13119 W WEDDINGTON ST 91401
Certificate Information: 13119 W WEDDINGTON ST 91401
- Application / Permit
- 22014-10000-03632
- Plan Check / Job No.
- B22LA14098
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan (N) Addition: 271 sq ft TO (E) SFD
- Permit Issued
- Issued on 8/16/2022
- Issuing Office
- Current Status
- CofO Issued on 7/10/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/20/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/21/2022 | ZAW HAN |
| Corrections Issued | 7/25/2022 | ZAW HAN |
| Plan Check Approved | 8/10/2022 | KHUONG TRUONG |
| Issued | 8/16/2022 | APPLICANT |
| CofO in Progress | 8/31/2023 | KIRK SANDERS |
| Permit Finaled | 7/10/2024 | RUBEN SALAS |
| CofO Issued | 7/10/2024 | RUBEN SALAS |
| Permit Finaled | 7/10/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 7/28/2022 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/3/2022 | MEGAN GODINEZ |
| Sewer availability | Cleared | 8/3/2022 | MEGAN GODINEZ |
| Public Works-Highway Ded. | Cleared | 8/3/2022 | MEGAN GODINEZ |
| Public Works-Open Permits | Cleared | 8/3/2022 | MEGAN GODINEZ |
| Public Works-Sewers | Cleared | 8/3/2022 | MEGAN GODINEZ |
Contact Information
| Contractor | Hollywood Contractor Corp; Lic. No.: 1092628-B | , |
| Engineer | Carrillo,, Jesus Eduardo; Lic. No.: C77737 | 8207 BROOKGREEN RD DOWNEY, CA 90240 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/26/2022 | Approved | RAFAEL CORTES |
| Floor/Roof Diaphrgm/Shear Wall | 9/7/2022 | Not Ready for Inspection | RAFAEL CORTES |
| Special/Order Compliance | 9/7/2022 | Corrections Issued | RAFAEL CORTES |
| Wood Frame | 9/7/2022 | Partial Approval | RAFAEL CORTES |
| Floor/Roof Diaphrgm/Shear Wall | 9/12/2022 | Partial Approval | ALAN MORELOS |
| Insulation | 9/12/2022 | Partial Approval | ALAN MORELOS |
| Floor/Roof Diaphrgm/Shear Wall | 10/19/2022 | Partial Approval | CALEB MEISTER |
| BUILDING-Rough-Frame | 10/27/2022 | Not Ready for Inspection | WILLIAM WREN |
| ELECTRICAL-Rough | 10/27/2022 | Not Ready for Inspection | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 10/27/2022 | Corrections Issued | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 11/7/2022 | Approved | WILLIAM WREN |
| ELECTRICAL-Rough | 11/30/2022 | Approved | JOHN COLEMAN |
| HVAC-Rough | 11/30/2022 | Not Ready for Inspection | JOHN COLEMAN |
| Interior/Exterior Lathing | 11/30/2022 | Partial Approval | JOHN COLEMAN |
| PLUMBING-Rough | 11/30/2022 | Not Ready for Inspection | JOHN COLEMAN |
| BUILDING-Rough-Frame | 12/12/2022 | No Access for Inspection | JOHN COLEMAN |
| Wood Frame | 12/12/2022 | No Access for Inspection | JOHN COLEMAN |
| BUILDING-Rough-Frame | 12/15/2022 | Not Ready for Inspection | JORDAN KUTZLY |
| PLUMBING-Rough | 12/15/2022 | Approved | JORDAN KUTZLY |
| Insulation | 12/16/2022 | Not Ready for Inspection | KIRK SANDERS |
| BUILDING-Rough-Frame | 12/20/2022 | Approved | JOHN COLEMAN |
| HVAC-Rough | 12/20/2022 | Approved | JOHN COLEMAN |
| Insulation | 12/22/2022 | Approved | WILLIAM WREN |
| Drywall Nailing | 12/29/2022 | Approved | JOHN COLEMAN |
| Insulation | 5/9/2023 | Partial Approval | JOHN COLEMAN |
| ELECTRICAL-Rough | 5/15/2023 | Approved | KIRK SANDERS |
| Final | 7/28/2023 | Corrections Issued | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 7/28/2023 | SGSOV Approved | KIRK SANDERS |
| Smoke Detectors | 7/28/2023 | Approved | KIRK SANDERS |
| Final | 8/30/2023 | OK to Issue CofO | KIRK SANDERS |