING-Rough-Frame 12/30/2022 No Access for Inspection LILIANA PORTILLO
Green Building Rough 12/30/2022 No Access for Inspection LILIANA PORTILLO
Reinforced Concrete Frame 12/30/2022 No Access for Inspection LILIANA PORTILLO
PLUMBING-Rough 1/4/2023 Corrections Issued BRENDAN MORELLI
PLUMBING-Rough 1/5/2023 Not Ready for Inspection BRENDAN MORELLI
PLUMBING-Rough 1/13/2023 Not Ready for Inspection LILIANA PORTILLO
Footing/Foundation/Slab 1/18/2023 Corrections Issued LILIANA PORTILLO
PLUMBING-Rough 1/18/2023 Corrections Issued LILIANA PORTILLO
Footing/Foundation/Slab 1/23/2023 Corrections Issued LILIANA PORTILLO
Footing/Foundation/Slab 2/3/2023 Corrections Issued LILIANA PORTILLO
BUILDING-Rough-Frame 3/6/2023 No Access for Inspection JOHN KLARIN
ELECTRICAL-Rough 3/6/2023 No Access for Inspection JOHN KLARIN
Green Building Rough 3/6/2023 No Access for Inspection JOHN KLARIN
PLUMBING-Rough 3/6/2023 No Access for Inspection JOHN KLARIN
BUILDING-Rough-Frame 3/15/2023 No Access for Inspection LILIANA PORTILLO
ELECTRICAL-Final 3/15/2023 No Access for Inspection LILIANA PORTILLO
Green Building Rough 3/15/2023 No Access for Inspection LILIANA PORTILLO
PLUMBING-Rough 3/15/2023 No Access for Inspection LILIANA PORTILLO
ELECTRICAL-Rough 3/20/2023 Not Ready for Inspection STUART CHAPMAN
PLUMBING-Rough 3/20/2023 Partial Approval STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 4/3/2023 Corrections Issued ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 4/5/2023 Conditional Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 4/7/2023 Partial Approval LILIANA PORTILLO
Insulation 4/7/2023 Partial Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 4/14/2023 No Access for Inspection LILIANA PORTILLO
BUILDING-Rough-Frame 5/1/2023 No Access for Inspection MICHAEL LEWIS
ELECTRICAL-Rough 5/1/2023 No Access for Inspection MICHAEL LEWIS
Green Building Rough 5/1/2023 No Access for Inspection MICHAEL LEWIS
PLUMBING-Rough 5/1/2023 No Access for Inspection MICHAEL LEWIS
PLUMBING-Rough 5/19/2023 Corrections Issued MICHAEL LEWIS
HVAC-Rough 5/30/2023 Approved MICHAEL LEWIS
PLUMBING-Rough 5/30/2023 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 6/2/2023 No Access for Inspection STUART CHAPMAN
ELECTRICAL-Rough 6/2/2023 No Access for Inspection STUART CHAPMAN
Green Building Rough 6/2/2023 No Access for Inspection STUART CHAPMAN
BUILDING-Rough-Frame 6/13/2023 Corrections Issued MICHAEL LEWIS
ELECTRICAL-Rough 6/13/2023 No Access for Inspection MICHAEL LEWIS
Green Building Rough 6/13/2023 No Access for Inspection MICHAEL LEWIS
BUILDING-Rough-Frame 7/18/2023 Partial Inspection MICHAEL LEWIS
Green Building Rough 7/18/2023 Partial Inspection MICHAEL LEWIS
ELECTRICAL-Rough 8/30/2023 Approved MICHAEL LEWIS
HVAC-Rough 8/30/2023 Partial Inspection MICHAEL LEWIS
PLUMBING-Rough 8/30/2023 Partial Inspection MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 9/11/2023 Corrections Issued MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 9/20/2023 Corrections Issued MICHAEL LEWIS
Deputy Wood Construction 10/10/2023 Conditional Approval BRENDAN MORELLI
BUILDING-Rough-Frame 10/16/2023 Approved JUSTIN HAWLEY
Excavation/Setback/Form/Re-Bar 10/16/2023 Approved JUSTIN HAWLEY
Floor/Roof Diaphrgm/Shear Wall 10/16/2023 Approved JUSTIN HAWLEY
Insulation 10/25/2023 Approved MICHAEL LEWIS
Interior/Exterior Lathing 10/25/2023 Approved MICHAEL LEWIS
Drywall Nailing 11/2/2023 Approved MICHAEL LEWIS
Green Building Rough 11/2/2023 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 12/18/2023 SGSOV Not Ready MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 12/29/2023 SGSOV Not Ready MICHAEL LEWIS
Final 2/15/2024 Corrections Issued MICHAEL LEWIS
Footing/Foundation/Slab 2/15/2024 Approved MICHAEL LEWIS
Green Building Final 2/15/2024 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 2/15/2024 SGSOV Approved MICHAEL LEWIS
Smoke Detectors 2/15/2024 Approved MICHAEL LEWIS
Final 3/4/2024 Corrections Issued MICHAEL LEWIS
Final 4/18/2024 OK to Issue CofO MICHAEL LEWIS