2858-2860 S EDGEHILL DR 90018

Certificate Information: 2858-2860 S EDGEHILL DR 90018

Application / Permit
22014-10000-03784
Plan Check / Job No.
B22LA14668
Group
Building
Type
Bldg-Addition
Sub-Type
Apartment
Primary Use
(1) Accessory Dwelling Unit
Work Description
Detach (E) storage and garage from (E) APT building to enlarge and convert detached structure into two ADU's per GCS 65852.2(e)(1)(D) & LAMC 12.22 A.33 (c)(d) and (g).
Permit Issued
Issued on 4/7/2023
Issuing Office
Metro
Current Status
CofO Issued on 5/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/26/2022 APPLICANT
Assigned to Plan Check Engineer 8/1/2022 GEORGE ALVAREZ
Corrections Issued 8/2/2022 GEORGE ALVAREZ
Building Plans Picked Up 8/5/2022 APPLICANT
Applicant returned to address corrections 10/19/2022 RICARDO RAMIREZ
Applicant returned to address corrections 1/26/2023 LAWRENCE QUIRANTE
Plan Check Approved 2/3/2023 MINA HABILI
Issued 4/7/2023 APPLICANT
CofO in Progress 4/24/2024 ALFREDO LOPEZ
Permit Finaled 5/3/2024 RAFAEL ESPINOZA
CofO Issued 5/3/2024 RAFAEL ESPINOZA
Permit Finaled 5/3/2024 RAFAEL ESPINOZA

Permit Application Clearance Information

Address approval Cleared 8/10/2022 STEVE MELGAR
Roof/Waste drainage to street Cleared 8/10/2022 STEVE MELGAR
ZA Case Cleared 8/10/2022 DALIA MOKAYED
Eng Process Fee Ord 176,300 Cleared 9/26/2022 STEVE MELGAR
Sewer availability Cleared 9/26/2022 STEVE MELGAR
Tenant Habitability Plan Cleared 11/16/2022 ISMAEL HERNANDEZ
Construction near power lines Cleared 1/10/2023 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Carrillo,, Jesus Eduardo; Lic. No.: C77737 8207 BROOKGREEN RD      DOWNEY, CA 90240

Inspector Information

PAUL BAZERKANIAN, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
LUIS CCAMACHO, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
ALAN MORELOS, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/11/2023 Approved MARTIN TAVITIAN
Excavation/Setback/Form/Re-Bar 5/26/2023 Approved ALAN MORELOS
Footing/Foundation/Slab 5/26/2023 Approved ALAN MORELOS
Floor/Roof Diaphrgm/Shear Wall 6/20/2023 Partial Approval MARTIN TAVITIAN
Green Building Rough 7/25/2023 Approved MARTIN TAVITIAN
Insulation 8/9/2023 Approved MARTIN TAVITIAN
Interior/Exterior Lathing 8/9/2023 Approved MARTIN TAVITIAN
Wood Frame 8/9/2023 Approved MARTIN TAVITIAN
Drywall Nailing 8/15/2023 OK to Expire Permit MARTIN TAVITIAN
SGSOV-Seismic Gas S/O Valve 3/5/2024 SGSOV Not Ready RAMAZANALI ALMASI
Final 3/7/2024 Partial Inspection ALFREDO LOPEZ
Green Building Final 3/7/2024 Conditional Approval ALFREDO LOPEZ
SGSOV-Seismic Gas S/O Valve 3/7/2024 SGSOV Approved ALFREDO LOPEZ
Smoke Detectors 3/7/2024 Not Ready for Inspection ALFREDO LOPEZ
Final 3/27/2024 OK to Issue CofO ALFREDO LOPEZ
Green Building Final 3/27/2024 Approved ALFREDO LOPEZ
Smoke Detectors 3/27/2024 Approved ALFREDO LOPEZ