144 W 106TH ST 90003
Certificate Information: 144 W 106TH ST 90003
- Application / Permit
- 22014-10000-04086
- Plan Check / Job No.
- B22LA16127
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 36'2"X36'3" ADDN TO EXTEND EX BEDRM W/ CLOSET & NEW REC RM (ACCESSIBLE FROM OUTSIDE ONLY). CONVERT EX PATIO COVER ENCLOSURE INTO BEDRM W/ BATH. ALL WORK PER ENGR.
- Permit Issued
- Issued on 9/27/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/7/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/12/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/15/2022 | KHUONG TRUONG |
| Corrections Issued | 8/16/2022 | KHUONG TRUONG |
| Building Plans Picked Up | 8/19/2022 | APPLICANT |
| Applicant returned to address corrections | 9/21/2022 | HAYATO TSUCHIYA |
| Issued | 9/27/2022 | APPLICANT |
| CofO in Progress | 7/4/2025 | JOHN KLARIN |
| Permit Finaled | 7/7/2025 | ANSON MAGLASANG |
| CofO Issued | 7/7/2025 | ANSON MAGLASANG |
| Permit Finaled | 7/7/2025 | ANSON MAGLASANG |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 8/20/2022 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 8/24/2022 | JEANETTE VONG |
| Low Impact Development | Cleared | 9/13/2022 | ROGELIO CORTES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Barragan,, Pedro; Lic. No.: C90531 | 329 N HUBBARD AVE SAN FERNANDO, CA 91340 |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/6/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Footing/Foundation/Slab | 4/20/2023 | Partial Inspection | JAMES CHAVEZ |
| Pre-Inspection | 4/20/2023 | Partial Inspection | JAMES CHAVEZ |
| Footing/Foundation/Slab | 7/11/2023 | Partial Inspection | JAMES CHAVEZ |
| Footing/Foundation/Slab | 7/31/2023 | Partial Approval | JAMES CHAVEZ |
| Footing/Foundation/Slab | 8/10/2023 | Partial Approval | JAMES CHAVEZ |
| Footing/Foundation/Slab | 8/16/2023 | Approved | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 10/16/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Pre-Inspection | 10/16/2023 | Partial Inspection | JAMES CHAVEZ |
| Wood Frame | 10/16/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 11/30/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Green Building Rough | 11/30/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Wood Frame | 11/30/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 1/17/2024 | Corrections Issued | JAMES CHAVEZ |
| Green Building Rough | 1/17/2024 | Not Ready for Inspection | JAMES CHAVEZ |
| Pre-Inspection | 4/23/2024 | Approved | BEN MOLSTAD |
| Special/Order Compliance | 6/3/2024 | Corrections Issued | JAMES CHAVEZ |
| Insulation | 8/15/2024 | Partial Approval | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 8/30/2024 | Not Ready for Inspection | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 8/30/2024 | Approved | BARRY HACHE |
| Green Building Rough | 8/30/2024 | Not Ready for Inspection | BARRY HACHE |
| ELECTRICAL-Rough | 10/8/2024 | Corrections Issued | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 10/8/2024 | Corrections Issued | BARRY HACHE |
| HVAC-Rough | 10/8/2024 | Corrections Issued | BARRY HACHE |
| PLUMBING-Rough | 10/8/2024 | Corrections Issued | BARRY HACHE |
| ELECTRICAL-Rough | 10/15/2024 | Approved | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 10/15/2024 | Approved | BARRY HACHE |
| HVAC-Rough | 10/15/2024 | Approved | BARRY HACHE |
| PLUMBING-Rough | 10/15/2024 | Corrections Issued | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2024 | Approved | BEN MOLSTAD |
| PLUMBING-Rough | 10/17/2024 | Corrections Issued | BEN MOLSTAD |
| PLUMBING-Rough | 11/1/2024 | Corrections Issued | BEN MOLSTAD |
| BUILDING-Rough-Frame | 11/12/2024 | Approved | BEN MOLSTAD |
| Green Building Rough | 11/12/2024 | Approved | BEN MOLSTAD |
| PLUMBING-Rough | 11/12/2024 | Approved | BEN MOLSTAD |
| Interior/Exterior Lathing | 11/25/2024 | Corrections Issued | BEN MOLSTAD |
| Interior/Exterior Lathing | 11/27/2024 | Partial Approval | BEN MOLSTAD |
| Insulation | 12/11/2024 | Approved | ANTHONY EGSON |
| Drywall Nailing | 1/7/2025 | Approved | BEN MOLSTAD |
| Interior/Exterior Lathing | 2/6/2025 | Partial Approval | BEN MOLSTAD |
| Shower Pan | 2/10/2025 | Approved | BEN MOLSTAD |
| ELECTRICAL-Final | 4/29/2025 | Corrections Issued | BEN MOLSTAD |
| Final | 4/29/2025 | Corrections Issued | BEN MOLSTAD |
| HVAC-Final | 4/29/2025 | Corrections Issued | BEN MOLSTAD |
| PLUMBING-Final | 4/29/2025 | Corrections Issued | BEN MOLSTAD |
| ELECTRICAL-Final | 5/29/2025 | Corrections Issued | JOHN KLARIN |
| HVAC-Final | 5/29/2025 | Corrections Issued | JOHN KLARIN |
| PLUMBING-Final | 5/29/2025 | Not Ready for Inspection | JOHN KLARIN |
| ELECTRICAL-Final | 6/5/2025 | Corrections Issued | BEN MOLSTAD |
| HVAC-Final | 6/5/2025 | Corrections Issued | BEN MOLSTAD |
| ELECTRICAL-Final | 6/24/2025 | Corrections Issued | JOHN KLARIN |
| Final | 6/24/2025 | Corrections Issued | JOHN KLARIN |
| Green Building Final | 6/24/2025 | Corrections Issued | JOHN KLARIN |
| HVAC-Final | 6/24/2025 | Approved | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 6/24/2025 | SGSOV Approved | JOHN KLARIN |
| Smoke Detectors | 6/24/2025 | Corrections Issued | JOHN KLARIN |
| ELECTRICAL-Final | 6/26/2025 | No Access for Inspection | BEN MOLSTAD |
| ELECTRICAL-Final | 6/27/2025 | Approved | JOHN KLARIN |
| Final | 6/27/2025 | Not Ready for Inspection | JOHN KLARIN |
| Green Building Final | 6/27/2025 | Approved | JOHN KLARIN |
| Smoke Detectors | 6/27/2025 | Approved | JOHN KLARIN |
| Final | 7/3/2025 | OK to Issue CofO | JOHN KLARIN |