6615 N YARMOUTH AVE 91335

Certificate Information: 6615 N YARMOUTH AVE 91335

Application / Permit
22014-10000-03917
Plan Check / Job No.
B22LA15297
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN PROPOSED ADDIITON TO EXISTING DETACHED GARAGE TO CREATE AN ACCESSORY DWELLING UNIT PER ORDINANCE with 2.5' x 4' patio cover.
Permit Issued
Issued on 10/3/2022
Issuing Office
Current Status
CofO Issued on 3/21/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/3/2022 APPLICANT
Assigned to Plan Check Engineer 8/10/2022 MICHAEL LOPEZ
Corrections Issued 8/11/2022 MICHAEL LOPEZ
Applicant returned to address corrections 9/21/2022 MICHAEL LOPEZ
Applicant returned to address corrections 9/22/2022 MICHAEL LOPEZ
Plan Check Approved 9/28/2022 MICHAEL LOPEZ
Issued 10/3/2022 APPLICANT
CofO in Progress 3/10/2023 JEFFREY BULL
Permit Finaled 3/21/2023 JOHN JANSON
CofO Issued 3/21/2023 JOHN JANSON
Permit Finaled 3/21/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 8/11/2022 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 8/11/2022 COLIN LOREDO
Roof/Waste drainage to street Cleared 8/11/2022 COLIN LOREDO
Sewer availability Cleared 8/11/2022 COLIN LOREDO
ZI Cleared 8/11/2022 STEVEN WECHSLER
Construction within easement Cleared 8/17/2022 TINA MIRANDA
Low Impact Development Cleared 9/14/2022 CHRIS VONG

Contact Information

Contractor Owner-Builder       ,
Engineer , ; Lic. No.: NA53080       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/13/2022 Conditional Approval KRISTEN CAUSEY
Footing/Foundation/Slab 10/18/2022 Approved JEFFREY BULL
Sewer 10/18/2022 Approved JEFFREY BULL
Underground Mechanical 10/18/2022 Approved JEFFREY BULL
Floor/Roof Diaphrgm/Shear Wall 11/21/2022 Approved JEFFREY BULL
BUILDING-Rough-Frame 12/9/2022 Approved JEFFREY BULL
ELECTRICAL-Rough 12/9/2022 Approved JEFFREY BULL
Green Building Rough 12/9/2022 Approved JEFFREY BULL
PLUMBING-Rough 12/9/2022 Approved JEFFREY BULL
Interior/Exterior Lathing 12/16/2022 Partial Approval MORRIS JACKSON
Insulation 12/21/2022 Approved JESUS PINEDA
Drywall Nailing 12/27/2022 Approved KRISTEN CAUSEY
Final 2/23/2023 Corrections Issued JEFFREY BULL
Green Building Final 2/23/2023 Not Ready for Inspection JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 2/23/2023 SGSOV Not Ready JEFFREY BULL
Smoke Detectors 2/23/2023 Approved JEFFREY BULL
ELECTRICAL-Final 3/9/2023 Approved JEFFREY BULL
Final 3/9/2023 OK to Issue CofO JEFFREY BULL
Green Building Final 3/9/2023 Approved JEFFREY BULL
HVAC-Final 3/9/2023 Approved JEFFREY BULL
PLUMBING-Final 3/9/2023 Approved JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 3/9/2023 SGSOV Approved JEFFREY BULL