3315 1/2 N SUNNYNOOK DR 90039
Certificate Information: 3315 1/2 N SUNNYNOOK DR 90039
- Application / Permit
- 22014-10000-03946
- Plan Check / Job No.
- B22LA11283
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED GROUND FLOOR ADDIITON AND SECOND FLOOR ADDITION TO AN EXISTING 1-STORY GARAGE TO CREATE A TWO STORY ACCESSORY DWELLING UNIT PER ODINANCE.
- Permit Issued
- Issued on 11/18/2023
- Issuing Office
- Current Status
- CofO Issued on 2/23/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/1/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/28/2022 | MICHAEL LOPEZ |
| Corrections Issued | 8/5/2022 | MICHAEL LOPEZ |
| Quality Review Completed | 8/12/2022 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 8/3/2023 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 8/15/2023 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 10/16/2023 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 11/7/2023 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 11/17/2023 | MICHAEL LOPEZ |
| Plan Check Approved | 11/17/2023 | MICHAEL LOPEZ |
| Issued | 11/18/2023 | APPLICANT |
| CofO in Progress | 2/18/2025 | THOMAS LOGRASSO |
| Permit Finaled | 2/23/2025 | DEROLD HAUFF |
| CofO Issued | 2/23/2025 | DEROLD HAUFF |
| Permit Finaled | 2/23/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/21/2023 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 8/21/2023 | WALLIE JONG |
| Sewer availability | Cleared | 8/21/2023 | WALLIE JONG |
| ZI | Cleared | 8/23/2023 | NATHAN ROMINE |
| Roof/Waste drainage to street | Cleared | 8/27/2023 | ADRIAN SANCHEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mamoyac,, Eulogio R; Lic. No.: C33294 | 5191 LENA DR LA PALMA, CA 90623 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/7/2024 | Partial Approval | THOMAS LOGRASSO |
| Sewer | 5/7/2024 | Approved | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 5/13/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 5/15/2024 | Corrections Issued | THOMAS LOGRASSO |
| Deputy Drilled-In Anchors | 5/17/2024 | Conditional Approval | CHARLES BOGHOSKHAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/6/2024 | Conditional Approval | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 6/12/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 6/20/2024 | Corrections Issued | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 7/2/2024 | Approved | JOSEPH MCGARRY |
| Excavation/Setback/Form/Re-Bar | 7/2/2024 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 7/2/2024 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 7/2/2024 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 8/26/2024 | Corrections Issued | THOMAS LOGRASSO |
| Deputy Wood Construction | 8/27/2024 | Conditional Approval | THOMAS LOGRASSO |
| Insulation | 9/16/2024 | Conditional Approval | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 9/16/2024 | Partial Approval | THOMAS LOGRASSO |
| Drywall Nailing | 10/2/2024 | Corrections Issued | BRENDAN MORELLI |
| Drywall Nailing | 10/7/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Drywall Nailing | 10/15/2024 | Conditional Approval | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 10/31/2024 | Approved | ANTHONY RAMOS |
| Shower Pan | 10/31/2024 | Approved | ANTHONY RAMOS |
| Excavation/Setback/Form/Re-Bar | 12/30/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Final | 1/16/2025 | Partial Inspection | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 1/27/2025 | Approved | THOMAS LOGRASSO |
| ELECTRICAL-Final | 2/7/2025 | Corrections Issued | THOMAS LOGRASSO |
| HVAC-Final | 2/7/2025 | Corrections Issued | THOMAS LOGRASSO |
| PLUMBING-Final | 2/7/2025 | Conditional Approval | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 2/14/2025 | Approved | THOMAS LOGRASSO |
| Final | 2/14/2025 | OK to Issue CofO | THOMAS LOGRASSO |
| Green Building Final | 2/14/2025 | Approved | THOMAS LOGRASSO |
| Green Building Rough | 2/14/2025 | Approved | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 2/14/2025 | SGSOV Approved | THOMAS LOGRASSO |
| Smoke Detectors | 2/14/2025 | Approved | THOMAS LOGRASSO |