2521 E MALABAR ST 90033
Certificate Information: 2521 E MALABAR ST 90033
- Application / Permit
- 22014-10000-04105
- Plan Check / Job No.
- B22LA16198
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: One story addition to (E) SFD. Add a new bathroom and laundry room; ALL WORK DONE PER WFPP
- Permit Issued
- Issued on 9/14/2022
- Issuing Office
- Current Status
- Issued on 9/14/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/15/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/16/2022 | KHUONG TRUONG |
| Corrections Issued | 8/17/2022 | KHUONG TRUONG |
| Plan Check Approved | 9/9/2022 | RICARDO RAMIREZ |
| Issued | 9/14/2022 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 8/19/2022 | ELAINE LEI |
| Eng Process Fee Ord 176,300 | Cleared | 8/23/2022 | ELAINE LEI |
| Grading Pre-Inspection | Cleared | 8/30/2022 | KIRK LINKLATER |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/11/2022 | Approved | OSVALDO PARAMO |
| Footing/Foundation/Slab | 10/11/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 10/24/2022 | Partial Approval | OSVALDO PARAMO |
| Footing/Foundation/Slab | 10/24/2022 | Approved | OSVALDO PARAMO |
| PLUMBING-Rough | 10/24/2022 | Partial Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 10/28/2022 | Partial Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 11/4/2022 | Partial Approval | OSVALDO PARAMO |
| Green Building Rough | 11/4/2022 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Rough | 12/12/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| PLUMBING-Rough | 12/12/2022 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Rough | 12/15/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| ELECTRICAL-Rough | 12/19/2022 | Approved | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 12/23/2022 | Approved | OSVALDO PARAMO |
| Wood Frame | 12/28/2022 | Approved | RUBEN SALAS |
| Insulation | 12/30/2022 | Approved | RUBEN SALAS |
| Drywall Nailing | 1/10/2023 | Approved | AMY COLIN |
| Interior/Exterior Lathing | 1/23/2023 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 3/6/2023 | Approved | OSVALDO PARAMO |
| Final | 3/6/2023 | Corrections Issued | OSVALDO PARAMO |
| Green Building Final | 3/6/2023 | Approved | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 3/6/2023 | SGSOV Not Ready | OSVALDO PARAMO |
| Smoke Detectors | 3/6/2023 | Approved | OSVALDO PARAMO |