1906 W ESCARPA DR 90041

Certificate Information: 1906 W ESCARPA DR 90041

Application / Permit
22014-10000-03904
Plan Check / Job No.
B22LA14486
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan HOUSE: MINOR REMODEL OF A 2,460 SF TWO-STORY SINGLE FAMILY RESIDENCE WITH BASEMENT & A 266 SF ADDITION (ENCLOSURE OF LOWER LEVEL PORCH & UPPER LEVEL BALCONY)
Permit Issued
Issued on 12/19/2022
Issuing Office
Current Status
CofO Issued on 3/6/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/25/2022 APPLICANT
Assigned to Plan Check Engineer 7/29/2022 VARAND SARKISIAN
Corrections Issued 8/2/2022 VARAND SARKISIAN
Quality Review Completed 8/3/2022 LIPING TENG
Applicant returned to address corrections 11/23/2022 VARAND SARKISIAN
Plan Check Approved 12/14/2022 VARAND SARKISIAN
Issued 12/19/2022 APPLICANT
CofO in Progress 3/3/2025 BRENDAN MORELLI
Permit Finaled 3/6/2025 DEROLD HAUFF
CofO Issued 3/6/2025 DEROLD HAUFF
Permit Finaled 3/6/2025 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 11/10/2022 STEVE MELGAR
Sewer availability Cleared 11/21/2022 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 11/28/2022 STEVE MELGAR
Grading Pre-Inspection Cleared 12/14/2022 VARAND SARKISIAN

Contact Information

Architect Ryan,, Oonagh C; Lic. No.: C33156 923 E 3RD STREET #105      LOS ANGELES, CA 90013
Contractor Drinchich Bryan Construction; Lic. No.: 631183-B       ,

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/22/2023 Not Ready for Inspection OSVALDO PARAMO
Pre-Inspection 3/22/2023 Approved OSVALDO PARAMO
Deputy Drilled-In Anchors 4/5/2023 Conditional Approval CRAIG VAUGHAN
Footing/Foundation/Slab 5/25/2023 Partial Approval CRAIG VAUGHAN
Deputy Reinf. Concrete 5/26/2023 Conditional Approval CRAIG VAUGHAN
Deputy Drilled-In Anchors 7/6/2023 Conditional Approval CRAIG VAUGHAN
Footing/Foundation/Slab 7/7/2023 Partial Approval CRAIG VAUGHAN
Deputy Drilled-In Anchors 7/20/2023 Conditional Approval CRAIG VAUGHAN
Footing/Foundation/Slab 8/21/2023 Not Ready for Inspection CRAIG VAUGHAN
Footing/Foundation/Slab 8/23/2023 Partial Approval CRAIG VAUGHAN
Footing/Foundation/Slab 9/6/2023 Approved ROY SPAULDING
Sewer 9/18/2023 Partial Approval CRAIG VAUGHAN
Deputy Drilled-In Anchors 9/22/2023 Conditional Approval CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 9/27/2023 Approved ROY SPAULDING
PLUMBING-Rough 10/17/2023 Partial Approval CRAIG VAUGHAN
Deputy Steel/Welding 10/31/2023 Conditional Approval CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 11/13/2023 Partial Approval CRAIG VAUGHAN
Sewer 12/4/2023 Partial Approval CRAIG VAUGHAN
Deputy Other (see comments) 1/31/2024 Conditional Approval CRAIG VAUGHAN
Deputy Drilled-In Anchors 3/20/2024 Conditional Approval CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 3/20/2024 Partial Approval CRAIG VAUGHAN
ELECTRICAL-Rough 5/28/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
Underground Mechanical 5/28/2024 Partial Approval ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 6/10/2024 Partial Approval CRAIG VAUGHAN
ELECTRICAL-Rough 7/1/2024 Partial Approval JOSEPH MCGARRY
HVAC-Rough 7/1/2024 Approved JOSEPH MCGARRY
PLUMBING-Rough 7/1/2024 Conditional Approval JOSEPH MCGARRY
BUILDING-Rough-Frame 7/2/2024 Partial Approval BRENDAN MORELLI
Green Building Rough 7/2/2024 Not Ready for Inspection BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 7/23/2024 Approved CRAIG VAUGHAN
Insulation 7/23/2024 Approved CRAIG VAUGHAN
PLUMBING-Rough 7/23/2024 Approved CRAIG VAUGHAN
Drywall Nailing 7/31/2024 Approved ANTHONY RAMOS
Interior/Exterior Lathing 7/31/2024 Not Ready for Inspection ANTHONY RAMOS
Shower Pan 8/30/2024 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 9/6/2024 Partial Approval ALIZAH MAYAGOITIA
Drywall Nailing 9/12/2024 Approved ROY SPAULDING
Interior/Exterior Lathing 9/13/2024 Approved ROY SPAULDING
Interior/Exterior Lathing 9/23/2024 Approved ROY SPAULDING
ELECTRICAL-Rough 11/14/2024 Partial Approval ROY SPAULDING
HVAC-Rough 12/6/2024 Approved ROY SPAULDING
Rough-Elec/Plmb/HVAC 12/6/2024 Not Ready for Inspection ROY SPAULDING
Underground Mechanical 12/6/2024 Approved ROY SPAULDING
ELECTRICAL-Final 1/22/2025 Corrections Issued BRENDAN MORELLI
HVAC-Final 1/22/2025 Corrections Issued BRENDAN MORELLI
PLUMBING-Final 1/22/2025 Corrections Issued BRENDAN MORELLI
ELECTRICAL-Final 2/7/2025 Approved BRENDAN MORELLI
Final 2/7/2025 Corrections Issued BRENDAN MORELLI
HVAC-Final 2/7/2025 Approved BRENDAN MORELLI
PLUMBING-Final 2/7/2025 Approved BRENDAN MORELLI
BUILDING-Rough-Frame 2/12/2025 Approved BRENDAN MORELLI
Final 2/12/2025 OK to Issue CofO BRENDAN MORELLI
Green Building Final 2/12/2025 Approved BRENDAN MORELLI
Green Building Rough 2/12/2025 Approved BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 2/12/2025 SGSOV Not Required BRENDAN MORELLI
Smoke Detectors 2/12/2025 Approved BRENDAN MORELLI