17637 W CALVERT ST 91316

Certificate Information: 17637 W CALVERT ST 91316

Application / Permit
22014-10000-03843
Plan Check / Job No.
B22LA14939
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan OBTAIN A PERMIT FOR AN UPERMITTED ADDITION TO EXISTING SFD "COMPLY WITH DEPARTMENT ORDER effective date 06/23/2022. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
Permit Issued
Issued on 8/11/2022
Issuing Office
Current Status
CofO Issued on 11/9/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/28/2022 APPLICANT
Assigned to Plan Check Engineer 7/29/2022 JOSEPH RAFOLS
Corrections Issued 8/1/2022 JOSEPH RAFOLS
Plan Check Approved 8/10/2022 JOSEPH RAFOLS
Issued 8/11/2022 APPLICANT
CofO in Progress 6/27/2023 PATRICK LIEBREGT
Permit Finaled 11/9/2023 JEFF NAPIER
CofO Issued 11/9/2023 JEFF NAPIER
Permit Finaled 11/9/2023 JEFF NAPIER

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/10/2022 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 8/10/2022 CARLOS AGUILERA
Sewer availability Cleared 8/10/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOEL ORDAZ, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
PTOLEMY HILL, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
JONATHAN FRANCHINI, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVAKIAN, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
EDMOND DECKERT, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
TIMOTHY KEY, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
ROBERT CHAVEZ, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 8/17/2022 Not Ready for Inspection GORDON ZUBER
Final 8/17/2022 Not Ready for Inspection GORDON ZUBER
Footing/Foundation/Slab 8/17/2022 Corrections Issued GORDON ZUBER
Green Building Final 8/17/2022 Not Ready for Inspection GORDON ZUBER
Green Building Rough 8/17/2022 Not Ready for Inspection GORDON ZUBER
SGSOV-Seismic Gas S/O Valve 8/17/2022 SGSOV Not Ready GORDON ZUBER
Smoke Detectors 8/17/2022 Not Ready for Inspection GORDON ZUBER
SGSOV-Seismic Gas S/O Valve 9/7/2022 SGSOV Not Ready GORDON ZUBER
BUILDING-Rough-Frame 9/12/2022 Partial Inspection GORDON ZUBER
Final 9/12/2022 Not Ready for Inspection GORDON ZUBER
Footing/Foundation/Slab 9/12/2022 Corrections Issued GORDON ZUBER
Green Building Final 9/12/2022 Not Ready for Inspection GORDON ZUBER
Green Building Rough 9/12/2022 Not Ready for Inspection GORDON ZUBER
SGSOV-Seismic Gas S/O Valve 9/12/2022 SGSOV Not Ready GORDON ZUBER
Smoke Detectors 9/12/2022 Not Ready for Inspection GORDON ZUBER
Footing/Foundation/Slab 2/9/2023 Approved PATRICK LIEBREGT
Pre-Inspection 2/9/2023 Corrections Issued PATRICK LIEBREGT
BUILDING-Rough-Frame 3/6/2023 Approved PATRICK LIEBREGT
Final 3/6/2023 Corrections Issued PATRICK LIEBREGT
Green Building Final 3/6/2023 Approved PATRICK LIEBREGT
Green Building Rough 3/6/2023 Approved PATRICK LIEBREGT
SGSOV-Seismic Gas S/O Valve 3/6/2023 SGSOV Approved PATRICK LIEBREGT
Smoke Detectors 3/6/2023 Approved PATRICK LIEBREGT
Final 6/27/2023 OK to Issue CofO PATRICK LIEBREGT