12541 W MITCHELL AVE 90066
Certificate Information: 12541 W MITCHELL AVE 90066
- Application / Permit
- 22014-10000-03672
- Plan Check / Job No.
- B22LA14202
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan 57 SQFT ADDITION TO 1ST STORY AND 2ND STORY ADDITION TO SINGLE FAMILY DWELLING.
- Permit Issued
- Issued on 10/13/2022
- Issuing Office
- Current Status
- CofO Issued on 12/30/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/20/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/28/2022 | NGHI SU |
| Corrections Issued | 8/1/2022 | NGHI SU |
| Quality Review Completed | 8/4/2022 | GARO TELMI |
| Applicant returned to address corrections | 9/15/2022 | NGHI SU |
| Plan Check Approved | 10/13/2022 | NGHI SU |
| Issued | 10/13/2022 | APPLICANT |
| CofO in Progress | 12/21/2023 | JESUS RODRIGUEZ |
| Permit Finaled | 12/30/2023 | DANIEL ORRANTE |
| CofO Issued | 12/30/2023 | DANIEL ORRANTE |
| Permit Finaled | 12/30/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Sewer availability | Cleared | 8/8/2022 | CATHERINE ADROVER |
| Eng Process Fee Ord 176,300 | Cleared | 8/9/2022 | CATHERINE ADROVER |
| Specific Plan | Cleared | 8/15/2022 | EDUARDO HERMOSO |
| Low Impact Development | Cleared | 9/1/2022 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 9/6/2022 | CATHERINE ADROVER |
Contact Information
| Architect | Kellen,, David; Lic. No.: C15684 | 2701 AIRPORT AVE 202 SANTA MONICA, CA 90405 |
| Contractor | Owner-Builder | , |
| Engineer | Almalla,, Dean; Lic. No.: C58024 | 15053 VENTURA BLVD STE 205 SHERMAN OAKS, CA 91403 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/2/2022 | Conditional Approval | JESUS RODRIGUEZ |
| Deputy Drilled-In Anchors | 12/5/2022 | Conditional Approval | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 12/8/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Green Building Rough | 12/8/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Deputy Reinf. Concrete | 12/9/2022 | Approved | JESUS RODRIGUEZ |
| Deputy Reinf. Concrete | 12/19/2022 | Conditional Approval | JESUS RODRIGUEZ |
| Deputy Other (see comments) | 12/20/2022 | Conditional Approval | DAVID FEILER |
| Deputy Reinf. Concrete | 12/20/2022 | No Access for Inspection | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 12/27/2022 | Partial Approval | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 12/27/2022 | Approved | JESUS RODRIGUEZ |
| Special/Order Compliance | 12/27/2022 | Partial Inspection | CLAYTON GRAHAM |
| Special/Order Compliance | 12/28/2022 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 1/24/2023 | Partial Approval | JESUS RODRIGUEZ |
| PLUMBING-Rough | 1/24/2023 | Partial Approval | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 2/15/2023 | Partial Approval | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/11/2023 | Partial Approval | HERBERT GIRON |
| PLUMBING-Rough | 5/17/2023 | Conditional Approval | BOBBY KEY |
| ELECTRICAL-Final | 6/6/2023 | Corrections Issued | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 6/6/2023 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/6/2023 | Corrections Issued | JESUS RODRIGUEZ |
| HVAC-Rough | 6/6/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 6/6/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/17/2023 | Conditional Approval | JESUS RODRIGUEZ |
| Insulation | 6/17/2023 | Conditional Approval | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 6/27/2023 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 6/27/2023 | Approved | JESUS RODRIGUEZ |
| Insulation | 6/27/2023 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 6/27/2023 | Approved | JESUS RODRIGUEZ |
| Shower Pan | 6/27/2023 | Approved | JESUS RODRIGUEZ |
| Verify Sprinkler Sign Off | 6/27/2023 | Approved | JESUS RODRIGUEZ |
| Sewer | 7/10/2023 | Approved | JESUS RODRIGUEZ |
| Underground Mechanical | 7/10/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Drywall Nailing | 7/20/2023 | Approved | JESUS RODRIGUEZ |
| Underground Mechanical | 7/20/2023 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 8/22/2023 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 9/27/2023 | Approved | JESUS RODRIGUEZ |
| Service/Power Release | 9/27/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Service/Power Release | 9/29/2023 | Approved | JESUS RODRIGUEZ |
| Gas Test | 10/3/2023 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 10/3/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 10/3/2023 | Approved | JESUS RODRIGUEZ |
| Final | 10/11/2023 | Corrections Issued | CLAYTON GRAHAM |
| Green Building Final | 10/11/2023 | Approved | CLAYTON GRAHAM |
| SGSOV-Seismic Gas S/O Valve | 10/11/2023 | SGSOV Approved | CLAYTON GRAHAM |
| Smoke Detectors | 10/11/2023 | Approved | CLAYTON GRAHAM |
| Final | 11/20/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Final | 12/20/2023 | OK to Issue CofO | JESUS RODRIGUEZ |