1611 W 64TH ST 90047

Certificate Information: 1611 W 64TH ST 90047

Application / Permit
22014-10000-03897
Plan Check / Job No.
B22LA15228
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ONE STORY ADDITION TO EXISTING SFD PER WFPP
Permit Issued
Issued on 3/22/2023
Issuing Office
Current Status
CofO Issued on 1/7/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/4/2022 APPLICANT
Assigned to Plan Check Engineer 8/12/2022 JOE VO
Corrections Issued 8/15/2022 JOE VO
Applicant returned to address corrections 3/15/2023 SELLA BENYAMIN
Plan Check Approved 3/21/2023 JOE VO
Issued 3/22/2023 APPLICANT
CofO in Progress 1/2/2024 HERBERT GIRON
Permit Finaled 1/7/2024 DEROLD HAUFF
CofO Issued 1/7/2024 DEROLD HAUFF
Permit Finaled 1/7/2024 DEROLD HAUFF

Permit Application Clearance Information

Sewer availability Cleared 1/30/2023 CHRISTOPHER ROCHA
Eng Process Fee Ord 176,300 Cleared 2/3/2023 CHRISTOPHER ROCHA
Roof/Waste drainage to street Cleared 3/15/2023 CHRISTOPHER ROCHA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/17/2023 Corrections Issued ENRIQUE MIRELES
Footing/Foundation/Slab 8/22/2023 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 8/29/2023 Corrections Issued STUART CHAPMAN
PLUMBING-Rough 8/29/2023 Partial Approval STUART CHAPMAN
PLUMBING-Rough 9/5/2023 Corrections Issued ENRIQUE MIRELES
PLUMBING-Rough 9/7/2023 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 10/2/2023 Approved MICHAEL LEWIS
PLUMBING-Rough 10/2/2023 Approved MICHAEL LEWIS
Shower Pan 10/2/2023 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 10/10/2023 Approved RONNIE MINDANAO
HVAC-Rough 10/10/2023 Approved RONNIE MINDANAO
BUILDING-Rough-Frame 10/12/2023 Not Ready for Inspection CRAIG DAVIS
Floor/Roof Diaphrgm/Shear Wall 10/12/2023 Approved CRAIG DAVIS
Green Building Rough 10/12/2023 Not Ready for Inspection CRAIG DAVIS
Interior/Exterior Lathing 10/12/2023 Approved CRAIG DAVIS
BUILDING-Rough-Frame 10/16/2023 Approved RONNIE MINDANAO
Floor/Roof Diaphrgm/Shear Wall 10/16/2023 Not Ready for Inspection RONNIE MINDANAO
Green Building Rough 10/18/2023 Approved JUSTIN HAWLEY
Insulation 10/18/2023 Corrections Issued JUSTIN HAWLEY
Interior/Exterior Lathing 10/18/2023 Approved JUSTIN HAWLEY
BUILDING-Rough-Frame 10/25/2023 Approved RONNIE MINDANAO
Drywall Nailing 10/25/2023 Approved RONNIE MINDANAO
Insulation 10/25/2023 Approved RONNIE MINDANAO
Final 11/22/2023 Not Ready for Inspection CRAIG DAVIS
Green Building Final 11/22/2023 Approved CRAIG DAVIS
SGSOV-Seismic Gas S/O Valve 11/22/2023 SGSOV Approved CRAIG DAVIS
Smoke Detectors 11/22/2023 Approved CRAIG DAVIS
Final 12/5/2023 Corrections Issued CRAIG DAVIS
ELECTRICAL-Final 1/2/2024 Approved HERBERT GIRON
Final 1/2/2024 OK to Issue CofO HERBERT GIRON
HVAC-Final 1/2/2024 Approved HERBERT GIRON
PLUMBING-Final 1/2/2024 Approved HERBERT GIRON