17035 W CANTARA ST 91406
Certificate Information: 17035 W CANTARA ST 91406
- Application / Permit
- 22014-10000-03651
- Plan Check / Job No.
- B22LA14129
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISITING GARAGE (334 SF) WITH AN ADDITION OF 32 SF INTO A 366 SF ACCESSORY DWELLING UNIT per Ordinance, LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 12/22/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/16/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/19/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/22/2022 | ZAW HAN |
| Corrections Issued | 7/26/2022 | ZAW HAN |
| Building Plans Picked Up | 8/2/2022 | APPLICANT |
| Plan Check Approved | 12/16/2022 | MINA HABILI |
| Issued | 12/22/2022 | APPLICANT |
| CofO in Progress | 12/30/2024 | KEVIN BERBERYAN |
| Permit Finaled | 1/16/2025 | RUBEN SALAS |
| CofO Issued | 1/16/2025 | RUBEN SALAS |
| Permit Finaled | 1/16/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 8/9/2022 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 8/9/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 8/24/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 8/24/2022 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 11/21/2022 | TORI CHEN |
| Construction within easement | Cleared | 11/21/2022 | TORI CHEN |
| Hold | Cleared | 3/10/2023 | JEREMY CORONEL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Demers,, Joe Alan; Lic. No.: C71535 | 894 SANTA MARIA CIRCLE DUARTE, CA 91010 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/30/2023 | Conditional Approval | ROBERT GOLD |
| PLUMBING-Rough | 7/6/2023 | Corrections Issued | RAUL OLAGI |
| Sewer | 7/6/2023 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 7/14/2023 | Partial Approval | RAUL OLAGI |
| Sewer | 7/14/2023 | Approved | RAUL OLAGI |
| Footing/Foundation/Slab | 7/21/2023 | Approved | RAUL OLAGI |
| Underground Mechanical | 7/21/2023 | Partial Approval | RAUL OLAGI |
| ELECTRICAL-Rough | 8/9/2023 | Corrections Issued | RAUL OLAGI |
| HVAC-Rough | 8/9/2023 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 8/9/2023 | Corrections Issued | RAUL OLAGI |
| BUILDING-Rough-Frame | 11/9/2023 | Approved | RAUL OLAGI |
| ELECTRICAL-Rough | 11/9/2023 | Approved | RAUL OLAGI |
| Green Building Rough | 11/9/2023 | Approved | RAUL OLAGI |
| HVAC-Rough | 11/9/2023 | Partial Approval | RAUL OLAGI |
| Interior/Exterior Lathing | 11/9/2023 | Partial Approval | RAUL OLAGI |
| PLUMBING-Rough | 11/9/2023 | Approved | RAUL OLAGI |
| Insulation | 11/22/2023 | Approved | RAUL OLAGI |
| Drywall Nailing | 12/1/2023 | Approved | JUAN VALENZUELA |
| Shower Pan | 12/7/2023 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 12/12/2023 | Approved | JUAN VALENZUELA |
| Final | 12/11/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Green Building Final | 12/11/2024 | Approved | SALVADOR MARTINEZ |
| SGSOV-Seismic Gas S/O Valve | 12/11/2024 | SGSOV Approved | SALVADOR MARTINEZ |
| Smoke Detectors | 12/11/2024 | Partial Inspection | SALVADOR MARTINEZ |
| Final | 12/27/2024 | Corrections Issued | KEVIN BERBERYAN |
| Smoke Detectors | 12/27/2024 | Approved | KEVIN BERBERYAN |
| Final | 12/30/2024 | OK to Issue CofO | KEVIN BERBERYAN |