1068 S QUEEN ANNE PL 90019

Certificate Information: 1068 S QUEEN ANNE PL 90019

Application / Permit
22014-10000-03649
Plan Check / Job No.
B22LA14127
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan Convert (E) Garage to ADU. Remodel (E) 370 SQ.FT. Garage to an ADU to include (N) Bathroom, (N) Living Space with Kitchenette and (N) Storage Room. (N) Addition of 130 SQ.FT. to garage conversion. Total (N) ADU = 500 SQ.FT
Permit Issued
Issued on 8/31/2023
Issuing Office
Current Status
CofO Issued on 6/10/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/20/2022 APPLICANT
Assigned to Plan Check Engineer 7/27/2022 RACHEL BEYENE
Corrections Issued 7/27/2022 RACHEL BEYENE
Applicant returned to address corrections 10/11/2022 RACHEL BEYENE
Plan Check Approved 10/17/2022 RAHEL BEYENE
Issued 8/31/2023 APPLICANT
CofO in Progress 6/6/2025 JUSTIN HAWLEY
Permit Finaled 6/10/2025 DEROLD HAUFF
Permit Finaled 6/10/2025 DEROLD HAUFF
CofO Issued 6/10/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 7/29/2022 CHRISTOPHER ROCHA
Eng Process Fee Ord 176,300 Cleared 7/29/2022 CHRISTOPHER ROCHA
Roof/Waste drainage to street Cleared 7/29/2022 CHRISTOPHER ROCHA
Sewer availability Cleared 7/29/2022 CHRISTOPHER ROCHA
Construction near power lines Cleared 10/1/2022 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Wavering,, Derek; Lic. No.: NA6239       ,
Engineer Wavering,, Derek; Lic. No.: S6239 1371 COLE LANE      UPLAND, CA 91784

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/5/2023 Partial Inspection CALEB MEISTER
Deputy Drilled-In Anchors 11/13/2023 Approved STUART CHAPMAN
Excavation/Setback/Form/Re-Bar 11/13/2023 Corrections Issued STUART CHAPMAN
Footing/Foundation/Slab 11/13/2023 Not Ready for Inspection STUART CHAPMAN
METHANE-Barrier 11/13/2023 Approved STUART CHAPMAN
METHANE-Subgrade 11/13/2023 Approved STUART CHAPMAN
Excavation/Setback/Form/Re-Bar 11/17/2023 Corrections Issued RONNIE MINDANAO
Excavation/Setback/Form/Re-Bar 12/6/2023 Approved JUSTIN HAWLEY
Pre-Inspection 12/6/2023 Approved JUSTIN HAWLEY
BUILDING-Rough-Frame 3/11/2024 Corrections Issued STUART CHAPMAN
BUILDING-Rough-Frame 3/22/2024 Partial Approval JUSTIN HAWLEY
Wood Frame 3/22/2024 Partial Approval JUSTIN HAWLEY
ELECTRICAL-Rough 4/25/2024 Approved JUSTIN HAWLEY
HVAC-Rough 4/25/2024 Corrections Issued JUSTIN HAWLEY
PLUMBING-Rough 4/25/2024 Corrections Issued JUSTIN HAWLEY
PLUMBING-Rough 5/1/2024 Approved JUSTIN HAWLEY
Insulation 7/31/2024 Not Ready for Inspection JOSH MEISTER
Interior/Exterior Lathing 7/31/2024 Partial Approval JOSH MEISTER
BUILDING-Rough-Frame 8/6/2024 Corrections Issued AMIR NAZARIAN
ELECTRICAL-Rough 8/6/2024 Approved AMIR NAZARIAN
HVAC-Rough 8/6/2024 Corrections Issued AMIR NAZARIAN
Insulation 8/6/2024 Not Ready for Inspection AMIR NAZARIAN
BUILDING-Rough-Frame 8/13/2024 Not Ready for Inspection JOAQUIN GREENOUGH
HVAC-Rough 8/13/2024 Corrections Issued JOAQUIN GREENOUGH
Special/Order Compliance 8/13/2024 Partial Inspection LUIS CASTRO
BUILDING-Rough-Frame 8/19/2024 Approved JUSTIN HAWLEY
Green Building Rough 8/19/2024 Approved JUSTIN HAWLEY
HVAC-Rough 8/19/2024 Approved JUSTIN HAWLEY
Insulation 8/19/2024 Approved JUSTIN HAWLEY
Drywall Nailing 9/18/2024 Approved ANTHONY RAMOS
Interior/Exterior Lathing 9/18/2024 Approved ANTHONY RAMOS
Shower Pan 9/18/2024 Approved ANTHONY RAMOS
ELECTRICAL-Final 5/23/2025 Approved ENRIQUE MIRELES
Final 5/23/2025 Corrections Issued ENRIQUE MIRELES
Footing/Foundation/Slab 5/23/2025 Approved ENRIQUE MIRELES
METHANE-Final 5/23/2025 Approved ENRIQUE MIRELES
PLUMBING-Final 5/23/2025 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 5/23/2025 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 5/23/2025 Approved ENRIQUE MIRELES
Final 6/4/2025 Not Ready for Inspection JUSTIN HAWLEY
PLUMBING-Final 6/4/2025 Approved JUSTIN HAWLEY
Final 6/5/2025 OK to Issue CofO JUSTIN HAWLEY
HVAC-Final 6/5/2025 Approved JUSTIN HAWLEY