5153 N MOUNT HELENA AVE 90041
Certificate Information: 5153 N MOUNT HELENA AVE 90041
- Application / Permit
- 22014-10000-03893
- Plan Check / Job No.
- B22LA15201
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: Ground floor addition to existing single family dwelling to the front of the structure . Work per Engineered Design .
- Permit Issued
- Issued on 9/5/2024
- Issuing Office
- Current Status
- CofO Issued on 3/18/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/5/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/12/2022 | SAMUEL GONZALEZ |
| Corrections Issued | 8/13/2022 | SAMUEL GONZALEZ |
| Applicant returned to address corrections | 10/28/2022 | SAMUEL GONZALEZ |
| Applicant returned to address corrections | 7/17/2023 | SAMUEL GONZALEZ |
| Applicant returned to address corrections | 7/19/2023 | VICTOR CHEN |
| Applicant returned to address corrections | 7/31/2023 | WEIJIAN HUANG |
| Plan Check Approved | 5/2/2024 | GEORGE ALVAREZ |
| Issued | 9/5/2024 | APPLICANT |
| CofO in Progress | 3/13/2025 | BRENDAN MORELLI |
| Permit Finaled | 3/18/2025 | DEROLD HAUFF |
| CofO Issued | 3/18/2025 | DEROLD HAUFF |
| Permit Finaled | 3/18/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/18/2022 | JEANIE LAM |
| Sewer availability | Cleared | 10/18/2022 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 10/31/2022 | JEANIE LAM |
| GPI Written Notices | Cleared | 7/19/2023 | SAMUEL GONZALEZ |
| Grading Pre-Inspection | Cleared | 7/19/2023 | SAMUEL GONZALEZ |
| Construction near power lines | Cleared | 4/25/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Abrahamian,, Zaven; Lic. No.: C41672 | 237 S LAMER ST BURBANK, CA 91506 |
| Engineer | Medina,, Ferdinand Casaclang; Lic. No.: C88007 | 1051 S HOLT AVE APT F LOS ANGELES, CA 90035 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/20/2024 | Conditional Approval | ROY SPAULDING |
| Excavation/Setback/Form/Re-Bar | 9/20/2024 | Corrections Issued | JEFFREY MEAD |
| Footing/Foundation/Slab | 9/20/2024 | Corrections Issued | JEFFREY MEAD |
| Footing/Foundation/Slab | 9/24/2024 | Approved | ROY SPAULDING |
| Floor/Roof Diaphrgm/Shear Wall | 10/3/2024 | Partial Approval | ROY SPAULDING |
| PLUMBING-Rough | 10/3/2024 | Approved | ROY SPAULDING |
| Floor/Roof Diaphrgm/Shear Wall | 10/7/2024 | Partial Approval | ROY SPAULDING |
| Green Building Rough | 10/7/2024 | Not Ready for Inspection | ROY SPAULDING |
| ELECTRICAL-Rough | 10/24/2024 | Corrections Issued | ROY SPAULDING |
| Floor/Roof Diaphrgm/Shear Wall | 10/24/2024 | Approved | ROY SPAULDING |
| PLUMBING-Rough | 10/24/2024 | Approved | ROY SPAULDING |
| Deputy Wood Construction | 10/28/2024 | Conditional Approval | ROY SPAULDING |
| BUILDING-Rough-Frame | 10/30/2024 | Partial Approval | ROY SPAULDING |
| ELECTRICAL-Rough | 10/30/2024 | Approved | ROY SPAULDING |
| Green Building Rough | 10/30/2024 | Not Ready for Inspection | ROY SPAULDING |
| HVAC-Rough | 10/30/2024 | Approved | ROY SPAULDING |
| Green Building Rough | 11/8/2024 | Approved | ROY SPAULDING |
| Interior/Exterior Lathing | 11/8/2024 | Approved | ROY SPAULDING |
| Shower Pan | 11/8/2024 | Approved | ROY SPAULDING |
| Insulation | 11/14/2024 | Approved | ROY SPAULDING |
| Drywall Nailing | 11/25/2024 | Approved | ROY SPAULDING |
| Deputy Drilled-In Anchors | 12/3/2024 | Conditional Approval | ROY SPAULDING |
| BUILDING-Rough-Frame | 2/6/2025 | Approved | BRENDAN MORELLI |
| Final | 2/6/2025 | Corrections Issued | BRENDAN MORELLI |
| Green Building Final | 2/6/2025 | Not Ready for Inspection | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 2/6/2025 | SGSOV Not Required | BRENDAN MORELLI |
| Smoke Detectors | 2/6/2025 | Corrections Issued | BRENDAN MORELLI |
| Final | 3/10/2025 | OK to Issue CofO | BRENDAN MORELLI |
| Green Building Final | 3/10/2025 | Approved | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 3/10/2025 | SGSOV Approved | BRENDAN MORELLI |
| Smoke Detectors | 3/10/2025 | Approved | BRENDAN MORELLI |