3743 N CODY ROAD 91403
Certificate Information: 3743 N CODY ROAD 91403
- Application / Permit
- 22014-10000-03685
- Plan Check / Job No.
- B22LA14274
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 38'x16'-5" Ground-Floor Addition and Interior Remodel to (E) 1-story SFD w/ attch. Garage
- Permit Issued
- Issued on 6/29/2023
- Issuing Office
- Current Status
- CofO Issued on 11/1/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/21/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/25/2022 | AUNG SOE |
| Corrections Issued | 7/29/2022 | AUNG SOE |
| Building Plans Picked Up | 8/1/2022 | APPLICANT |
| Applicant returned to address corrections | 6/7/2023 | CRISTINA SALAZAR |
| Applicant returned to address corrections | 6/14/2023 | MICHAEL LANZONE |
| Plan Check Approved | 6/29/2023 | MICHAEL LANZONE |
| Issued | 6/29/2023 | APPLICANT |
| CofO in Progress | 10/24/2024 | JACK KARGODORIAN |
| Permit Finaled | 11/1/2024 | DANIEL ORRANTE |
| CofO Issued | 11/1/2024 | DANIEL ORRANTE |
| Permit Finaled | 11/1/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 8/4/2022 | DAGOVERTO GUERRERO |
| BHO/Hillside ordinance | Cleared | 8/4/2022 | DAGOVERTO GUERRERO |
| BHO/Hillside ordinance | Cleared | 8/4/2022 | DAGOVERTO GUERRERO |
| BHO/Hillside ordinance | Cleared | 8/4/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 8/4/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 8/4/2022 | DAGOVERTO GUERRERO |
| Hydrant and Access approval | Cleared | 8/26/2022 | RUEL COLE |
| Distance to fire station | Cleared | 9/29/2022 | RUEL COLE |
| Low Impact Development | Cleared | 11/1/2022 | MARTIN FRAGOSO |
| Specific Plan | Cleared | 3/6/2023 | OLGA AYALA |
| BHO/Hillside ordinance | Cleared | 4/13/2023 | DAGOVERTO GUERRERO |
| GPI Written Notices | Cleared | 6/7/2023 | AUNG SOE |
| Grading Pre-Inspection | Cleared | 6/7/2023 | AUNG SOE |
| Roof/Waste drainage to street | Cleared | 6/8/2023 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/16/2023 | Partial Approval | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 8/25/2023 | Not Ready for Inspection | THOMAS FINNILA |
| Footing/Foundation/Slab | 8/25/2023 | Corrections Issued | THOMAS FINNILA |
| Deputy Drilled-In Anchors | 8/28/2023 | Conditional Approval | ROBERT GOLD |
| Excavation/Setback/Form/Re-Bar | 8/30/2023 | Not Ready for Inspection | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 9/1/2023 | Conditional Approval | THOMAS FINNILA |
| PLUMBING-Rough | 9/1/2023 | Partial Approval | THOMAS FINNILA |
| Deputy Drilled-In Anchors | 11/16/2023 | Conditional Approval | DAVID MATSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/20/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Rough-Elec/Plmb/HVAC | 2/20/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Structural Steel Frame | 2/20/2024 | Not Ready for Inspection | THOMAS FINNILA |
| BUILDING-Rough-Frame | 2/22/2024 | Partial Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 2/22/2024 | Partial Approval | THOMAS FINNILA |
| Green Building Rough | 2/22/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Rough-Elec/Plmb/HVAC | 2/22/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Deputy Drilled-In Anchors | 2/29/2024 | Conditional Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 2/29/2024 | Partial Approval | THOMAS FINNILA |
| Rough-Elec/Plmb/HVAC | 2/29/2024 | Corrections Issued | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 3/7/2024 | Partial Approval | THOMAS FINNILA |
| Rough-Elec/Plmb/HVAC | 3/7/2024 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 3/15/2024 | Corrections Issued | THOMAS FINNILA |
| Rough-Elec/Plmb/HVAC | 3/15/2024 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 3/19/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Wood Frame | 3/19/2024 | Approved | THOMAS FINNILA |
| Insulation | 3/21/2024 | Corrections Issued | THOMAS FINNILA |
| Interior/Exterior Lathing | 3/21/2024 | Partial Approval | THOMAS FINNILA |
| Shower Pan | 3/21/2024 | Approved | THOMAS FINNILA |
| Insulation | 3/27/2024 | Partial Approval | MISAEL ESPARZA |
| Interior/Exterior Lathing | 3/27/2024 | Approved | MISAEL ESPARZA |
| Insulation | 4/2/2024 | Approved | THOMAS FINNILA |
| Drywall Nailing | 4/16/2024 | Approved | THOMAS FINNILA |
| BUILDING-Rough-Frame | 10/2/2024 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Final | 10/2/2024 | Not Ready for Inspection | JACK KARGODORIAN |
| Final | 10/2/2024 | Corrections Issued | JACK KARGODORIAN |
| Footing/Foundation/Slab | 10/2/2024 | Approved | JACK KARGODORIAN |
| Green Building Final | 10/2/2024 | Not Ready for Inspection | JACK KARGODORIAN |
| Green Building Rough | 10/2/2024 | Approved | JACK KARGODORIAN |
| HVAC-Final | 10/2/2024 | Approved | JACK KARGODORIAN |
| PLUMBING-Final | 10/2/2024 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 10/2/2024 | SGSOV Not Ready | JACK KARGODORIAN |
| Smoke Detectors | 10/2/2024 | Approved | JACK KARGODORIAN |
| Final | 10/3/2024 | Corrections Issued | JACK KARGODORIAN |
| ELECTRICAL-Final | 10/23/2024 | Approved | JACK KARGODORIAN |
| Final | 10/23/2024 | OK to Issue CofO | JACK KARGODORIAN |
| Green Building Final | 10/23/2024 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 10/23/2024 | SGSOV Approved | JACK KARGODORIAN |