809 N ORLANDO AVE 90069
Certificate Information: 809 N ORLANDO AVE 90069
- Application / Permit
- 22014-10000-03835
- Plan Check / Job No.
- B22LA14916
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan GROUND FLOOR ADDTIOTION AND INT. & EXT. STRUCTURAL REMODEL TO (E) 1-STORY SFD.
- Permit Issued
- Issued on 11/9/2022
- Issuing Office
- Current Status
- CofO Issued on 10/2/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/11/2022 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 8/17/2022 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 8/30/2022 | TEODORO DIAZ RODRIGUEZ |
| Plan Check Approved | 11/9/2022 | MAHNAZ NOURHASHEMI |
| Issued | 11/9/2022 | APPLICANT |
| CofO in Progress | 9/16/2024 | JOSE MACIAS |
| Permit Finaled | 10/2/2024 | RUBEN SALAS |
| CofO Issued | 10/2/2024 | RUBEN SALAS |
| Permit Finaled | 10/2/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/31/2022 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 8/31/2022 | CHRISTOPHER ROCHA |
| Low Impact Development | Cleared | 10/11/2022 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 10/12/2022 | CHRISTOPHER ROCHA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Maalouf,, Sami; Lic. No.: NA53210 | , |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/17/2022 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 11/29/2022 | Partial Approval | MICHAEL LEWIS |
| PLUMBING-Rough | 11/29/2022 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 12/1/2022 | Partial Approval | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 12/14/2022 | Approved | MICHAEL LEWIS |
| Deputy Wood Construction | 12/15/2022 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 12/19/2022 | Partial Approval | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 12/28/2022 | Approved | MICHAEL LEWIS |
| Insulation | 12/28/2022 | Partial Approval | MICHAEL LEWIS |
| Rough-Elec/Plmb/HVAC | 1/17/2023 | Approved | MICHAEL LEWIS |
| Shower Pan | 1/17/2023 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 1/19/2023 | Approved | MICHAEL LEWIS |
| Green Building Rough | 1/19/2023 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 1/19/2023 | Approved | MICHAEL LEWIS |
| Insulation | 1/23/2023 | Approved | MICHAEL LEWIS |
| Drywall Nailing | 1/31/2023 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 1/31/2023 | Approved | MICHAEL LEWIS |
| Final | 5/19/2023 | Corrections Issued | LILIANA PORTILLO |
| Green Building Final | 5/19/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 5/19/2023 | SGSOV Not Ready | LILIANA PORTILLO |
| Smoke Detectors | 5/19/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| Final | 8/27/2024 | Corrections Issued | AMIR NAZARIAN |
| Green Building Final | 8/27/2024 | Corrections Issued | AMIR NAZARIAN |
| SGSOV-Seismic Gas S/O Valve | 8/27/2024 | SGSOV Approved | AMIR NAZARIAN |
| Smoke Detectors | 8/27/2024 | Corrections Issued | AMIR NAZARIAN |
| Final | 9/3/2024 | Conditional Approval | JOSE MACIAS |
| Green Building Final | 9/3/2024 | Approved | JOSE MACIAS |
| Smoke Detectors | 9/3/2024 | Approved | JOSE MACIAS |
| Final | 9/4/2024 | OK to Issue CofO | JOSE MACIAS |
| Service/Power Release | 9/16/2024 | Approved | JOSE MACIAS |