1397 N AVENIDA DE CORTEZ 90272
Certificate Information: 1397 N AVENIDA DE CORTEZ 90272
- Application / Permit
- 22014-10000-03796
- Plan Check / Job No.
- B22LA14724
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan; Attach (E) Garage to (N) SFD dwelling with 2nd story addition for SFD.
- Permit Issued
- Issued on 4/17/2023
- Issuing Office
- Current Status
- Issued on 4/17/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/19/2022 | HANS SANTIAGO |
| Corrections Issued | 8/22/2022 | HANS SANTIAGO |
| Quality Review Completed | 8/23/2022 | LIPING TENG |
| Applicant returned to address corrections | 11/15/2022 | HANS SANTIAGO |
| Applicant returned to address corrections | 12/21/2022 | HANS SANTIAGO |
| Applicant returned to address corrections | 4/4/2023 | HANS SANTIAGO |
| Plan Check Approved | 4/13/2023 | ANDREW SANTIAGO |
| Issued | 4/17/2023 | APPLICANT |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 8/30/2022 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 8/30/2022 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 8/30/2022 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 8/30/2022 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 8/30/2022 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 9/6/2022 | DINAH GARIN |
| Sewer availability | Cleared | 9/6/2022 | DINAH GARIN |
| Hydrant and Access approval | Cleared | 11/18/2022 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 12/5/2022 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 12/6/2022 | CATHERINE ADROVER |
| Coastal Zone | Cleared | 2/21/2023 | ASHLEY RODARTE |
| ZA Case | Cleared | 2/21/2023 | ASHLEY RODARTE |
| ZA Case | Cleared | 2/21/2023 | ASHLEY RODARTE |
| GPI Written Notices | Cleared | 4/3/2023 | ANDREW SANTIAGO |
| Grading Pre-Inspection | Cleared | 4/3/2023 | ANDREW SANTIAGO |
| ZA Case | Cleared | 4/10/2023 | DANG NGUYEN |
| Miscellaneous | Cleared | 4/12/2023 | DANG NGUYEN |
Contact Information
| Contractor | M D R N Remodeling Company; Lic. No.: 1065843-B | , |
| Contractor | Mdrn Construction; Lic. No.: 1065843-B | , |
| Engineer | Kyupelyan,, Emil; Lic. No.: C91238 | 8045 LASAINE AVE NORTHRIDGE, CA 91325 |
Inspector Information
| MICHAEL ALLEN, (310) 914-3886 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/25/2023 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| Excavation/Setback/Form/Re-Bar | 5/26/2023 | No Access for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 5/26/2023 | No Access for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Excavation/Setback/Form/Re-Bar | 5/31/2023 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Excavation/Setback/Form/Re-Bar | 6/5/2023 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 7/7/2023 | Partial Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 7/28/2023 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 8/21/2023 | Corrections Issued | EVAN COOPER |
| PLUMBING-Rough | 8/22/2023 | Approved | EVAN COOPER |
| ELECTRICAL-Rough | 8/23/2023 | Corrections Issued | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 8/24/2023 | Corrections Issued | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 9/1/2023 | Partial Approval | EVAN COOPER |
| Interior/Exterior Lathing | 9/15/2023 | Partial Approval | EVAN COOPER |
| Insulation | 9/22/2023 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 9/22/2023 | Partial Approval | ARAM AVEDISIAN |
| Drywall Nailing | 9/29/2023 | Approved | EVAN COOPER |
| Shower Pan | 11/1/2023 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 11/3/2023 | Approved | MICHAEL PELHAM |
| BUILDING-Rough-Frame | 12/19/2023 | Approved | EVAN COOPER |
| Final | 12/19/2023 | Corrections Issued | EVAN COOPER |
| Footing/Foundation/Slab | 12/19/2023 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 12/19/2023 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 12/19/2023 | Approved | EVAN COOPER |