3315 1/2 N SUNNYNOOK DR 90039

Certificate Information: 3315 1/2 N SUNNYNOOK DR 90039

Application / Permit
22014-10000-03946
Plan Check / Job No.
B22LA11283
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED GROUND FLOOR ADDIITON AND SECOND FLOOR ADDITION TO AN EXISTING 1-STORY GARAGE TO CREATE A TWO STORY ACCESSORY DWELLING UNIT PER ODINANCE.
Permit Issued
Issued on 11/18/2023
Issuing Office
Current Status
CofO Issued on 2/23/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/1/2022 APPLICANT
Assigned to Plan Check Engineer 7/28/2022 MICHAEL LOPEZ
Corrections Issued 8/5/2022 MICHAEL LOPEZ
Quality Review Completed 8/12/2022 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 8/3/2023 MICHAEL LOPEZ
Applicant returned to address corrections 8/15/2023 MICHAEL LOPEZ
Applicant returned to address corrections 10/16/2023 MICHAEL LOPEZ
Applicant returned to address corrections 11/7/2023 MICHAEL LOPEZ
Applicant returned to address corrections 11/17/2023 MICHAEL LOPEZ
Plan Check Approved 11/17/2023 MICHAEL LOPEZ
Issued 11/18/2023 APPLICANT
CofO in Progress 2/18/2025 THOMAS LOGRASSO
Permit Finaled 2/23/2025 DEROLD HAUFF
CofO Issued 2/23/2025 DEROLD HAUFF
Permit Finaled 2/23/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/21/2023 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 8/21/2023 WALLIE JONG
Sewer availability Cleared 8/21/2023 WALLIE JONG
ZI Cleared 8/23/2023 NATHAN ROMINE
Roof/Waste drainage to street Cleared 8/27/2023 ADRIAN SANCHEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Mamoyac,, Eulogio R; Lic. No.: C33294 5191 LENA DR      LA PALMA, CA 90623

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/7/2024 Partial Approval THOMAS LOGRASSO
Sewer 5/7/2024 Approved THOMAS LOGRASSO
Excavation/Setback/Form/Re-Bar 5/13/2024 Not Ready for Inspection THOMAS LOGRASSO
Excavation/Setback/Form/Re-Bar 5/15/2024 Corrections Issued THOMAS LOGRASSO
Deputy Drilled-In Anchors 5/17/2024 Conditional Approval CHARLES BOGHOSKHAN
Floor/Roof Diaphrgm/Shear Wall 6/6/2024 Conditional Approval THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 6/12/2024 Not Ready for Inspection THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 6/20/2024 Corrections Issued JOSEPH MCGARRY
ELECTRICAL-Rough 7/2/2024 Approved JOSEPH MCGARRY
Excavation/Setback/Form/Re-Bar 7/2/2024 Approved JOSEPH MCGARRY
HVAC-Rough 7/2/2024 Approved JOSEPH MCGARRY
PLUMBING-Rough 7/2/2024 Approved JOSEPH MCGARRY
BUILDING-Rough-Frame 8/26/2024 Corrections Issued THOMAS LOGRASSO
Deputy Wood Construction 8/27/2024 Conditional Approval THOMAS LOGRASSO
Insulation 9/16/2024 Conditional Approval THOMAS LOGRASSO
Interior/Exterior Lathing 9/16/2024 Partial Approval THOMAS LOGRASSO
Drywall Nailing 10/2/2024 Corrections Issued BRENDAN MORELLI
Drywall Nailing 10/7/2024 Not Ready for Inspection THOMAS LOGRASSO
Drywall Nailing 10/15/2024 Conditional Approval THOMAS LOGRASSO
Interior/Exterior Lathing 10/31/2024 Approved ANTHONY RAMOS
Shower Pan 10/31/2024 Approved ANTHONY RAMOS
Excavation/Setback/Form/Re-Bar 12/30/2024 Not Ready for Inspection THOMAS LOGRASSO
Final 1/16/2025 Partial Inspection THOMAS LOGRASSO
Footing/Foundation/Slab 1/27/2025 Approved THOMAS LOGRASSO
ELECTRICAL-Final 2/7/2025 Corrections Issued THOMAS LOGRASSO
HVAC-Final 2/7/2025 Corrections Issued THOMAS LOGRASSO
PLUMBING-Final 2/7/2025 Conditional Approval THOMAS LOGRASSO
BUILDING-Rough-Frame 2/14/2025 Approved THOMAS LOGRASSO
Final 2/14/2025 OK to Issue CofO THOMAS LOGRASSO
Green Building Final 2/14/2025 Approved THOMAS LOGRASSO
Green Building Rough 2/14/2025 Approved THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 2/14/2025 SGSOV Approved THOMAS LOGRASSO
Smoke Detectors 2/14/2025 Approved THOMAS LOGRASSO