6533 W OLYMPIC PL 90035

Certificate Information: 6533 W OLYMPIC PL 90035

Application / Permit
22014-10000-03931
Plan Check / Job No.
B22LA15389
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) FIRST FLOOR ADDITION OF BEDROOM AND BATH WITH REMODEL OF (E) BATH AND (E) HALLWAY
Permit Issued
Issued on 2/8/2023
Issuing Office
Valley
Current Status
CofO Issued on 3/30/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/3/2022 APPLICANT
Assigned to Plan Check Engineer 8/8/2022 KHUONG TRUONG
Corrections Issued 8/10/2022 KHUONG TRUONG
Building Plans Picked Up 10/12/2022 APPLICANT
Applicant returned to address corrections 12/22/2022 SERGIO MUNIZ
Plan Check Approved 1/10/2023 ALEC MOUSAKHANIAN
Issued 2/8/2023 APPLICANT
CofO in Progress 4/25/2024 RICHARD DOCKUS
Permit Finaled 3/30/2025 DEROLD HAUFF
CofO Issued 3/30/2025 DEROLD HAUFF
Permit Finaled 3/30/2025 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 10/25/2022 CINDY QI
HPOZ Cleared 11/17/2022 MELISSA JONES
Hist. Property Cntrct Mgr Appr Cleared 11/17/2022 MELISSA JONES
Hist. Property Cntrct Mgr Appr Cleared 11/17/2022 MELISSA JONES
Historic monument Cleared 11/17/2022 MELISSA JONES
Eng Process Fee Ord 176,300 Cleared 11/21/2022 CINDY QI
Sewer availability Cleared 11/21/2022 CINDY QI
ZA Case Cleared 12/1/2022 STEVEN WECHSLER

Contact Information

Architect Brettler-Weiner,, Linda Nanette; Lic. No.: C23458 1760 COURTNEY AVE.      LOS ANGELES, CA 90046
Contractor Becker S Enterprises Inc; Lic. No.: 674852-B PO BOX 729      ACTON, CA 93510
Engineer Manalo,, Philip Casis; Lic. No.: S3823 9547 WYSTONE AVE      NORTHRIDGE, CA 91324

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/8/2023 Conditional Approval JOSE AVILA
Footing/Foundation/Slab 5/23/2023 Approved JOSE AVILA
METHANE-Barrier 5/23/2023 Approved JOSE AVILA
METHANE-Subgrade 5/23/2023 Approved JOSE AVILA
Deputy Reinf. Concrete 5/25/2023 Approved JOSE AVILA
Deputy Wood Construction 6/21/2023 Conditional Approval JOSE AVILA
HVAC-Rough 7/10/2023 Approved JOSE AVILA
PLUMBING-Rough 7/10/2023 Approved JOSE AVILA
Sewer 7/10/2023 Approved JOSE AVILA
ELECTRICAL-Rough 7/17/2023 Approved JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 7/17/2023 Approved JOSE AVILA
BUILDING-Rough-Frame 8/1/2023 Approved JOSE AVILA
Green Building Rough 8/1/2023 Approved JOSE AVILA
Interior/Exterior Lathing 8/1/2023 Approved JOSE AVILA
METHANE-Rough 8/1/2023 Approved JOSE AVILA
ELECTRICAL-Final 12/7/2023 Approved ANTHONY EGSON
HVAC-Final 12/7/2023 No Access for Inspection ANTHONY EGSON
PLUMBING-Final 12/7/2023 Approved ANTHONY EGSON
HVAC-Final 4/4/2024 Approved RICHARD DOCKUS
Final 4/8/2024 Corrections Issued RICHARD DOCKUS
Green Building Final 4/8/2024 Approved RICHARD DOCKUS
SGSOV-Seismic Gas S/O Valve 4/8/2024 SGSOV Approved RICHARD DOCKUS
Smoke Detectors 4/8/2024 Partial Approval RICHARD DOCKUS
Final 4/24/2024 OK to Issue CofO RICHARD DOCKUS
Smoke Detectors 4/24/2024 Approved RICHARD DOCKUS