4048 N VAN HORNE AVE 90032

Certificate Information: 4048 N VAN HORNE AVE 90032

Application / Permit
22014-10000-04100
Plan Check / Job No.
B22LA16194
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan 14'x16' addtion at front of existing one story single family dewlling per engineer design
Permit Issued
Issued on 12/1/2022
Issuing Office
Current Status
Issued on 12/1/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/16/2022 APPLICANT
Assigned to Plan Check Engineer 8/16/2022 AUNG SOE
Corrections Issued 8/17/2022 AUNG SOE
Applicant returned to address corrections 9/21/2022 MINA HABILI
Plan Check Approved 9/26/2022 ZAW HAN
Issued 12/1/2022 APPLICANT

Permit Application Clearance Information

Grading Pre-Inspection Cleared 9/1/2022 KIRK LINKLATER
Roof/Waste drainage to street Cleared 9/3/2022 CHRISTOPHER ROCHA
Sewer availability Cleared 9/3/2022 CHRISTOPHER ROCHA
Eng Process Fee Ord 176,300 Cleared 9/9/2022 CHRISTOPHER ROCHA

Contact Information

Contractor Sanz Construction Inc; Lic. No.: 896113-B 2724 W MAIN STREET      ALHAMBRA, CA 91801
Engineer Chan,, Terence Ka-Hing; Lic. No.: C48893 3579 E FOOTHILL BLVD   #206    PASADENA, CA 91107

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/22/2023 Approved AMY COLIN
PLUMBING-Rough 3/13/2023 Partial Approval AMY COLIN
Wood Frame 3/13/2023 Partial Approval AMY COLIN
Floor/Roof Diaphrgm/Shear Wall 3/20/2023 Partial Approval AMY COLIN
Insulation 3/20/2023 Partial Approval AMY COLIN
BUILDING-Rough-Frame 4/3/2023 Corrections Issued AMY COLIN
ELECTRICAL-Rough 4/3/2023 Approved AMY COLIN
Green Building Rough 4/3/2023 Not Ready for Inspection AMY COLIN
PLUMBING-Rough 4/3/2023 Approved AMY COLIN
Insulation 4/6/2023 Not Ready for Inspection RUBEN SALAS
Insulation 4/7/2023 Approved RUBEN SALAS
Drywall Nailing 4/13/2023 Conditional Approval AMY COLIN
Interior/Exterior Lathing 4/13/2023 Partial Approval AMY COLIN
Interior/Exterior Lathing 5/15/2023 Corrections Issued AMY COLIN
BUILDING-Rough-Frame 8/22/2023 Approved AMY COLIN
Final 8/22/2023 Corrections Issued AMY COLIN
Green Building Final 8/22/2023 Approved AMY COLIN
Green Building Rough 8/22/2023 Approved AMY COLIN
SGSOV-Seismic Gas S/O Valve 8/22/2023 SGSOV Not Ready AMY COLIN
Smoke Detectors 8/22/2023 Corrections Issued AMY COLIN
Final 11/16/2023 Corrections Issued ROY SPAULDING
SGSOV-Seismic Gas S/O Valve 11/16/2023 SGSOV Approved ROY SPAULDING
Smoke Detectors 11/16/2023 Approved ROY SPAULDING