5116 E RANGE VIEW AVE 90042
Certificate Information: 5116 E RANGE VIEW AVE 90042
- Application / Permit
- 22014-10000-03711
- Plan Check / Job No.
- B22LA13607
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert (E) 2-car garage into ADU and addition of 22 sq ft
- Permit Issued
- Issued on 6/22/2023
- Issuing Office
- Current Status
- CofO in Progress on 5/22/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/15/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/22/2022 | JOE VO |
| Corrections Issued | 7/24/2022 | JOE VO |
| Quality Review Completed | 7/26/2022 | GARO TELMI |
| Applicant returned to address corrections | 1/23/2023 | JOE VO |
| Plan Check Approved | 5/25/2023 | JOE VO |
| Issued | 6/22/2023 | APPLICANT |
| CofO in Progress | 3/16/2026 | DAVID WILLIAMS |
| CofO in Progress | 5/19/2026 | LILIANA PORTILLO |
| No Progress | 5/22/2026 | DEROLD HAUFF |
| CofO in Progress | 5/22/2026 | DEROLD HAUFF |
| CofO in Progress | 5/27/2026 | ALIZAH MAYAGOITIA |
Permit Application Clearance Information
| Address approval | Cleared | 8/31/2022 | TREVOR QUAN |
| Roof/Waste drainage to street | Cleared | 8/31/2022 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 10/17/2022 | TREVOR QUAN |
| Sewer availability | Cleared | 10/17/2022 | TREVOR QUAN |
| Grading Pre-Inspection | Cleared | 5/25/2023 | JOE VO |
Contact Information
| Contractor | Powell Construction Llc; Lic. No.: 895535-B | 3835 E THOUSAND OAKS BLVD SUITE R 247 WESTLAKE VILLAGE, CA 91362 |
| Engineer | Rooks,, Bret; Lic. No.: C63445 | 174 LOMA BONITA SAN LUIS OBISPO, CA 93401 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Interior/Exterior Lathing | 11/20/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 3/16/2026 | Not Ready for Inspection | DAVID WILLIAMS |
| Final | 3/16/2026 | Not Ready for Inspection | DAVID WILLIAMS |
| Footing/Foundation/Slab | 3/16/2026 | Not Ready for Inspection | DAVID WILLIAMS |
| Green Building Final | 3/16/2026 | Not Ready for Inspection | DAVID WILLIAMS |
| Green Building Rough | 3/16/2026 | Not Ready for Inspection | DAVID WILLIAMS |
| SGSOV-Seismic Gas S/O Valve | 3/16/2026 | SGSOV Not Ready | DAVID WILLIAMS |
| Smoke Detectors | 3/16/2026 | Not Ready for Inspection | DAVID WILLIAMS |
| Final | 5/20/2026 | Not Ready for Inspection | DAVID WILLIAMS |