430-430 1/2 E 119TH ST 90061
Certificate Information: 430-430 1/2 E 119TH ST 90061
- Application / Permit
- 22014-10000-03683
- Plan Check / Job No.
- B22LA14269
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED ONE STORY ADDITION TO BE USED AS PART OF ADU (348.45 SQ. FT.) AND PART OF EXISTING AREA TO BE USED AS PART OF ADU (358.85 SQ. FT. ) IN EXISTING ONE STORY SINGLE FAMILY DEWLLING , attached ADU per LAMC 12.22 A.33(c)and (e)
- Permit Issued
- Issued on 4/21/2023
- Issuing Office
- Current Status
- CofO Issued on 9/28/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/21/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/25/2022 | AUNG SOE |
| Corrections Issued | 7/29/2022 | AUNG SOE |
| Building Plans Picked Up | 8/3/2022 | APPLICANT |
| Applicant returned to address corrections | 1/25/2023 | WEIJIAN HUANG |
| Plan Check Approved | 1/30/2023 | MINA HABILI |
| Issued | 4/21/2023 | APPLICANT |
| CofO in Progress | 9/22/2023 | JOHN KLARIN |
| Permit Finaled | 9/28/2023 | ANSON MAGLASANG |
| CofO Issued | 9/28/2023 | ANSON MAGLASANG |
| Permit Finaled | 9/28/2023 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 10/13/2022 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 10/13/2022 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 10/20/2022 | WALLIE JONG |
| Sewer availability | Cleared | 1/26/2023 | WALLIE JONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lu,, Yi; Lic. No.: S5678 | P O BOX 2754 PALOS VERDES PENINSULA, CA 90274 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/4/2023 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 5/12/2023 | Partial Approval | JOHN KLARIN |
| Green Building Rough | 5/12/2023 | Not Ready for Inspection | JOHN KLARIN |
| MERV13>=Rough | 5/12/2023 | Not Ready for Inspection | JOHN KLARIN |
| Insulation | 5/16/2023 | Partial Approval | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 5/17/2023 | Partial Approval | JOHN KLARIN |
| ELECTRICAL-Rough | 6/1/2023 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 6/1/2023 | Corrections Issued | JOHN KLARIN |
| HVAC-Rough | 6/8/2023 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 6/8/2023 | Approved | JOHN KLARIN |
| Insulation | 6/13/2023 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 6/13/2023 | Not Ready for Inspection | JOHN KLARIN |
| Drywall Nailing | 6/16/2023 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 6/16/2023 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 7/25/2023 | Approved | JOHN KLARIN |
| Final | 7/25/2023 | Corrections Issued | JOHN KLARIN |
| Green Building Final | 7/25/2023 | Corrections Issued | JOHN KLARIN |
| Green Building Rough | 7/25/2023 | Approved | JOHN KLARIN |
| MERV13>=Final | 7/25/2023 | Approved | JOHN KLARIN |
| MERV13>=Rough | 7/25/2023 | Approved | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 7/25/2023 | SGSOV Approved | JOHN KLARIN |
| Smoke Detectors | 7/25/2023 | Approved | JOHN KLARIN |
| Final | 7/31/2023 | Corrections Issued | JOHN KLARIN |
| Green Building Final | 7/31/2023 | Approved | JOHN KLARIN |
| ELECTRICAL-Final | 8/9/2023 | Approved | JOHN KLARIN |
| Final | 8/9/2023 | Corrections Issued | JOHN KLARIN |
| HVAC-Final | 8/9/2023 | Approved | JOHN KLARIN |
| PLUMBING-Final | 8/9/2023 | Approved | JOHN KLARIN |
| Final | 9/21/2023 | OK to Issue CofO | JOHN KLARIN |
| Service/Power Release | 9/21/2023 | Approved | JOHN KLARIN |