6624 N DENNY AVE 91606
Certificate Information: 6624 N DENNY AVE 91606
- Application / Permit
- 22014-10000-03788
- Plan Check / Job No.
- B22LA14676
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION TO (E) GARAGE TO CREATE A (N) DETACHED ADU “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the finaling of the permit.”
- Permit Issued
- Issued on 8/12/2022
- Issuing Office
- Current Status
- CofO Issued on 2/16/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/26/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/26/2022 | SAMUEL GONZALEZ |
| Plan Check Approved | 8/10/2022 | FERNANDO FLORES |
| Issued | 8/12/2022 | APPLICANT |
| CofO in Progress | 2/16/2023 | JOHN HAYES |
| CofO Issued | 2/16/2023 | RONALD MYRICK |
| Permit Finaled | 2/16/2023 | RONALD MYRICK |
Permit Application Clearance Information
| Address approval | Cleared | 7/29/2022 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 7/29/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 8/2/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 8/2/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Arrow Construction Co; Lic. No.: 573067-B | 18729 CLARK DALE AVE #C ARTESIA, CA 90701 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/29/2022 | Corrections Issued | DEANDRE HOFFMAN |
| Underground Mechanical | 9/29/2022 | Not Ready for Inspection | DEANDRE HOFFMAN |
| Excavation/Setback/Form/Re-Bar | 10/13/2022 | Not Ready for Inspection | JOHN HAYES |
| Underground Mechanical | 10/13/2022 | Corrections Issued | JOHN HAYES |
| PLUMBING-Rough | 10/15/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 10/20/2022 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 10/20/2022 | Partial Approval | JENNIFER RABUCHIN |
| Deputy Drilled-In Anchors | 10/24/2022 | Conditional Approval | MICHAEL SMITH |
| Footing/Foundation/Slab | 10/26/2022 | Approved | JOHN HAYES |
| Pre-Inspection | 10/27/2022 | Approved | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 11/22/2022 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 11/28/2022 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 11/28/2022 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 11/28/2022 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 11/28/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| HVAC-Rough | 11/28/2022 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 11/28/2022 | Approved | JENNIFER RABUCHIN |
| Special/Order Compliance | 11/28/2022 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 12/1/2022 | Approved | JOHN HAYES |
| Green Building Rough | 12/1/2022 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 12/1/2022 | Partial Approval | JOHN HAYES |
| Insulation | 12/6/2022 | Approved | JOHN HAYES |
| Drywall Nailing | 12/13/2022 | Approved | JORDAN KUTZLY |
| Interior/Exterior Lathing | 12/13/2022 | Approved | JORDAN KUTZLY |
| Final | 2/13/2023 | Corrections Issued | JOHN HAYES |
| Green Building Final | 2/13/2023 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 2/13/2023 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 2/13/2023 | Not Ready for Inspection | JOHN HAYES |
| Final | 2/15/2023 | OK to Issue CofO | JOHN HAYES |
| Green Building Final | 2/15/2023 | Approved | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 2/15/2023 | SGSOV Approved | JOHN HAYES |
| Smoke Detectors | 2/15/2023 | Approved | JOHN HAYES |