3031 S CARDIFF AVE 90034
Certificate Information: 3031 S CARDIFF AVE 90034
- Application / Permit
- 22014-10000-03804
- Plan Check / Job No.
- B22LA14772
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED ADDITION AT REAR OF (E) SFD. INCLUDES REMODEL OF (E) KITCHEN, LAUNDRY ROOM AND BATHROOM.
- Permit Issued
- Issued on 3/22/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 3/11/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/1/2022 | LAWRENCE QUIRANTE |
| Corrections Issued | 8/4/2022 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 8/12/2022 | APPLICANT |
| Plan Check Approved | 10/6/2022 | FERNANDO FLORES |
| Issued | 3/22/2023 | APPLICANT |
| CofO in Progress | 3/5/2025 | ARAM AVEDISIAN |
| Permit Finaled | 3/11/2025 | RICHARD STEINBACH |
| CofO Issued | 3/11/2025 | RICHARD STEINBACH |
| Permit Finaled | 3/11/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 9/2/2022 | KIRK LINKLATER |
| Eng Process Fee Ord 176,300 | Cleared | 9/6/2022 | CATHERINE ADROVER |
| Roof/Waste drainage to street | Cleared | 9/14/2022 | CATHERINE ADROVER |
Contact Information
| Architect | Adams,, Lauren Amanda; Lic. No.: C30146 | LETTER FOUR INC 12822 WASHINGTON BLVD LOS ANGELES, CA 90266 |
| Contractor | Letter Four Inc; Lic. No.: 1028949-B | 12822 WASHINGTN BLVD LOS ANGELES, CA 90066 |
| Engineer | Truong,, Phong; Lic. No.: C70784 | 20439 E CRESTLINE DRIVE WALNUT, CA 91789 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/11/2023 | Corrections Issued | CLAYTON GRAHAM |
| Footing/Foundation/Slab | 9/13/2023 | Corrections Issued | CLAYTON GRAHAM |
| Deputy Drilled-In Anchors | 9/19/2023 | Conditional Approval | JAMES CHAVEZ |
| Footing/Foundation/Slab | 9/19/2023 | Conditional Approval | JAMES CHAVEZ |
| Wood Frame | 10/3/2023 | Partial Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2023 | Partial Approval | MEL KHACHATOURIAN |
| PLUMBING-Rough | 10/31/2023 | Approved | MICHAEL PELHAM |
| ELECTRICAL-Rough | 12/5/2023 | Partial Approval | OGANES TARAKHCHYAN |
| HVAC-Rough | 12/13/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| Deputy Wood Construction | 4/3/2024 | Partial Approval | OGANES TARAKHCHYAN |
| HVAC-Rough | 4/10/2024 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 4/22/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/22/2024 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 5/7/2024 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 5/7/2024 | Approved | OGANES TARAKHCHYAN |
| Green Building Rough | 5/7/2024 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 5/9/2024 | Partial Approval | OGANES TARAKHCHYAN |
| Insulation | 5/20/2024 | Approved | ASHLEY THOMPSON |
| Shower Pan | 5/20/2024 | Corrections Issued | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 5/28/2024 | Approved | AMY COLIN |
| Shower Pan | 5/28/2024 | Approved | AMY COLIN |
| Drywall Nailing | 6/12/2024 | Approved | AMY COLIN |
| Gas Test | 1/17/2025 | Approved | ARAM AVEDISIAN |
| Green Building Final | 1/17/2025 | Approved | ARAM AVEDISIAN |
| HVAC-Final | 1/17/2025 | Not Ready for Inspection | ARAM AVEDISIAN |
| PLUMBING-Final | 1/17/2025 | Corrections Issued | ARAM AVEDISIAN |
| ELECTRICAL-Final | 2/7/2025 | Corrections Issued | ASHLEY THOMPSON |
| Final | 2/7/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| Footing/Foundation/Slab | 2/7/2025 | Approved | ASHLEY THOMPSON |
| HVAC-Final | 2/7/2025 | Corrections Issued | ASHLEY THOMPSON |
| PLUMBING-Final | 2/7/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| SGSOV-Seismic Gas S/O Valve | 2/7/2025 | SGSOV Approved | ASHLEY THOMPSON |
| Smoke Detectors | 2/7/2025 | Corrections Issued | ASHLEY THOMPSON |
| ELECTRICAL-Final | 3/5/2025 | Approved | ARAM AVEDISIAN |
| Final | 3/5/2025 | OK to Issue CofO | ARAM AVEDISIAN |
| HVAC-Final | 3/5/2025 | Approved | ARAM AVEDISIAN |
| PLUMBING-Final | 3/5/2025 | Approved | ARAM AVEDISIAN |
| Smoke Detectors | 3/5/2025 | Approved | ARAM AVEDISIAN |