6522 N SHORT WAY 90042

Certificate Information: 6522 N SHORT WAY 90042

Application / Permit
22014-10000-03762
Plan Check / Job No.
B22LA14616
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
*eplan* PROPOSED GROUND FLOOR ADDITION AND SECOND STORY ADDITION TO EXISTING SINGLE FAMILY DWELLING.SCOPE WILL CONSIST OF TWO NEW ROOF DECKS, COMPLETE INTERIOR REMODEL, AND ATTACHED 2-CAR GARAGE. 1 OF 2
Permit Issued
Issued on 2/21/2023
Issuing Office
Current Status
CofO Issued on 1/28/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/27/2022 APPLICANT
Assigned to Plan Check Engineer 8/4/2022 MICHAEL LOPEZ
Corrections Issued 8/15/2022 MICHAEL LOPEZ
Quality Review Completed 8/19/2022 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 2/3/2023 MICHAEL LOPEZ
Plan Check Approved 2/16/2023 MICHAEL LOPEZ
Issued 2/21/2023 APPLICANT
CofO in Progress 1/27/2025 LILIANA PORTILLO
Permit Finaled 1/28/2025 DEROLD HAUFF
Permit Finaled 1/28/2025 DEROLD HAUFF
CofO Issued 1/28/2025 DEROLD HAUFF

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 9/11/2022 ADRIAN SANCHEZ
BHO/Hillside ordinance Cleared 9/11/2022 ADRIAN SANCHEZ
BHO/Hillside ordinance Cleared 9/11/2022 ADRIAN SANCHEZ
BHO/Hillside ordinance Cleared 9/11/2022 ADRIAN SANCHEZ
BHO/Hillside ordinance Cleared 9/11/2022 ADRIAN SANCHEZ
Hydrant and Access approval Cleared 10/8/2022 GILBERT URREA
Eng Process Fee Ord 176,300 Cleared 11/5/2022 ADRIAN SANCHEZ
Low Impact Development Cleared 11/18/2022 ANTHONY VARGAS
"D" conditions Cleared 1/11/2023 RUBEN VASQUEZ
"Q" conditions Cleared 1/11/2023 RUBEN VASQUEZ
ZI Cleared 1/11/2023 RUBEN VASQUEZ
GPI Written Notices Cleared 2/14/2023 MICHAEL LOPEZ
Grading Pre-Inspection Cleared 2/14/2023 ROBERT HUGHES

Contact Information

Contractor Owner-Builder       ,
Engineer Sivushenka,, Mikita; Lic. No.: C87698 22814 DOLOROSA ST      WOODLAND HILLS, CA 91367
Engineer Vardeh,, Edmond; Lic. No.: C56992 43 INVERARY      TRABUCO CANYON, CA 92679
Geologist Hogrefe,, Scott Joseph; Lic. No.: EG1516 3157 ESCOLLERA AVE      SANTA ROSA VALLEY, CA 93012

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/27/2023 Partial Inspection AMY COLIN
Excavation/Setback/Form/Re-Bar 3/20/2023 Partial Approval AMY COLIN
Footing/Foundation/Slab 3/20/2023 Partial Approval AMY COLIN
Excavation/Setback/Form/Re-Bar 4/6/2023 Partial Approval AMY COLIN
Footing/Foundation/Slab 4/6/2023 Partial Approval AMY COLIN
Excavation/Setback/Form/Re-Bar 4/18/2023 Partial Approval AMY COLIN
Footing/Foundation/Slab 4/18/2023 Partial Approval AMY COLIN
Excavation/Setback/Form/Re-Bar 5/3/2023 Not Ready for Inspection AMY COLIN
Floor/Roof Diaphrgm/Shear Wall 5/3/2023 Partial Approval AMY COLIN
Footing/Foundation/Slab 5/3/2023 Not Ready for Inspection AMY COLIN
Excavation/Setback/Form/Re-Bar 5/8/2023 Partial Approval AMY COLIN
Floor/Roof Diaphrgm/Shear Wall 5/8/2023 Partial Approval AMY COLIN
Excavation/Setback/Form/Re-Bar 5/17/2023 Partial Approval AMY COLIN
Excavation/Setback/Form/Re-Bar 6/6/2023 Approved JEFFREY MEAD
Floor/Roof Diaphrgm/Shear Wall 6/6/2023 Partial Approval JEFFREY MEAD
Footing/Foundation/Slab 6/6/2023 Approved JEFFREY MEAD
Deputy Wood Construction 7/10/2023 Conditional Approval AMY COLIN
Floor/Roof Diaphrgm/Shear Wall 7/12/2023 Corrections Issued AMY COLIN
PLUMBING-Rough 9/18/2023 Approved AMY COLIN
ELECTRICAL-Rough 12/6/2023 Approved AMY COLIN
HVAC-Rough 12/6/2023 Approved AMY COLIN
Shower Pan 12/19/2023 Approved AMY COLIN
Wood Frame 12/19/2023 Approved AMY COLIN
Insulation 1/2/2024 Corrections Issued CRAIG VAUGHAN
Insulation 1/9/2024 Approved AMY COLIN
Drywall Nailing 1/18/2024 Approved AMY COLIN
Interior/Exterior Lathing 1/18/2024 Approved AMY COLIN
Interior/Exterior Lathing 1/23/2024 Approved AMY COLIN
BUILDING-Rough-Frame 10/7/2024 Conditional Approval LILIANA PORTILLO
ELECTRICAL-Final 10/7/2024 Not Ready for Inspection LILIANA PORTILLO
Final 10/7/2024 Not Ready for Inspection LILIANA PORTILLO
Green Building Final 10/7/2024 Not Ready for Inspection LILIANA PORTILLO
Green Building Rough 10/7/2024 Approved LILIANA PORTILLO
HVAC-Final 10/7/2024 Not Ready for Inspection LILIANA PORTILLO
PLUMBING-Final 10/7/2024 Not Ready for Inspection LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 10/7/2024 SGSOV Not Ready LILIANA PORTILLO
Smoke Detectors 10/7/2024 Not Ready for Inspection LILIANA PORTILLO
Verify Sprinkler Sign Off 10/7/2024 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 10/15/2024 Approved LILIANA PORTILLO
ELECTRICAL-Final 10/15/2024 Not Ready for Inspection LILIANA PORTILLO
Final 10/15/2024 Corrections Issued LILIANA PORTILLO
Green Building Final 10/15/2024 Not Ready for Inspection LILIANA PORTILLO
HVAC-Final 10/15/2024 Not Ready for Inspection LILIANA PORTILLO
PLUMBING-Final 10/15/2024 Not Ready for Inspection LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 10/15/2024 SGSOV Not Ready LILIANA PORTILLO
Smoke Detectors 10/15/2024 Approved LILIANA PORTILLO
ELECTRICAL-Final 10/22/2024 Approved LILIANA PORTILLO
Final 10/22/2024 Not Ready for Inspection LILIANA PORTILLO
Green Building Final 10/22/2024 Approved LILIANA PORTILLO
HVAC-Final 10/22/2024 Approved LILIANA PORTILLO
PLUMBING-Final 10/22/2024 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 10/22/2024 SGSOV Approved LILIANA PORTILLO
Final 1/24/2025 OK to Issue CofO LILIANA PORTILLO
Service/Power Release 1/24/2025 Approved LILIANA PORTILLO