2725 W AVENUE 31 90065

Certificate Information: 2725 W AVENUE 31 90065

Application / Permit
22014-10000-03652
Plan Check / Job No.
B22LA14148
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION AND REMODEL TO (E) SFD
Permit Issued
Issued on 3/6/2023
Issuing Office
Metro
Current Status
CofO Issued on 7/30/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/19/2022 APPLICANT
Assigned to Plan Check Engineer 7/25/2022 LAWRENCE QUIRANTE
Corrections Issued 7/27/2022 LAWRENCE QUIRANTE
Building Plans Picked Up 7/29/2022 APPLICANT
Applicant returned to address corrections 8/9/2022 MINA HABILI
Applicant returned to address corrections 8/10/2022 LAWRENCE QUIRANTE
Plan Check Approved 3/3/2023 FERNANDO FLORES
Issued 3/6/2023 APPLICANT
CofO in Progress 7/29/2024 BRIAN SULLIVAN
Permit Finaled 7/30/2024 RONALD MYRICK
CofO Issued 7/30/2024 RONALD MYRICK
Permit Finaled 7/30/2024 RONALD MYRICK

Permit Application Clearance Information

Sewer availability Cleared 8/4/2022 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 8/8/2022 CELINA MORENO
Roof/Waste drainage to street Cleared 8/8/2022 CELINA MORENO
Supp. Use District POD/CDO/TDO Cleared 3/1/2023 RYAN LY
Grading Pre-Inspection Cleared 3/3/2023 KIRK LINKLATER

Contact Information

Contractor Kafe Design & Construction; Lic. No.: 977712-B 317 E RAMONA ROAD      ALHAMBRA, CA 91801
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 11 CEDARWOOD DR      POMONA, CA 91766

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 5/3/2023 Approved OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 7/6/2023 Corrections Issued HAMIK HARTOUNIAN
Underground Mechanical 7/6/2023 Not Ready for Inspection HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 7/13/2023 Corrections Issued HAMIK HARTOUNIAN
Pre-Inspection 7/13/2023 Not Ready for Inspection HAMIK HARTOUNIAN
Pre-Inspection 8/8/2023 No Access for Inspection HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 10/11/2023 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 10/11/2023 Not Ready for Inspection HAMIK HARTOUNIAN
BUILDING-Rough-Frame 11/6/2023 Partial Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 11/6/2023 Approved HAMIK HARTOUNIAN
Green Building Rough 11/6/2023 Not Ready for Inspection HAMIK HARTOUNIAN
ELECTRICAL-Rough 12/6/2023 Corrections Issued HAMIK HARTOUNIAN
PLUMBING-Rough 12/6/2023 Not Ready for Inspection HAMIK HARTOUNIAN
ELECTRICAL-Rough 12/8/2023 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 12/21/2023 Conditional Approval HAMIK HARTOUNIAN
PLUMBING-Rough 12/21/2023 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 12/26/2023 Approved ROY SPAULDING
Green Building Rough 12/26/2023 Approved ROY SPAULDING
Insulation 12/29/2023 Corrections Issued HAMIK HARTOUNIAN
HVAC-Rough 1/5/2024 Not Ready for Inspection HAMIK HARTOUNIAN
Insulation 1/5/2024 Not Ready for Inspection HAMIK HARTOUNIAN
HVAC-Rough 1/17/2024 Approved HAMIK HARTOUNIAN
Insulation 1/17/2024 Not Ready for Inspection HAMIK HARTOUNIAN
Insulation 1/23/2024 Approved HAMIK HARTOUNIAN
Drywall Nailing 2/1/2024 Approved HAMIK HARTOUNIAN
Final 6/6/2024 Not Ready for Inspection THOMAS LOGRASSO
Final 6/13/2024 Corrections Issued THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 6/13/2024 SGSOV Not Ready THOMAS LOGRASSO
Smoke Detectors 6/13/2024 Approved THOMAS LOGRASSO
Final 6/26/2024 OK to Issue CofO BRIAN SULLIVAN
Green Building Final 6/26/2024 Approved BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 6/26/2024 SGSOV Approved BRIAN SULLIVAN