9731 W LOCKFORD ST 90035
Certificate Information: 9731 W LOCKFORD ST 90035
- Application / Permit
- 22014-10000-03609
- Plan Check / Job No.
- B22LA14052
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED MAJOR REMODEL AND ADDITION TO EXISTING SINGLE FAMILY DWELLING WITH AN ATTACHED 2 CAR GARAGE. ***SHALL BE SPRINKLERED PER NFPA 13D***
- Permit Issued
- Issued on 6/13/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 11/8/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/19/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/28/2022 | MICHAEL LOPEZ |
| Corrections Issued | 8/4/2022 | MICHAEL LOPEZ |
| Quality Review Completed | 8/10/2022 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 8/12/2022 | APPLICANT |
| Applicant returned to address corrections | 4/21/2023 | MICHAEL LOPEZ |
| Plan Check Approved | 6/8/2023 | MICHAEL LOPEZ |
| Issued | 6/13/2023 | APPLICANT |
| CofO in Progress | 10/24/2025 | EVAN COOPER |
| Permit Finaled | 11/8/2025 | RICHARD STEINBACH |
| CofO Issued | 11/8/2025 | RICHARD STEINBACH |
| Permit Finaled | 11/8/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Permit | Cleared | 8/8/2022 | CATHERINE ADROVER |
| Specific Plan | Cleared | 9/7/2022 | EDUARDO HERMOSO |
| Low Impact Development | Cleared | 9/16/2022 | LONDY ALVARADO |
| Eng Process Fee Ord 176,300 | Cleared | 9/20/2022 | CATHERINE ADROVER |
| Sewer availability | Cleared | 9/20/2022 | CATHERINE ADROVER |
| Roof/Waste drainage to street | Cleared | 9/28/2022 | CATHERINE ADROVER |
| Hydrant and Access approval | Cleared | 10/17/2022 | LAVEON RIDER |
| Miscellaneous | Cleared | 2/22/2023 | ANACANY HURTADO |
| Trees in Parkway | Cleared | 2/22/2023 | ADALBERTO VERA |
| GPI Written Notices | Cleared | 4/21/2023 | MICHAEL LOPEZ |
| Grading Pre-Inspection | Cleared | 4/21/2023 | TIMOTHY POWELL |
Contact Information
| Architect | Leishman,, Thomas Edward; Lic. No.: C15059 | 28100 RIDGEFERN COURT RANCHO PALOS VERDES, CA 90275 |
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/27/2023 | Corrections Issued | BRENDAN LOONEY |
| Pre-Inspection | 8/8/2023 | Partial Inspection | CLAYTON GRAHAM |
| Deputy Drilled-In Anchors | 9/20/2023 | Conditional Approval | MICHAEL PELHAM |
| Excavation/Setback/Form/Re-Bar | 9/20/2023 | Approved | MEL KHACHATOURIAN |
| Underground Mechanical | 9/20/2023 | Partial Approval | MEL KHACHATOURIAN |
| Deputy Reinf. Concrete | 9/22/2023 | Conditional Approval | MICHAEL PELHAM |
| METHANE-Subgrade | 9/28/2023 | Conditional Approval | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 10/11/2023 | Approved | MEL KHACHATOURIAN |
| METHANE-Barrier | 10/11/2023 | Approved | MEL KHACHATOURIAN |
| METHANE-Subgrade | 10/11/2023 | Approved | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/26/2023 | Partial Approval | CLAYTON GRAHAM |
| Floor/Roof Diaphrgm/Shear Wall | 1/9/2024 | Partial Approval | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 2/27/2024 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 2/27/2024 | Approved | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/29/2024 | Approved | OGANES TARAKHCHYAN |
| HVAC-Rough | 3/19/2024 | Approved | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| Green Building Rough | 4/1/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| METHANE-Rough | 4/1/2024 | Approved | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/2/2024 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 4/8/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 4/11/2024 | Partial Approval | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 4/15/2024 | Partial Approval | OGANES TARAKHCHYAN |
| Insulation | 4/17/2024 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 4/25/2024 | Approved | OGANES TARAKHCHYAN |
| Shower Pan | 5/15/2024 | Approved | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 7/9/2024 | Approved | ASHLEY THOMPSON |
| Gas Test | 1/10/2025 | Approved | BOBBY KEY |
| Special/Order Compliance | 1/10/2025 | Partial Inspection | JAYLIN GRAVITTE |
| ELECTRICAL-Final | 3/6/2025 | Corrections Issued | ASHLEY THOMPSON |
| PLUMBING-Final | 5/5/2025 | Corrections Issued | ARAM AVEDISIAN |
| ELECTRICAL-Final | 7/9/2025 | Approved | ARAM AVEDISIAN |
| PLUMBING-Final | 7/9/2025 | Approved | ARAM AVEDISIAN |
| HVAC-Final | 7/23/2025 | Corrections Issued | ASHLEY THOMPSON |
| Service/Power Release | 7/23/2025 | Approved | ASHLEY THOMPSON |
| HVAC-Final | 8/18/2025 | Approved | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 9/26/2025 | Approved | ASHLEY THOMPSON |
| Final | 9/26/2025 | Corrections Issued | ASHLEY THOMPSON |
| Green Building Final | 9/26/2025 | Approved | ASHLEY THOMPSON |
| Green Building Rough | 9/26/2025 | Approved | ASHLEY THOMPSON |
| SGSOV-Seismic Gas S/O Valve | 9/26/2025 | SGSOV Approved | ASHLEY THOMPSON |
| Smoke Detectors | 9/26/2025 | Corrections Issued | ASHLEY THOMPSON |
| Verify Sprinkler Sign Off | 9/26/2025 | Approved | ASHLEY THOMPSON |
| Final | 10/24/2025 | OK to Issue CofO | EVAN COOPER |
| Smoke Detectors | 10/24/2025 | Approved | EVAN COOPER |