2347 S MIDVALE AVE 90064
Certificate Information: 2347 S MIDVALE AVE 90064
- Application / Permit
- 22014-10000-03825
- Plan Check / Job No.
- B22LA14884
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION TO DETACHED GARAGE AND CONVERT TO ADU.
- Permit Issued
- Issued on 2/7/2023
- Issuing Office
- Current Status
- CofO Issued on 4/16/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/5/2022 | JOE VO |
| Corrections Issued | 8/6/2022 | JOE VO |
| Applicant returned to address corrections | 9/7/2022 | JOE VO |
| Plan Check Approved | 11/1/2022 | JOE VO |
| Issued | 2/7/2023 | APPLICANT |
| CofO in Progress | 4/15/2024 | JESUS PINEDA |
| Permit Finaled | 4/16/2024 | DANIEL ORRANTE |
| CofO Issued | 4/16/2024 | DANIEL ORRANTE |
| Permit Finaled | 4/16/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 8/14/2022 | STEVEN JIN |
| Grading Pre-Inspection | Cleared | 9/6/2022 | KIRK LINKLATER |
| Eng Process Fee Ord 176,300 | Cleared | 9/12/2022 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 9/12/2022 | HISASHI KOBAYAKAWA |
| Specific Plan | Cleared | 9/12/2022 | WESTON PRINGLE |
| Construction near power lines | Cleared | 10/12/2022 | RIDWAN HARDY |
| Roof/Waste drainage to street | Cleared | 10/31/2022 | HISASHI KOBAYAKAWA |
Contact Information
| Contractor | L A Developing Inc; Lic. No.: 1083426-B | , |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/22/2023 | Conditional Approval | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 2/22/2023 | Partial Approval | JOHNNY MIRANDA |
| Reinforced Concrete Frame | 2/22/2023 | Approved | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 2/28/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| Excavation/Setback/Form/Re-Bar | 3/3/2023 | Approved | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 3/17/2023 | Partial Approval | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 3/31/2023 | Not Ready for Inspection | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 4/20/2023 | Corrections Issued | JOHNNY MIRANDA |
| HVAC-Rough | 4/20/2023 | Corrections Issued | JOHNNY MIRANDA |
| PLUMBING-Rough | 4/20/2023 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 4/27/2023 | Approved | JEREMY TODD |
| Interior/Exterior Lathing | 4/27/2023 | Approved | JEREMY TODD |
| Rough-Elec/Plmb/HVAC | 4/27/2023 | Approved | JEREMY TODD |
| Insulation | 5/9/2023 | Approved | JOHNNY MIRANDA |
| Insulation | 5/11/2023 | Approved | JOHNNY MIRANDA |
| Drywall Nailing | 5/18/2023 | Approved | JEREMY TODD |
| Interior/Exterior Lathing | 6/8/2023 | Not Ready for Inspection | JESUS PINEDA |
| Shower Pan | 6/8/2023 | Corrections Issued | JESUS PINEDA |
| Drywall Nailing | 6/20/2023 | Approved | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 6/20/2023 | Approved | ASHLEY THOMPSON |
| Shower Pan | 6/20/2023 | Approved | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 8/16/2023 | Approved | JESUS PINEDA |
| Final | 8/16/2023 | Corrections Issued | JESUS PINEDA |
| Footing/Foundation/Slab | 8/16/2023 | Approved | JESUS PINEDA |
| Green Building Final | 8/16/2023 | Approved | JESUS PINEDA |
| Green Building Rough | 8/16/2023 | Approved | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 8/16/2023 | SGSOV Approved | JESUS PINEDA |
| Smoke Detectors | 8/16/2023 | Approved | JESUS PINEDA |
| Final | 3/22/2024 | Conditional Approval | MICHAEL PELHAM |
| Final | 4/15/2024 | OK to Issue CofO | JESUS PINEDA |