502 1/4-3/4 E 64TH ST 90003

Certificate Information: 502 1/4-3/4 E 64TH ST 90003

Application / Permit
22014-10000-03664
Plan Check / Job No.
B22LA14173
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 3 CAR DETACHED GARAGE AND ADD TO BECOME 2 ADU's (Two ADUs per State Law, CA Govt. Code 65852.2(e)(1)(D) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g)) Framing to comply with WFPP.
Permit Issued
Issued on 8/22/2022
Issuing Office
Valley
Current Status
CofO Issued on 4/8/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/20/2022 APPLICANT
Assigned to Plan Check Engineer 7/22/2022 AUNG SOE
Corrections Issued 7/25/2022 AUNG SOE
Building Plans Picked Up 7/27/2022 APPLICANT
Applicant returned to address corrections 8/11/2022 LUKE GONZALES
Plan Check Approved 8/16/2022 RICARDO RAMIREZ
Issued 8/22/2022 APPLICANT
CofO in Progress 4/6/2023 BRENDAN MORELLI
Permit Finaled 4/8/2023 DEROLD HAUFF
CofO Issued 4/8/2023 DEROLD HAUFF
Permit Finaled 4/8/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/4/2022 TREVOR QUAN
Roof/Waste drainage to street Cleared 8/4/2022 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 8/8/2022 TREVOR QUAN
Sewer availability Cleared 8/8/2022 TREVOR QUAN

Contact Information

Contractor Jkc Construction & Design; Lic. No.: 1007078-B 18880 WELLS DRIVE      TARZANA, CA 91356

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/7/2022 Not Ready for Inspection SABAS ALONSO
Pre-Inspection 9/12/2022 Partial Inspection LILIANA PORTILLO
Pre-Inspection 10/20/2022 Partial Inspection SHAVONNE ESPINOZA
Pre-Inspection 10/24/2022 Approved ALIZAH MAYAGOITIA
Excavation/Setback/Form/Re-Bar 11/9/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
PLUMBING-Rough 11/9/2022 Partial Approval ALIZAH MAYAGOITIA
Excavation/Setback/Form/Re-Bar 11/16/2022 Approved SCOTT FINNILA
Footing/Foundation/Slab 11/16/2022 Conditional Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 11/30/2022 Partial Approval JULIAN AMAYA
Floor/Roof Diaphrgm/Shear Wall 12/8/2022 Partial Approval JULIAN AMAYA
Interior/Exterior Lathing 12/13/2022 Partial Approval BRENDAN MORELLI
BUILDING-Rough-Frame 12/15/2022 Partial Inspection BRENDAN MORELLI
ELECTRICAL-Rough 12/15/2022 Approved BRENDAN MORELLI
Green Building Rough 12/15/2022 Partial Approval BRENDAN MORELLI
HVAC-Rough 12/15/2022 Conditional Approval BRENDAN MORELLI
PLUMBING-Rough 12/15/2022 Approved BRENDAN MORELLI
BUILDING-Rough-Frame 12/20/2022 Approved BRENDAN MORELLI
Green Building Rough 12/20/2022 Approved BRENDAN MORELLI
Sewer 12/20/2022 Approved BRENDAN MORELLI
Insulation 12/22/2022 Conditional Approval BRENDAN MORELLI
Drywall Nailing 12/29/2022 Approved BRENDAN MORELLI
Interior/Exterior Lathing 12/29/2022 Approved BRENDAN MORELLI
ELECTRICAL-Rough 1/12/2023 Corrections Issued BRENDAN MORELLI
Underground Mechanical 1/12/2023 Approved BRENDAN MORELLI
Underground Mechanical 2/23/2023 Approved BRENDAN MORELLI
Service/Power Release 3/3/2023 Approved BRENDAN MORELLI
Final 3/31/2023 No Access for Inspection ANTHONY EGSON
Footing/Foundation/Slab 3/31/2023 No Access for Inspection ANTHONY EGSON
Green Building Final 3/31/2023 No Access for Inspection ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 3/31/2023 SGSOV Not Ready ANTHONY EGSON
Smoke Detectors 3/31/2023 No Access for Inspection ANTHONY EGSON
ELECTRICAL-Final 4/5/2023 Approved BRENDAN MORELLI
Final 4/5/2023 OK to Issue CofO BRENDAN MORELLI
Footing/Foundation/Slab 4/5/2023 Approved BRENDAN MORELLI
Gas Test 4/5/2023 Approved BRENDAN MORELLI
Green Building Final 4/5/2023 Approved BRENDAN MORELLI
HVAC-Final 4/5/2023 Approved BRENDAN MORELLI
PLUMBING-Final 4/5/2023 Approved BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 4/5/2023 SGSOV Approved BRENDAN MORELLI
Smoke Detectors 4/5/2023 Approved BRENDAN MORELLI