13831 W HARTSOOK ST 91423
Certificate Information: 13831 W HARTSOOK ST 91423
- Application / Permit
- 22014-10000-03708
- Plan Check / Job No.
- B22LA14445
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan. ADDITION TO EXISTING GARAGE AND ADDITION OF 2ND STORY ADU
- Permit Issued
- Issued on 12/24/2022
- Issuing Office
- Current Status
- CofO Issued on 1/23/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/23/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/18/2022 | CRYSTEL MAALOUF |
| Corrections Issued | 8/31/2022 | CRYSTEL MAALOUF |
| Quality Review Completed | 9/2/2022 | FARUK SEZER |
| Applicant returned to address corrections | 11/10/2022 | CRYSTEL MAALOUF |
| Plan Check Approved | 12/23/2022 | CRYSTEL MAALOUF |
| Issued | 12/24/2022 | APPLICANT |
| CofO in Progress | 1/17/2024 | MISAEL ESPARZA |
| CofO Issued | 1/23/2024 | RUBEN SALAS |
| Permit Finaled | 1/23/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 9/16/2022 | MEGAN GODINEZ |
| Address approval | Cleared | 9/19/2022 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 10/31/2022 | MEGAN GODINEZ |
| Sewer availability | Cleared | 11/1/2022 | MEGAN GODINEZ |
| Public Works-Highway Ded. | Cleared | 11/1/2022 | MEGAN GODINEZ |
| Public Works-Open Permits | Cleared | 11/1/2022 | MEGAN GODINEZ |
| Public Works-Sewers | Cleared | 11/1/2022 | MEGAN GODINEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Basma,, Ali J; Lic. No.: C53080 | 21757 DEVONSHIRE ST. SUITE 3 CANOGA PARK, CA 91311 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/25/2023 | Conditional Approval | MICHAEL SMITH |
| Footing/Foundation/Slab | 1/31/2023 | Corrections Issued | MISAEL ESPARZA |
| Footing/Foundation/Slab | 2/6/2023 | Approved | MISAEL ESPARZA |
| Deputy Reinf. Concrete | 2/8/2023 | Conditional Approval | ROBERT GOLD |
| Deputy Drilled-In Anchors | 3/28/2023 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 3/30/2023 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 5/22/2023 | Not Ready for Inspection | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 5/22/2023 | Corrections Issued | THOMAS FINNILA |
| PLUMBING-Rough | 5/22/2023 | Approved | THOMAS FINNILA |
| Deputy Wood Construction | 5/25/2023 | Conditional Approval | MICHAEL SMITH |
| BUILDING-Rough-Frame | 6/5/2023 | Partial Approval | THOMAS FINNILA |
| ELECTRICAL-Rough | 6/5/2023 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 6/20/2023 | Approved | JOHN COLEMAN |
| BUILDING-Rough-Frame | 6/23/2023 | Corrections Issued | JOHN COLEMAN |
| Insulation | 6/30/2023 | Conditional Approval | JOHN COLEMAN |
| Wood Frame | 7/18/2023 | Conditional Approval | MISAEL ESPARZA |
| Drywall Nailing | 8/1/2023 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Final | 8/22/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Final | 11/29/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| Final | 11/29/2023 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 11/29/2023 | SGSOV Not Ready | CHRISTOPHER ROJAS |
| Smoke Detectors | 11/29/2023 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 12/13/2023 | Approved | MISAEL ESPARZA |
| Final | 12/13/2023 | Corrections Issued | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 12/13/2023 | SGSOV Approved | MISAEL ESPARZA |
| Final | 1/12/2024 | OK to Issue CofO | MISAEL ESPARZA |