948 S BERNAL AVE 90023

Certificate Information: 948 S BERNAL AVE 90023

Application / Permit
22014-10000-03795
Plan Check / Job No.
B22LA14723
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
2ND STORY ADDITION TO (E) SFD
Permit Issued
Issued on 11/21/2022
Issuing Office
Current Status
CofO Issued on 2/2/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/29/2022 APPLICANT
Assigned to Plan Check Engineer 8/11/2022 CARLOS MONTES
Corrections Issued 8/14/2022 CARLOS MONTES
Quality Review Completed 8/17/2022 GARO TELMI
Plan Check Approved 11/18/2022 CARLOS MONTES
Issued 11/21/2022 APPLICANT
CofO in Progress 1/31/2025 FREDDIE RIVERA
Permit Finaled 2/2/2025 DEROLD HAUFF
Permit Finaled 2/2/2025 DEROLD HAUFF
CofO Issued 2/2/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/30/2022 CINDY QI
Roof/Waste drainage to street Cleared 8/30/2022 CINDY QI
Eng Process Fee Ord 176,300 Cleared 9/1/2022 CINDY QI
Sewer availability Cleared 9/1/2022 CINDY QI
Grading Pre-Inspection Cleared 9/2/2022 KIRK LINKLATER
Clean Up Green Up Cleared 10/18/2022 RUBEN VASQUEZ
GPI Written Notices Cleared 11/18/2022 CARLOS MONTES

Contact Information

Contractor Alloy Construction And Restoration; Lic. No.: 1054043-B       ,
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 11 CEDARWOOD DR      POMONA, CA 91766

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/3/2023 Corrections Issued FREDDIE RIVERA
Footing/Foundation/Slab 6/29/2023 Partial Inspection FREDDIE RIVERA
Special/Order Compliance 6/29/2023 Corrections Issued FREDDIE RIVERA
Deputy Drilled-In Anchors 9/11/2023 Conditional Approval FREDDIE RIVERA
Footing/Foundation/Slab 9/15/2023 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 10/19/2023 Partial Approval FREDDIE RIVERA
Interior/Exterior Lathing 12/13/2023 Partial Inspection FREDDIE RIVERA
Rough-Elec/Plmb/HVAC 12/13/2023 Approved FREDDIE RIVERA
Shower Pan 12/13/2023 Partial Inspection FREDDIE RIVERA
BUILDING-Rough-Frame 12/21/2023 Corrections Issued ENRIQUE MIRELES
ELECTRICAL-Rough 12/21/2023 Not Ready for Inspection ENRIQUE MIRELES
HVAC-Rough 12/21/2023 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Rough 12/21/2023 Not Ready for Inspection ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 2/9/2024 Approved FREDDIE RIVERA
PLUMBING-Rough 2/9/2024 Partial Inspection FREDDIE RIVERA
Rough-Elec/Plmb/HVAC 2/9/2024 Partial Inspection FREDDIE RIVERA
Deputy Wood Construction 2/14/2024 Conditional Approval FREDDIE RIVERA
BUILDING-Rough-Frame 3/12/2024 Approved FREDDIE RIVERA
Green Building Rough 3/12/2024 Approved FREDDIE RIVERA
Insulation 3/12/2024 Conditional Approval FREDDIE RIVERA
Interior/Exterior Lathing 3/12/2024 Approved FREDDIE RIVERA
MERV13>=Rough 3/12/2024 Approved FREDDIE RIVERA
Pre-Inspection 3/12/2024 Corrections Issued FREDDIE RIVERA
Verify Sprinkler Sign Off 3/12/2024 Approved FREDDIE RIVERA
Drywall Nailing 4/17/2024 Approved JOSH MEISTER
Gas Test 8/14/2024 Approved ANTHONY RAMOS
Final 11/15/2024 Corrections Issued FREDDIE RIVERA
Green Building Final 11/15/2024 Conditional Approval FREDDIE RIVERA
MERV13>=Final 11/15/2024 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 11/15/2024 SGSOV Approved FREDDIE RIVERA
Smoke Detectors 11/15/2024 Approved FREDDIE RIVERA
Final 11/27/2024 Partial Inspection FREDDIE RIVERA
Green Building Final 11/27/2024 Approved FREDDIE RIVERA
Final 12/19/2024 OK to Issue CofO FREDDIE RIVERA