1600 W 21ST ST 90732

Certificate Information: 1600 W 21ST ST 90732

Application / Permit
22014-10000-03787
Plan Check / Job No.
B22LA14673
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO (E) SFD COMPLY WITH DEPARTMENT ORDER effective date 02/25/2022. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
Permit Issued
Issued on 9/14/2022
Issuing Office
Metro
Current Status
CofO Issued on 6/4/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/26/2022 APPLICANT
Assigned to Plan Check Engineer 7/26/2022 DANIEL SANJUAN
Corrections Issued 7/26/2022 DANIEL SANJUAN
Applicant returned to address corrections 9/14/2022 FERNANDO FLORES
Plan Check Approved 9/14/2022 FERNANDO FLORES
Issued 9/14/2022 APPLICANT
CofO in Progress 5/2/2023 PAUL BECKER
Permit Finaled 6/4/2024 PAUL BECKER
CofO Issued 6/4/2024 PAUL BECKER
Permit Finaled 6/4/2024 PAUL BECKER

Permit Application Clearance Information

Grading Pre-Inspection Cleared 8/15/2022 KIRK LINKLATER
Construction near power lines Cleared 8/19/2022 OSCAR CASTRO
Eng Process Fee Ord 176,300 Cleared 8/19/2022 JEANETTE VONG
Roof/Waste drainage to street Cleared 8/19/2022 JEANETTE VONG
Sewer availability Cleared 8/19/2022 JEANETTE VONG

Contact Information

Contractor Owner-Builder       ,
Engineer Hale,, Ronald Richard; Lic. No.: C17056 1869 PALACIOS DR      SAN PEDRO, CA 90732

Inspector Information

KELLY WARNER, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
PAUL BECKER, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
KEITH EDGHILL, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
DANIEL GONZALEZ, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/21/2022 Approved ANDREW BEELI
Footing/Foundation/Slab 10/12/2022 Corrections Issued ANDREW BEELI
Excavation/Setback/Form/Re-Bar 10/18/2022 Approved ANDREW BEELI
Footing/Foundation/Slab 10/18/2022 Approved ANDREW BEELI
BUILDING-Rough-Frame 10/25/2022 Not Ready for Inspection ANDREW BEELI
ELECTRICAL-Rough 10/25/2022 Not Ready for Inspection ANDREW BEELI
Green Building Rough 10/25/2022 Not Ready for Inspection ANDREW BEELI
Insulation 10/25/2022 Not Ready for Inspection ANDREW BEELI
Wood Frame 10/25/2022 Corrections Issued ANDREW BEELI
BUILDING-Rough-Frame 10/31/2022 Corrections Issued ANDREW BEELI
ELECTRICAL-Rough 10/31/2022 Not Ready for Inspection ANDREW BEELI
Green Building Rough 10/31/2022 Not Ready for Inspection ANDREW BEELI
ELECTRICAL-Rough 11/14/2022 Corrections Issued ANDREW BEELI
HVAC-Rough 11/14/2022 Approved ANDREW BEELI
Wood Frame 11/14/2022 Corrections Issued ANDREW BEELI
ELECTRICAL-Rough 11/17/2022 Approved ANDREW BEELI
Insulation 11/17/2022 Approved ANDREW BEELI
Floor/Roof Diaphrgm/Shear Wall 11/21/2022 Approved ANDREW BEELI
Pre-Inspection 3/15/2023 Approved PAUL BECKER
BUILDING-Rough-Frame 3/21/2023 Approved PAUL BECKER
Final 3/21/2023 Not Ready for Inspection PAUL BECKER
Green Building Final 3/21/2023 Approved PAUL BECKER
Green Building Rough 3/21/2023 Approved PAUL BECKER
SGSOV-Seismic Gas S/O Valve 3/21/2023 SGSOV Not Ready PAUL BECKER
Smoke Detectors 3/21/2023 Approved PAUL BECKER
Final 4/7/2023 Not Ready for Inspection PAUL BECKER
SGSOV-Seismic Gas S/O Valve 4/7/2023 SGSOV Not Ready PAUL BECKER
Final 5/2/2023 OK to Issue CofO PAUL BECKER
SGSOV-Seismic Gas S/O Valve 5/2/2023 SGSOV Approved PAUL BECKER