5218 N ARGUS DR 90041

Certificate Information: 5218 N ARGUS DR 90041

Application / Permit
22014-10000-03938
Plan Check / Job No.
B22LA15414
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD SECOND FLOOR BEDROOM AND CONVERT POWDER RM TO LAUNDRY ROOM AT SECOND FLOOR.
Permit Issued
Issued on 12/9/2022
Issuing Office
Metro
Current Status
Issued on 12/9/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/4/2022 APPLICANT
Assigned to Plan Check Engineer 8/8/2022 LAWRENCE QUIRANTE
Corrections Issued 8/10/2022 LAWRENCE QUIRANTE
Applicant returned to address corrections 9/27/2022 GEORGE ALVAREZ
Plan Check Approved 9/27/2022 GEORGE ALVAREZ
Issued 12/9/2022 APPLICANT

Permit Application Clearance Information

Sewer availability Cleared 9/11/2022 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 9/21/2022 ADRIAN SANCHEZ
Roof/Waste drainage to street Cleared 9/21/2022 ADRIAN SANCHEZ
Grading Pre-Inspection Cleared 9/27/2022 LAWRENCE QUIRANTE

Contact Information

Architect Gaetos,, Benjamin Abat; Lic. No.: C31227 5129 CASPAR AVENUE      LOS ANGELES, CA 90041
Contractor Owner-Builder       ,
Engineer Hernandez,, Gerardo; Lic. No.: C78115 1426 E STUART AVE      WEST COVINA, CA 91791

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/20/2022 Partial Approval BRIAN SULLIVAN
Footing/Foundation/Slab 12/20/2022 Partial Approval BRIAN SULLIVAN
Deputy Drilled-In Anchors 12/28/2022 Conditional Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 2/1/2023 Not Ready for Inspection BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 2/1/2023 Partial Approval BRIAN SULLIVAN
Green Building Rough 2/1/2023 Not Ready for Inspection BRIAN SULLIVAN
BUILDING-Rough-Frame 5/12/2023 Partial Approval RUBEN SALAS
Green Building Rough 5/12/2023 Not Ready for Inspection RUBEN SALAS
BUILDING-Rough-Frame 6/1/2023 Partial Approval CRAIG VAUGHAN
Green Building Rough 6/1/2023 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Rough 8/7/2023 Approved BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 8/7/2023 Partial Approval BRIAN SULLIVAN
PLUMBING-Rough 8/7/2023 Approved BRIAN SULLIVAN
Insulation 8/21/2023 Corrections Issued JOSH MEISTER
Interior/Exterior Lathing 8/21/2023 Approved JOSH MEISTER
Shower Pan 8/21/2023 Approved JOSH MEISTER
BUILDING-Rough-Frame 8/28/2023 Corrections Issued CRAIG VAUGHAN
Green Building Rough 8/28/2023 Approved CRAIG VAUGHAN
HVAC-Rough 8/28/2023 Not Ready for Inspection CRAIG VAUGHAN
Insulation 8/28/2023 Not Ready for Inspection CRAIG VAUGHAN
BUILDING-Rough-Frame 9/1/2023 Approved CRAIG VAUGHAN
Drywall Nailing 9/7/2023 Approved CRAIG VAUGHAN
Drywall Nailing 9/11/2023 Approved BRENDAN MORELLI
Interior/Exterior Lathing 9/15/2023 Approved BRIAN SULLIVAN
Wood Frame 9/15/2023 Approved BRIAN SULLIVAN