1368 W 27TH ST 90731

Certificate Information: 1368 W 27TH ST 90731

Application / Permit
22014-10000-04015
Plan Check / Job No.
B22LA15776
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan ADD TO AND CONVERT STORAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) (GARAGE TO REMAIN)
Permit Issued
Issued on 1/15/2024
Issuing Office
Current Status
CofO Issued on 9/5/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/9/2022 APPLICANT
Assigned to Plan Check Engineer 8/12/2022 SELLA BENYAMIN
Corrections Issued 8/15/2022 SELLA BENYAMIN
Applicant returned to address corrections 8/22/2022 SELLA BENYAMIN
Applicant returned to address corrections 1/4/2024 SELLA BENYAMIN
Plan Check Approved 1/9/2024 SELLA BENYAMIN
No Progress 1/12/2024 SELLA BENYAMIN
Plan Check Approved 1/12/2024 SELLA BENYAMIN
Issued 1/15/2024 APPLICANT
CofO in Progress 9/5/2024 JOSEPH MCGARRY
Permit Finaled 9/5/2024 ANSON MAGLASANG
CofO Issued 9/5/2024 ANSON MAGLASANG
Permit Finaled 9/5/2024 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 9/2/2022 JOSE HERNANDEZ
Roof/Waste drainage to street Cleared 9/2/2022 JOSE HERNANDEZ
Eng Process Fee Ord 176,300 Cleared 9/9/2022 JOSE HERNANDEZ
Sewer availability Cleared 9/9/2022 JOSE HERNANDEZ
Coastal Zone Cleared 1/3/2024 DAVID URITA
Specific Plan Cleared 1/3/2024 DAVID URITA
Grading Pre-Inspection Cleared 3/7/2024 SELLA BENYAMIN

Contact Information

Contractor Atlas Builders And Development Inc; Lic. No.: 1064138-B       ,
Contractor Atlas Builders; Lic. No.: 1064138-B       ,
Engineer Mezey,, Steven William; Lic. No.: S2665 14017 HARTSOOK ST      SHERMAN OAKS, CA 91423

Inspector Information

JOSEPH MCGARRY, (310) 732-4559 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/16/2024 Conditional Approval ANSON MAGLASANG
Excavation/Setback/Form/Re-Bar 2/20/2024 Not Ready for Inspection JAMES CHAVEZ
Footing/Foundation/Slab 2/20/2024 Not Ready for Inspection JAMES CHAVEZ
Footing/Foundation/Slab 2/22/2024 Not Ready for Inspection JAMES CHAVEZ
Excavation/Setback/Form/Re-Bar 2/26/2024 Corrections Issued JAMES CHAVEZ
ELECTRICAL-Rough 4/22/2024 Not Ready for Inspection ANSON MAGLASANG
Floor/Roof Diaphrgm/Shear Wall 4/22/2024 Conditional Approval ANSON MAGLASANG
Wood Frame 4/22/2024 Not Ready for Inspection ANSON MAGLASANG
ELECTRICAL-Rough 5/6/2024 Not Ready for Inspection JAMES CHAVEZ
Floor/Roof Diaphrgm/Shear Wall 5/6/2024 Partial Approval JAMES CHAVEZ
PLUMBING-Rough 5/6/2024 Not Ready for Inspection JAMES CHAVEZ
Underground Mechanical 5/6/2024 Not Ready for Inspection JAMES CHAVEZ
Wood Frame 5/6/2024 Corrections Issued JAMES CHAVEZ
Floor/Roof Diaphrgm/Shear Wall 5/13/2024 Not Ready for Inspection ANSON MAGLASANG
Wood Frame 5/13/2024 Corrections Issued ANSON MAGLASANG
ELECTRICAL-Rough 5/16/2024 Approved JAMES CHAVEZ
Floor/Roof Diaphrgm/Shear Wall 5/16/2024 Partial Approval JAMES CHAVEZ
HVAC-Rough 5/16/2024 Approved JAMES CHAVEZ
PLUMBING-Rough 5/16/2024 Approved JAMES CHAVEZ
Wood Frame 5/16/2024 Approved JAMES CHAVEZ
Insulation 5/20/2024 Approved ANSON MAGLASANG
Interior/Exterior Lathing 5/20/2024 Corrections Issued ANSON MAGLASANG
Drywall Nailing 5/23/2024 Partial Approval JAMES CHAVEZ
Shower Pan 5/23/2024 Approved JAMES CHAVEZ
ELECTRICAL-Rough 5/31/2024 Approved JAMES CHAVEZ
Interior/Exterior Lathing 5/31/2024 Approved JAMES CHAVEZ
Sewer 5/31/2024 Not Ready for Inspection JAMES CHAVEZ
Underground Mechanical 5/31/2024 Not Ready for Inspection JAMES CHAVEZ
Gas Test 6/11/2024 Partial Approval JAMES CHAVEZ
Sewer 6/11/2024 Partial Approval JAMES CHAVEZ
Underground Mechanical 6/11/2024 Approved JAMES CHAVEZ
Drywall Nailing 6/18/2024 Approved ANSON MAGLASANG
Interior/Exterior Lathing 6/18/2024 Partial Approval ANSON MAGLASANG
Sewer 6/18/2024 Approved ANSON MAGLASANG
SGSOV-Seismic Gas S/O Valve 8/1/2024 SGSOV Not Ready ANSON MAGLASANG
Gas Test 8/2/2024 Approved JOSEPH MCGARRY
Pre-Inspection 8/2/2024 Approved JOSEPH MCGARRY
BUILDING-Rough-Frame 8/9/2024 Approved JOSEPH MCGARRY
Final 8/9/2024 Corrections Issued JOSEPH MCGARRY
Footing/Foundation/Slab 8/9/2024 Approved JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 8/9/2024 SGSOV Approved JOSEPH MCGARRY
Smoke Detectors 8/9/2024 Approved JOSEPH MCGARRY
Final 9/4/2024 OK to Issue CofO JOSEPH MCGARRY