1718 2/3-3/4 W 49TH ST 90062
Certificate Information: 1718 2/3-3/4 W 49TH ST 90062
- Application / Permit
- 22014-10000-03869
- Plan Check / Job No.
- B22LA15038
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan Addition to existing garage and convert to two ADU per ordinace
- Permit Issued
- Issued on 1/31/2023
- Issuing Office
- Current Status
- CofO Issued on 12/20/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/3/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/25/2022 | YASHAR EMAMI |
| Corrections Issued | 9/15/2022 | YASHAR EMAMI |
| Quality Review Completed | 9/27/2022 | CHIHARU SUZUKI |
| Applicant returned to address corrections | 11/8/2022 | YASHAR EMAMI |
| Applicant returned to address corrections | 12/16/2022 | KAVIAN REFAHI |
| Plan Check Approved | 1/23/2023 | YASHAR EMAMI |
| Issued | 1/31/2023 | APPLICANT |
| CofO in Progress | 12/19/2024 | BARRY HACHE |
| Permit Finaled | 12/20/2024 | DEROLD HAUFF |
| CofO Issued | 12/20/2024 | DEROLD HAUFF |
| Permit Finaled | 12/20/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/27/2022 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 10/31/2022 | WALLIE JONG |
| Low Impact Development | Cleared | 10/31/2022 | DEBORA LEITE |
| Sewer availability | Cleared | 10/31/2022 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 11/1/2022 | WALLIE JONG |
Contact Information
| Contractor | Swami International Inc; Lic. No.: 833804-B | , |
| Engineer | Kazemi,, Milad; Lic. No.: C92143 | 21126 MERRIDY STREET CHATSWORTH, CA 91311 |
| Engineer | Kazemi,, Milad; Lic. No.: NA92143 | , |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/15/2023 | Approved | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 5/2/2023 | Not Ready for Inspection | SABAS ALONSO |
| Underground Mechanical | 5/2/2023 | Partial Approval | SABAS ALONSO |
| Excavation/Setback/Form/Re-Bar | 5/18/2023 | Approved | SABAS ALONSO |
| Footing/Foundation/Slab | 5/18/2023 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 6/14/2023 | Partial Approval | SABAS ALONSO |
| BUILDING-Rough-Frame | 7/19/2023 | Partial Approval | STUART CHAPMAN |
| ELECTRICAL-Rough | 7/19/2023 | Approved | STUART CHAPMAN |
| HVAC-Rough | 7/19/2023 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 7/19/2023 | Approved | STUART CHAPMAN |
| Insulation | 7/26/2023 | Corrections Issued | ANTHONY EGSON |
| Insulation | 7/31/2023 | Conditional Approval | MICHAEL LEWIS |
| Interior/Exterior Lathing | 7/31/2023 | Approved | MICHAEL LEWIS |
| Insulation | 8/17/2023 | Conditional Approval | MICHAEL LEWIS |
| Interior/Exterior Lathing | 8/17/2023 | Approved | MICHAEL LEWIS |
| Shower Pan | 8/17/2023 | Approved | MICHAEL LEWIS |
| Drywall Nailing | 8/30/2023 | Corrections Issued | SABAS ALONSO |
| Drywall Nailing | 9/13/2023 | Partial Approval | SABAS ALONSO |
| Drywall Nailing | 11/8/2023 | Approved | CRAIG DAVIS |
| ELECTRICAL-Final | 11/4/2024 | Corrections Issued | CRAIG DAVIS |
| HVAC-Final | 11/4/2024 | Approved | CRAIG DAVIS |
| PLUMBING-Final | 11/4/2024 | Corrections Issued | CRAIG DAVIS |
| BUILDING-Rough-Frame | 11/21/2024 | Approved | JOHN QUINTANILLA |
| Final | 11/21/2024 | Conditional Approval | JOHN QUINTANILLA |
| SGSOV-Seismic Gas S/O Valve | 11/21/2024 | SGSOV Approved | JOHN QUINTANILLA |
| Smoke Detectors | 11/21/2024 | Approved | JOHN QUINTANILLA |
| Final | 12/9/2024 | Corrections Issued | CRAIG DAVIS |
| Final | 12/16/2024 | OK to Issue CofO | BARRY HACHE |