5016 S 3RD AVE 90043
Certificate Information: 5016 S 3RD AVE 90043
- Application / Permit
- 22014-10000-03690
- Plan Check / Job No.
- B22LA14327
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- SMALL ADDITION TO (E) SFD
- Permit Issued
- Issued on 8/26/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/21/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/21/2022 | ZAW HAN |
| Corrections Issued | 7/21/2022 | ZAW HAN |
| Plan Check Approved | 8/26/2022 | FERNANDO FLORES |
| Issued | 8/26/2022 | APPLICANT |
| CofO in Progress | 11/8/2023 | ANTHONY EGSON |
| Permit Finaled | 11/21/2023 | DEROLD HAUFF |
| CofO Issued | 11/21/2023 | DEROLD HAUFF |
| Permit Finaled | 11/21/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 8/25/2022 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 8/26/2022 | JEANETTE VONG |
Contact Information
| Contractor | American Home Improvement Inc; Lic. No.: 835537-B | 20335 VENTURA BLVD #422 WOODLAND HILLS, CA 91364 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/17/2022 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 10/28/2022 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 11/10/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Footing/Foundation/Slab | 11/16/2022 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 11/30/2022 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 11/30/2022 | Corrections Issued | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/6/2022 | Partial Approval | ANTHONY EGSON |
| Green Building Rough | 12/6/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Insulation | 12/6/2022 | Not Ready for Inspection | ANTHONY EGSON |
| PLUMBING-Rough | 12/6/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Insulation | 12/9/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 12/21/2022 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/18/2023 | Partial Approval | ANTHONY EGSON |
| BUILDING-Rough-Frame | 2/14/2023 | Corrections Issued | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 2/14/2023 | Not Ready for Inspection | ENRIQUE MIRELES |
| Green Building Rough | 2/14/2023 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 2/14/2023 | Not Ready for Inspection | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 2/28/2023 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Rough | 2/28/2023 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Rough | 2/28/2023 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 2/28/2023 | Not Ready for Inspection | ANTHONY EGSON |
| BUILDING-Rough-Frame | 3/21/2023 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Rough | 3/21/2023 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 3/21/2023 | Approved | ANTHONY EGSON |
| Deputy Wood Construction | 3/28/2023 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 4/5/2023 | Approved | ANTHONY EGSON |
| ELECTRICAL-Rough | 4/5/2023 | Approved | ANTHONY EGSON |
| ELECTRICAL-Rough | 4/7/2023 | Approved | ANTHONY EGSON |
| Service/Power Release | 4/7/2023 | Approved | ANTHONY EGSON |
| Insulation | 4/13/2023 | Approved | ANTHONY EGSON |
| Drywall Nailing | 4/19/2023 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 4/26/2023 | Approved | ANTHONY EGSON |
| Shower Pan | 4/26/2023 | Corrections Issued | ANTHONY EGSON |
| Final | 7/11/2023 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 7/11/2023 | Corrections Issued | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 7/11/2023 | SGSOV Not Ready | ANTHONY EGSON |
| Smoke Detectors | 7/11/2023 | Approved | ANTHONY EGSON |
| Final | 7/24/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Final | 7/24/2023 | Approved | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 7/24/2023 | SGSOV Not Ready | ANTHONY EGSON |
| Final | 9/26/2023 | Corrections Issued | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 9/26/2023 | SGSOV Approved | ANTHONY EGSON |
| Final | 11/8/2023 | OK to Issue CofO | ANTHONY EGSON |