10944-10946 W REGENT ST 90034
Certificate Information: 10944-10946 W REGENT ST 90034
- Application / Permit
- 22014-10000-03971
- Plan Check / Job No.
- B22LA15600
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- *EPLAN* CONVERSION OF (E) GARAGE/STORAGE TO ADU AND ADDITION OF (170 SF) TO ADU PER LAMC 12.22A.33(c) AND (e) AND ADDITION (110 SF) TO (E) DUPLEX UNIT 1.
- Permit Issued
- Issued on 10/16/2022
- Issuing Office
- Current Status
- CofO Issued on 11/8/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/8/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/15/2022 | VIVIAN LAO |
| Corrections Issued | 8/16/2022 | VIVIAN LAO |
| Quality Review Completed | 8/19/2022 | GARO TELMI |
| Applicant returned to address corrections | 9/20/2022 | VIVIAN LAO |
| Plan Check Approved | 10/3/2022 | VIVIAN LAO |
| Issued | 10/16/2022 | APPLICANT |
| CofO in Progress | 11/7/2023 | JESUS PINEDA |
| Permit Finaled | 11/8/2023 | DANIEL ORRANTE |
| CofO Issued | 11/8/2023 | DANIEL ORRANTE |
| Permit Finaled | 11/8/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/29/2022 | JENSON LEE |
| Grading Pre-Inspection | Cleared | 8/30/2022 | KIRK LINKLATER |
| Sewer availability | Cleared | 8/30/2022 | JENSON LEE |
| Address approval | Cleared | 9/7/2022 | JENSON LEE |
| Roof/Waste drainage to street | Cleared | 9/7/2022 | JENSON LEE |
| Specific Plan | Cleared | 9/13/2022 | ROBERT SANCHEZ |
| Miscellaneous | Cleared | 9/15/2022 | JENSON LEE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Wassef,, Mena; Lic. No.: C84979 | 28131 VALERIO CT VALENCIA, CA 91354 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/15/2022 | Partial Approval | JOHNNY MIRANDA |
| Excavation/Setback/Form/Re-Bar | 2/16/2023 | Not Ready for Inspection | HERBERT GIRON |
| Excavation/Setback/Form/Re-Bar | 3/13/2023 | Corrections Issued | CLAYTON GRAHAM |
| Footing/Foundation/Slab | 3/13/2023 | Corrections Issued | CLAYTON GRAHAM |
| Underground Mechanical | 3/13/2023 | Approved | CLAYTON GRAHAM |
| Deputy Drilled-In Anchors | 3/17/2023 | Conditional Approval | JOHNNY MIRANDA |
| Excavation/Setback/Form/Re-Bar | 3/20/2023 | Approved | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 3/20/2023 | Partial Approval | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 6/2/2023 | Corrections Issued | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 6/2/2023 | Corrections Issued | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 6/2/2023 | Approved | JOHNNY MIRANDA |
| Green Building Rough | 6/2/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| HVAC-Rough | 6/2/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| PLUMBING-Rough | 6/2/2023 | Approved | JOHNNY MIRANDA |
| Wood Frame | 6/2/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 6/9/2023 | Approved | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 6/9/2023 | Approved | JESUS PINEDA |
| HVAC-Rough | 6/9/2023 | Approved | JESUS PINEDA |
| Wood Frame | 6/9/2023 | Approved | JESUS PINEDA |
| BUILDING-Rough-Frame | 6/14/2023 | Approved | JOHNNY MIRANDA |
| Green Building Rough | 6/14/2023 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 6/14/2023 | Partial Approval | JOHNNY MIRANDA |
| Insulation | 6/23/2023 | Approved | JOHNNY MIRANDA |
| Shower Pan | 6/23/2023 | Approved | JOHNNY MIRANDA |
| Drywall Nailing | 6/30/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| Drywall Nailing | 7/10/2023 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 7/10/2023 | Approved | JESUS PINEDA |
| ELECTRICAL-Final | 8/28/2023 | Partial Approval | JESUS PINEDA |
| Final | 8/28/2023 | Corrections Issued | JESUS PINEDA |
| Footing/Foundation/Slab | 8/28/2023 | Approved | JESUS PINEDA |
| Green Building Final | 8/28/2023 | Approved | JESUS PINEDA |
| HVAC-Final | 8/28/2023 | Partial Approval | JESUS PINEDA |
| PLUMBING-Final | 8/28/2023 | Corrections Issued | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 8/28/2023 | SGSOV Approved | JESUS PINEDA |
| Smoke Detectors | 8/28/2023 | Partial Approval | JESUS PINEDA |
| Final | 9/11/2023 | Corrections Issued | JESUS PINEDA |
| Smoke Detectors | 9/11/2023 | Approved | JESUS PINEDA |
| ELECTRICAL-Final | 11/7/2023 | Approved | JESUS PINEDA |
| Final | 11/7/2023 | OK to Issue CofO | JESUS PINEDA |
| HVAC-Final | 11/7/2023 | Approved | JESUS PINEDA |
| PLUMBING-Final | 11/7/2023 | Approved | JESUS PINEDA |
| Service/Power Release | 11/7/2023 | Approved | JESUS PINEDA |