3910 1/2 S 3RD AVE 90008
Certificate Information: 3910 1/2 S 3RD AVE 90008
- Application / Permit
- 22014-10000-03903
- Plan Check / Job No.
- B22LA15247
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: ADDITION AND CONVERT (E) GARAGE TO 1-STORY ACCESSORY DWELING UNIT PER LAMC 12.22.A.33.(c)-(d)
- Permit Issued
- Issued on 8/17/2022
- Issuing Office
- Current Status
- CofO Issued on 7/28/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/2/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/8/2022 | DANIEL YIP |
| Corrections Issued | 8/9/2022 | DANIEL YIP |
| Plan Check Approved | 8/17/2022 | DANIEL YIP |
| Issued | 8/17/2022 | APPLICANT |
| CofO in Progress | 6/7/2023 | ANTHONY EGSON |
| CofO in Progress | 6/26/2023 | DONALD CRICHLOW |
| CofO in Progress | 6/26/2023 | ANTHONY EGSON |
| CofO Issued | 7/28/2023 | DEROLD HAUFF |
| Permit Finaled | 7/28/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/9/2022 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 8/9/2022 | STEVE MELGAR |
| Roof/Waste drainage to street | Cleared | 8/9/2022 | STEVE MELGAR |
| Sewer availability | Cleared | 8/9/2022 | STEVE MELGAR |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Almalla,, Dean; Lic. No.: C58024 | 15053 VENTURA BLVD STE 205 SHERMAN OAKS, CA 91403 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/12/2022 | Partial Inspection | ANTHONY EGSON |
| Footing/Foundation/Slab | 10/19/2022 | Partial Approval | ANTHONY EGSON |
| Footing/Foundation/Slab | 11/15/2022 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/17/2022 | Partial Approval | ANTHONY EGSON |
| Insulation | 11/21/2022 | Partial Approval | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/30/2022 | No Access for Inspection | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/11/2023 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Rough | 1/12/2023 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 1/12/2023 | Corrections Issued | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/19/2023 | Approved | ANTHONY EGSON |
| HVAC-Rough | 1/19/2023 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 1/19/2023 | Approved | ANTHONY EGSON |
| Green Building Rough | 1/20/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Interior/Exterior Lathing | 1/20/2023 | Not Ready for Inspection | ANTHONY EGSON |
| BUILDING-Rough-Frame | 1/25/2023 | Partial Approval | ANTHONY EGSON |
| Insulation | 1/25/2023 | Partial Approval | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/27/2023 | Approved | ANTHONY EGSON |
| Insulation | 1/27/2023 | Approved | ANTHONY EGSON |
| Drywall Nailing | 2/3/2023 | Partial Approval | ANTHONY EGSON |
| BUILDING-Rough-Frame | 2/8/2023 | Approved | SCOTT FINNILA |
| Green Building Rough | 2/8/2023 | Approved | SCOTT FINNILA |
| Interior/Exterior Lathing | 2/8/2023 | Partial Approval | SCOTT FINNILA |
| Shower Pan | 2/8/2023 | Approved | SCOTT FINNILA |
| Interior/Exterior Lathing | 2/9/2023 | No Access for Inspection | STUART CHAPMAN |
| Interior/Exterior Lathing | 2/21/2023 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 4/20/2023 | Approved | ANTHONY EGSON |
| HVAC-Final | 4/20/2023 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 4/20/2023 | Partial Approval | ANTHONY EGSON |
| PLUMBING-Final | 5/23/2023 | Corrections Issued | ANTHONY EGSON |
| Service/Power Release | 5/23/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Final | 5/30/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Gas Test | 5/30/2023 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 5/30/2023 | Approved | ANTHONY EGSON |
| Drywall Nailing | 6/6/2023 | Approved | ANTHONY EGSON |
| Final | 6/6/2023 | Partial Approval | ANTHONY EGSON |
| Green Building Final | 6/6/2023 | Approved | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 6/6/2023 | SGSOV Approved | ANTHONY EGSON |
| Smoke Detectors | 6/6/2023 | Approved | ANTHONY EGSON |
| Final | 6/26/2023 | OK to Issue CofO | ANTHONY EGSON |
| Service/Power Release | 6/26/2023 | Approved | ANTHONY EGSON |