5022 E ALMADEN DR 90042

Certificate Information: 5022 E ALMADEN DR 90042

Application / Permit
22014-10000-03990
Plan Check / Job No.
B22LA15670
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION AND REMODEL TO (E) SFD
Permit Issued
Issued on 11/21/2022
Issuing Office
Metro
Current Status
CofO Issued on 5/28/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/9/2022 APPLICANT
Assigned to Plan Check Engineer 8/15/2022 LUISANGEL VALENZUELA
Corrections Issued 8/16/2022 LUISANGEL VALENZUELA
Plan Check Approved 9/15/2022 KHUONG TRUONG
Issued 11/21/2022 APPLICANT
CofO in Progress 5/24/2023 CRAIG VAUGHAN
Permit Finaled 5/28/2023 DEROLD HAUFF
CofO Issued 5/28/2023 DEROLD HAUFF
Permit Finaled 5/28/2023 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 8/19/2022 KIRK LINKLATER
Eng Process Fee Ord 176,300 Cleared 8/22/2022 JEANETTE VONG
Roof/Waste drainage to street Cleared 8/22/2022 JEANETTE VONG
Sewer availability Cleared 8/22/2022 JEANETTE VONG

Contact Information

Contractor L A Builder Construction Inc; Lic. No.: 933468-B 7301 ANATOLA AVE      VAN NUYS, CA 91406
Engineer Kim,, Hong Kook; Lic. No.: C64529 3600 WILSHIRE BLVD STE 1903      LOS ANGELES, CA 90010

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/6/2022 Approved SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 12/30/2022 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 1/11/2023 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Rough 1/11/2023 Approved CRAIG VAUGHAN
HVAC-Rough 1/11/2023 Approved CRAIG VAUGHAN
Wood Frame 1/11/2023 Partial Approval CRAIG VAUGHAN
Deputy Drilled-In Anchors 1/19/2023 Conditional Approval CRAIG VAUGHAN
Interior/Exterior Lathing 1/20/2023 Not Ready for Inspection CRAIG VAUGHAN
Wood Frame 1/20/2023 Approved CRAIG VAUGHAN
Insulation 1/25/2023 Approved KATHRYN BUTTERWORTH
Interior/Exterior Lathing 1/25/2023 Partial Approval KATHRYN BUTTERWORTH
Drywall Nailing 1/30/2023 Approved CRAIG VAUGHAN
Green Building Rough 1/30/2023 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 3/29/2023 Approved KATHRYN BUTTERWORTH
Final 3/29/2023 Corrections Issued KATHRYN BUTTERWORTH
Green Building Final 3/29/2023 Approved KATHRYN BUTTERWORTH
SGSOV-Seismic Gas S/O Valve 3/29/2023 SGSOV Approved KATHRYN BUTTERWORTH
Smoke Detectors 3/29/2023 Approved KATHRYN BUTTERWORTH
Final 4/6/2023 Corrections Issued ALIZAH MAYAGOITIA
ELECTRICAL-Final 5/23/2023 Approved CRAIG VAUGHAN
Final 5/23/2023 OK to Issue CofO CRAIG VAUGHAN
HVAC-Final 5/23/2023 Approved CRAIG VAUGHAN
PLUMBING-Final 5/23/2023 Approved CRAIG VAUGHAN