10731 W WESTMINSTER AVE 90034
Certificate Information: 10731 W WESTMINSTER AVE 90034
- Application / Permit
- 22014-10000-03691
- Plan Check / Job No.
- B22LA14333
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED GARAGE CONVERSION AND ADDITION INTO A.D.U. PER LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 12/7/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/10/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/21/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/25/2022 | LAWRENCE QUIRANTE |
| Corrections Issued | 7/29/2022 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 8/2/2022 | APPLICANT |
| Applicant returned to address corrections | 10/7/2022 | RACHEL BEYENE |
| Plan Check Approved | 10/18/2022 | ADAM HEGAZI |
| Issued | 12/7/2022 | APPLICANT |
| CofO in Progress | 6/13/2023 | DAVID FEILER |
| Permit Finaled | 8/10/2023 | DANIEL ORRANTE |
| CofO Issued | 8/10/2023 | DANIEL ORRANTE |
| Permit Finaled | 8/10/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 8/11/2022 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/16/2022 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 8/16/2022 | ANTHONY MAINEZ |
| Specific Plan | Cleared | 9/13/2022 | PEDRO AYALA |
| Grading Pre-Inspection | Cleared | 10/17/2022 | KIRK LINKLATER |
| Roof/Waste drainage to street | Cleared | 10/27/2022 | ANTHONY MAINEZ |
Contact Information
| Contractor | Martinez Zadot A; Lic. No.: 1050143-B | 4042 WEST BLVD APT A LOS ANGELES, CA 90008 |
| Engineer | Abdel, Messih, Raymond Philippe; Lic. No.: C79913 | 30603 YOSEMITE DRIVE CASTAIC, CA 93184 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/30/2022 | Conditional Approval | JOHNNY MIRANDA |
| PLUMBING-Rough | 1/11/2023 | Partial Approval | JOHNNY MIRANDA |
| Sewer | 1/11/2023 | Approved | JOHNNY MIRANDA |
| Excavation/Setback/Form/Re-Bar | 1/12/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| Excavation/Setback/Form/Re-Bar | 1/17/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| Excavation/Setback/Form/Re-Bar | 1/20/2023 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 2/8/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 2/8/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 2/8/2023 | Conditional Approval | JESUS RODRIGUEZ |
| Green Building Rough | 2/8/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| PLUMBING-Rough | 2/8/2023 | Approved | JESUS RODRIGUEZ |
| Underground Mechanical | 2/8/2023 | Partial Approval | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 2/9/2023 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 2/14/2023 | Partial Approval | JOHNNY MIRANDA |
| Green Building Rough | 2/14/2023 | Approved | JOHNNY MIRANDA |
| Pre-Inspection | 2/14/2023 | Partial Approval | JOHNNY MIRANDA |
| Green Building Rough | 2/17/2023 | Approved | JOHNNY MIRANDA |
| Insulation | 2/17/2023 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 2/17/2023 | Partial Approval | JOHNNY MIRANDA |
| Drywall Nailing | 2/24/2023 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 3/22/2023 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 5/18/2023 | Approved | JEREMY TODD |
| Final | 5/18/2023 | Not Ready for Inspection | JEREMY TODD |
| Footing/Foundation/Slab | 5/18/2023 | Approved | JEREMY TODD |
| Green Building Final | 5/18/2023 | Approved | JEREMY TODD |
| SGSOV-Seismic Gas S/O Valve | 5/18/2023 | SGSOV Not Ready | JEREMY TODD |
| Smoke Detectors | 5/18/2023 | Approved | JEREMY TODD |
| ELECTRICAL-Final | 5/23/2023 | Approved | JOHNNY MIRANDA |
| Final | 5/23/2023 | Corrections Issued | JOHNNY MIRANDA |
| HVAC-Final | 5/23/2023 | Corrections Issued | JOHNNY MIRANDA |
| PLUMBING-Final | 5/23/2023 | Corrections Issued | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 5/23/2023 | SGSOV Not Ready | JOHNNY MIRANDA |
| Final | 5/31/2023 | Corrections Issued | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 5/31/2023 | SGSOV Approved | JOHNNY MIRANDA |
| Final | 6/13/2023 | OK to Issue CofO | DAVID FEILER |