4635 N NOBLE AVE 91403

Certificate Information: 4635 N NOBLE AVE 91403

Application / Permit
22014-10000-03993
Plan Check / Job No.
B22LA15673
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: MAJOR REMODEL AND ADDITION TO (E) 1-STORY SINGLE FAMILY DWELLING TO CREATE 2-STORY SINGLE FAMILY DWELLING WITH ATTAHCED GARAGE
Permit Issued
Issued on 3/9/2023
Issuing Office
Current Status
CofO Issued on 3/13/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/9/2022 APPLICANT
Assigned to Plan Check Engineer 8/18/2022 DANIEL YIP
Corrections Issued 8/19/2022 DANIEL YIP
Quality Review Completed 8/24/2022 GARO TELMI
Applicant returned to address corrections 11/10/2022 DANIEL YIP
Plan Check Approved 1/3/2023 DANIEL YIP
Issued 3/9/2023 APPLICANT
CofO in Progress 2/10/2025 JACK KARGODORIAN
CofO in Progress 2/14/2025 JUAN VALENZUELA
CofO in Progress 2/18/2025 JACK KARGODORIAN
CofO in Progress 3/12/2025 JUAN VALENZUELA
Permit Finaled 3/13/2025 RUBEN SALAS
CofO Issued 3/13/2025 RUBEN SALAS
Permit Finaled 3/13/2025 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/21/2022 CARLOS AGUILERA
Sewer availability Cleared 9/21/2022 CARLOS AGUILERA
Hydrant and Access approval Cleared 10/9/2022 RUEL COLE
Low Impact Development Cleared 10/18/2022 LUIS LUVANO
Roof/Waste drainage to street Cleared 10/25/2022 JOHN LIN

Contact Information

Contractor Owner-Builder       ,
Engineer Gosen,, James W; Lic. No.: C43590 15315 BLEDSOE ST      SYLMAR, CA 91342
Engineer Gosen,, James W; Lic. No.: NA43590       ,

Inspector Information

RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/13/2023 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 3/13/2023 Corrections Issued THOMAS FINNILA
PLUMBING-Rough 3/14/2023 Not Ready for Inspection THOMAS FINNILA
Footing/Foundation/Slab 3/16/2023 Corrections Issued THOMAS FINNILA
PLUMBING-Rough 3/16/2023 Partial Approval THOMAS FINNILA
Deputy Drilled-In Anchors 3/20/2023 Conditional Approval THOMAS FINNILA
Footing/Foundation/Slab 3/20/2023 Corrections Issued THOMAS FINNILA
Footing/Foundation/Slab 4/18/2023 Corrections Issued THOMAS FINNILA
Deputy Drilled-In Anchors 4/19/2023 Conditional Approval DAVID MATSON
Footing/Foundation/Slab 4/24/2023 Approved THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 5/2/2023 Partial Approval THOMAS FINNILA
Deputy Wood Construction 5/26/2023 Conditional Approval MICHAEL SMITH
ELECTRICAL-Rough 5/30/2023 Corrections Issued THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 5/30/2023 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 5/30/2023 Approved THOMAS FINNILA
ELECTRICAL-Rough 6/2/2023 Approved THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 6/2/2023 Partial Approval THOMAS FINNILA
HVAC-Rough 6/2/2023 Not Ready for Inspection THOMAS FINNILA
HVAC-Rough 6/7/2023 Approved THOMAS FINNILA
BUILDING-Rough-Frame 6/20/2023 Partial Approval THOMAS FINNILA
Green Building Rough 6/20/2023 Not Ready for Inspection THOMAS FINNILA
BUILDING-Rough-Frame 7/3/2023 Corrections Issued THOMAS FINNILA
Green Building Rough 7/3/2023 Approved THOMAS FINNILA
Interior/Exterior Lathing 7/3/2023 Not Ready for Inspection THOMAS FINNILA
Insulation 7/6/2023 Corrections Issued MISAEL ESPARZA
Interior/Exterior Lathing 7/6/2023 Partial Approval MISAEL ESPARZA
BUILDING-Rough-Frame 7/10/2023 Corrections Issued THOMAS FINNILA
Insulation 7/10/2023 Conditional Approval THOMAS FINNILA
Drywall Nailing 7/14/2023 Approved THOMAS FINNILA
Interior/Exterior Lathing 7/14/2023 Approved THOMAS FINNILA
Underground Mechanical 10/12/2023 Partial Approval MICHEL ABAJAN
ELECTRICAL-Final 4/18/2024 Corrections Issued THOMAS FINNILA
Gas Test 4/18/2024 Approved THOMAS FINNILA
HVAC-Final 4/18/2024 Corrections Issued THOMAS FINNILA
PLUMBING-Final 4/18/2024 Approved THOMAS FINNILA
BUILDING-Rough-Frame 5/3/2024 Approved THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 5/3/2024 SGSOV Not Ready THOMAS FINNILA
Smoke Detectors 5/3/2024 Approved THOMAS FINNILA
HVAC-Final 7/15/2024 Approved JACK KARGODORIAN
Final 1/15/2025 Corrections Issued MISAEL ESPARZA
Green Building Final 1/15/2025 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 1/15/2025 SGSOV Approved MISAEL ESPARZA
Final 1/17/2025 Corrections Issued JACK KARGODORIAN
PLUMBING-Final 1/21/2025 Approved JACK KARGODORIAN
Final 2/10/2025 Not Ready for Inspection JACK KARGODORIAN
Service/Power Release 2/10/2025 Approved JACK KARGODORIAN
Final 2/18/2025 Corrections Issued JACK KARGODORIAN
Final 3/12/2025 OK to Issue CofO JUAN VALENZUELA