751 W 110TH ST 90044
Certificate Information: 751 W 110TH ST 90044
- Application / Permit
- 22014-10000-04069
- Plan Check / Job No.
- B22LA16087
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 25'-4" X 28'-5" IRREG SHAPED ADDITION AND REMODEL TO SINGLE FAMILY DWELLING TO ADD NEW BEDROOM, BATHROOM, AND CLOSET.
- Permit Issued
- Issued on 11/8/2022
- Issuing Office
- Current Status
- CofO Issued on 5/24/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/16/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/19/2022 | JEROME MAGAT PALMA |
| Corrections Issued | 8/20/2022 | JEROME MAGAT PALMA |
| Applicant returned to address corrections | 10/13/2022 | JEROME MAGAT PALMA |
| Plan Check Approved | 11/4/2022 | JEROME MAGAT PALMA |
| Issued | 11/8/2022 | APPLICANT |
| CofO in Progress | 5/24/2023 | JAMES CHAVEZ |
| Permit Finaled | 5/24/2023 | ANSON MAGLASANG |
| CofO Issued | 5/24/2023 | ANSON MAGLASANG |
| Permit Finaled | 5/24/2023 | ANSON MAGLASANG |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 10/14/2022 | AMAAN MALIK |
| Sewer availability | Cleared | 10/19/2022 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 10/25/2022 | AMAAN MALIK |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Grigoryan,, Souren; Lic. No.: C93320 | 6506 TEESDALE AVE NORTH HOLLYWOOD, CA 91606 |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/29/2022 | Approved | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 1/24/2023 | Approved | JAMES CHAVEZ |
| Footing/Foundation/Slab | 1/24/2023 | Approved | JAMES CHAVEZ |
| Underground Mechanical | 1/24/2023 | Approved | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 1/25/2023 | Approved | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 1/27/2023 | Approved | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 3/9/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/9/2023 | Partial Approval | JAMES CHAVEZ |
| Green Building Rough | 3/9/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Deputy Wood Construction | 3/13/2023 | Conditional Approval | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/14/2023 | Approved | JAMES CHAVEZ |
| PLUMBING-Rough | 3/14/2023 | Approved | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 3/15/2023 | Partial Inspection | JAMES CHAVEZ |
| Deputy Wood Construction | 3/15/2023 | Conditional Approval | JAMES CHAVEZ |
| ELECTRICAL-Rough | 3/15/2023 | Approved | JAMES CHAVEZ |
| HVAC-Rough | 3/15/2023 | Approved | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 3/17/2023 | Approved | JAMES CHAVEZ |
| Green Building Rough | 3/17/2023 | Approved | JAMES CHAVEZ |
| Shower Pan | 3/17/2023 | Approved | JAMES CHAVEZ |
| Insulation | 3/20/2023 | Approved | JAMES CHAVEZ |
| Drywall Nailing | 3/30/2023 | Approved | JAMES CHAVEZ |
| Interior/Exterior Lathing | 3/30/2023 | Approved | JAMES CHAVEZ |
| Final | 4/25/2023 | Corrections Issued | JAMES CHAVEZ |
| Green Building Final | 4/25/2023 | Corrections Issued | JAMES CHAVEZ |
| SGSOV-Seismic Gas S/O Valve | 4/25/2023 | SGSOV Not Ready | JAMES CHAVEZ |
| Smoke Detectors | 4/25/2023 | Corrections Issued | JAMES CHAVEZ |
| Final | 5/2/2023 | Corrections Issued | JAMES CHAVEZ |
| Green Building Final | 5/2/2023 | Approved | JAMES CHAVEZ |
| SGSOV-Seismic Gas S/O Valve | 5/2/2023 | SGSOV Approved | JAMES CHAVEZ |
| Smoke Detectors | 5/2/2023 | Approved | JAMES CHAVEZ |
| Final | 5/23/2023 | OK to Issue CofO | JAMES CHAVEZ |
| Service/Power Release | 5/23/2023 | Approved | JAMES CHAVEZ |