4393 N SCANDIA WAY 90065
Certificate Information: 4393 N SCANDIA WAY 90065
- Application / Permit
- 22014-10000-03817
- Plan Check / Job No.
- B22LA14825
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- GROUND FLOOR AND SECOND FLOOR ADDITION TO (E) SFD
- Permit Issued
- Issued on 4/19/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/23/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/25/2022 | CARLOS MONTES |
| Corrections Issued | 9/1/2022 | CARLOS MONTES |
| Quality Review Completed | 9/6/2022 | KEN GILL |
| Building Plans Picked Up | 9/9/2022 | APPLICANT |
| Applicant returned to address corrections | 3/16/2023 | CARLOS MONTES |
| Plan Check Approved | 4/11/2023 | CARLOS MONTES |
| Issued | 4/19/2023 | APPLICANT |
| CofO in Progress | 3/21/2025 | NICHOLAS LOPEZ |
| Permit Finaled | 3/23/2025 | DEROLD HAUFF |
| CofO Issued | 3/23/2025 | DEROLD HAUFF |
| Permit Finaled | 3/23/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 11/4/2022 | STEVE MELGAR |
| BHO/Hillside ordinance | Cleared | 11/4/2022 | STEVE MELGAR |
| BHO/Hillside ordinance | Cleared | 11/4/2022 | STEVE MELGAR |
| BHO/Hillside ordinance | Cleared | 11/4/2022 | STEVE MELGAR |
| Distance to fire station | Cleared | 11/15/2022 | GILBERT URREA |
| Hydrant and Access approval | Cleared | 11/15/2022 | GILBERT URREA |
| Miscellaneous | Cleared | 11/29/2022 | DANIEL CORONADO |
| Miscellaneous | Cleared | 11/29/2022 | DANIEL CORONADO |
| Specific Plan | Cleared | 11/29/2022 | DANIEL CORONADO |
| Roof/Waste drainage to street | Cleared | 12/9/2022 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 12/13/2022 | AMAAN MALIK |
| Sewer availability | Cleared | 12/13/2022 | AMAAN MALIK |
| BHO/Hillside ordinance | Cleared | 12/14/2022 | AMAAN MALIK |
| GPI Written Notices | Cleared | 4/11/2023 | CARLOS MONTES |
| Grading Pre-Inspection | Cleared | 4/11/2023 | CARLOS MONTES |
Contact Information
| Contractor | Williams Christopher; Lic. No.: 711380-B | P O BOX 8652 LA CRESCENTA, CA 91224 |
| Engineer | Phillips,, Craig; Lic. No.: C69673 | 2123 VESTAL AVE LOS ANGELES, CA 90026 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/8/2023 | Partial Approval | SCOTT FINNILA |
| ELECTRICAL-Rough | 7/28/2023 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/28/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| HVAC-Rough | 7/28/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 7/28/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/4/2023 | Partial Approval | HAMIK HARTOUNIAN |
| Green Building Rough | 8/4/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| HVAC-Rough | 8/4/2023 | Approved | HAMIK HARTOUNIAN |
| Verify Sprinkler Sign Off | 8/4/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 8/18/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Rough | 8/18/2023 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 8/18/2023 | Approved | HAMIK HARTOUNIAN |
| Verify Sprinkler Sign Off | 8/18/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 8/24/2023 | Approved | HAMIK HARTOUNIAN |
| Verify Sprinkler Sign Off | 8/24/2023 | Approved | HAMIK HARTOUNIAN |
| Insulation | 8/30/2023 | Approved | JOSH MEISTER |
| Drywall Nailing | 9/12/2023 | Approved | BRENDAN MORELLI |
| Shower Pan | 9/18/2023 | Approved | JOSH MEISTER |
| Gas Test | 9/28/2023 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 9/28/2023 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Final | 5/31/2024 | Partial Approval | THOMAS LOGRASSO |
| Final | 5/31/2024 | Corrections Issued | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 5/31/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Green Building Final | 5/31/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| HVAC-Final | 5/31/2024 | Approved | THOMAS LOGRASSO |
| PLUMBING-Final | 5/31/2024 | Approved | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 5/31/2024 | SGSOV Approved | THOMAS LOGRASSO |
| Smoke Detectors | 5/31/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 8/8/2024 | Corrections Issued | THOMAS LOGRASSO |
| Final | 10/2/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 10/2/2024 | Approved | THOMAS LOGRASSO |
| Smoke Detectors | 10/2/2024 | Approved | THOMAS LOGRASSO |
| ELECTRICAL-Final | 10/15/2024 | Approved | THOMAS LOGRASSO |
| Final | 3/21/2025 | OK to Issue CofO | NICHOLAS LOPEZ |
| Green Building Final | 3/21/2025 | Approved | NICHOLAS LOPEZ |