6960 N NEWGATE ROAD 91307

Certificate Information: 6960 N NEWGATE ROAD 91307

Application / Permit
22014-10000-04132
Plan Check / Job No.
B22LA16345
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
6'-3"x31' ADDITION TO SIDE OF EXISTING ONE STORY SINGLE FAMILY DEWLLING WITH ATTACHED GARAGE AND INTERIOR REMODEL PER ENGINEERED DESIGN.
Permit Issued
Issued on 8/21/2023
Issuing Office
Valley
Current Status
CofO Issued on 10/25/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/16/2022 APPLICANT
Assigned to Plan Check Engineer 8/18/2022 AUNG SOE
Corrections Issued 8/22/2022 AUNG SOE
Building Plans Picked Up 8/29/2022 APPLICANT
Plan Check Approved 8/11/2023 DANIEL SMILEY
Issued 8/21/2023 APPLICANT
CofO in Progress 10/11/2024 JEFFREY HARTLINE
Permit Finaled 10/25/2024 JOHN JANSON
CofO Issued 10/25/2024 JOHN JANSON
Permit Finaled 10/25/2024 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/1/2023 DINAH GARIN
Grading Pre-Inspection Cleared 6/14/2023 BRIAN MILLER
Roof/Waste drainage to street Cleared 7/7/2023 CARLOS AGUILERA

Contact Information

Architect Hurtado,, Jesus; Lic. No.: C29969 1310 S MCDONNELL AVENUE      LOS ANGELES, CA 90022
Contractor Outlaw Construction; Lic. No.: 615612-B 19234 BENSION DRIVE      SANTA CLARITA, CA 91350
Engineer Medina,, Ferdinand Casaclang; Lic. No.: C88007 1051 S HOLT AVE APT F      LOS ANGELES, CA 90035

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/13/2023 Approved JEFFREY HARTLINE
Deputy Drilled-In Anchors 9/19/2023 Conditional Approval CHRIS CHRISTENSEN
Excavation/Setback/Form/Re-Bar 10/13/2023 Corrections Issued CHRIS CHRISTENSEN
Excavation/Setback/Form/Re-Bar 10/17/2023 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 12/6/2023 Not Ready for Inspection JEFFREY HARTLINE
ELECTRICAL-Rough 12/6/2023 Corrections Issued JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 12/6/2023 Approved JEFFREY HARTLINE
HVAC-Rough 12/6/2023 Not Ready for Inspection JEFFREY HARTLINE
PLUMBING-Rough 12/6/2023 Corrections Issued JEFFREY HARTLINE
ELECTRICAL-Rough 12/20/2023 Approved JEFFREY HARTLINE
HVAC-Rough 12/20/2023 Approved JEFFREY HARTLINE
Interior/Exterior Lathing 12/20/2023 Approved JEFFREY HARTLINE
PLUMBING-Rough 12/20/2023 Approved JEFFREY HARTLINE
BUILDING-Rough-Frame 12/27/2023 Conditional Approval CHRIS CHRISTENSEN
Green Building Rough 12/27/2023 Approved CHRIS CHRISTENSEN
Insulation 12/27/2023 Approved CHRIS CHRISTENSEN
Drywall Nailing 1/17/2024 Approved JEFFREY HARTLINE
BUILDING-Rough-Frame 5/16/2024 Approved JEFFREY HARTLINE
Final 5/16/2024 Corrections Issued JEFFREY HARTLINE
Green Building Final 5/16/2024 Approved JEFFREY HARTLINE
SGSOV-Seismic Gas S/O Valve 5/16/2024 SGSOV Not Ready JEFFREY HARTLINE
Smoke Detectors 5/16/2024 Approved JEFFREY HARTLINE
Final 9/11/2024 Corrections Issued CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 9/11/2024 SGSOV Not Ready CHRIS CHRISTENSEN
Final 10/10/2024 OK to Issue CofO JEFFREY HARTLINE
SGSOV-Seismic Gas S/O Valve 10/10/2024 SGSOV Approved JEFFREY HARTLINE