3858 S MINERVA AVE 90066

Certificate Information: 3858 S MINERVA AVE 90066

Application / Permit
22014-10000-03597
Plan Check / Job No.
B22LA13972
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE TO RECREATION ROOM AND STORAGE ADD NEW ACCESSORY DWELLING UNIT ADDITION ABOVE PER LAMC 12.22A.33 (c)-(d)
Permit Issued
Issued on 11/20/2023
Issuing Office
Metro
Current Status
CofO in Progress on 2/25/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/18/2022 APPLICANT
Assigned to Plan Check Engineer 8/11/2022 MAHNAZ NOURHASHEMI
Corrections Issued 8/18/2022 MAHNAZ NOURHASHEMI
Quality Review Completed 8/24/2022 KEN GILL
Building Plans Picked Up 9/2/2022 APPLICANT
Applicant returned to address corrections 10/27/2023 MAHNAZ NOURHASHEMI
Plan Check Approved 11/20/2023 MAHNAZ NOURHASHEMI
Issued 11/20/2023 APPLICANT
CofO in Progress 1/30/2026 DAVID FEILER
No Progress 2/25/2026 DAVID FEILER
CofO in Progress 2/25/2026 DAVID FEILER

Permit Application Clearance Information

Address approval Cleared 9/3/2023 AHMED AMARRAGY
Eng Process Fee Ord 176,300 Cleared 9/6/2023 AHMED AMARRAGY
Roof/Waste drainage to street Cleared 9/6/2023 AHMED AMARRAGY
Sewer availability Cleared 9/6/2023 AHMED AMARRAGY
Specific Plan Cleared 9/12/2023 FREDDY GARCIA

Contact Information

Contractor Owner-Builder       ,
Engineer Sarrami,, Gholamali F; Lic. No.: C43720 4942 HIGHLAND VIEW AVENUE      LOS ANGELES, CA 90041

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/20/2024 Corrections Issued HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 2/4/2025 Partial Approval BOBBY KEY
Rough-Elec/Plmb/HVAC 2/4/2025 Corrections Issued BOBBY KEY
ELECTRICAL-Rough 2/11/2025 Approved EVAN COOPER
HVAC-Rough 3/19/2025 Approved MICHAEL ALLEN
Interior/Exterior Lathing 3/19/2025 Partial Approval MICHAEL ALLEN
PLUMBING-Rough 3/19/2025 Approved MICHAEL ALLEN
Floor/Roof Diaphrgm/Shear Wall 4/1/2025 Corrections Issued JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 4/3/2025 Approved MICHAEL ALLEN
Insulation 4/3/2025 Approved MICHAEL ALLEN
Drywall Nailing 4/11/2025 Approved MICHAEL ALLEN
Interior/Exterior Lathing 4/11/2025 Approved MICHAEL ALLEN
Shower Pan 6/20/2025 Approved RUBEN RIVAS
ELECTRICAL-Final 11/25/2025 No Access for Inspection WILBER ROSALES
HVAC-Final 11/25/2025 No Access for Inspection WILBER ROSALES
PLUMBING-Final 11/25/2025 No Access for Inspection WILBER ROSALES
ELECTRICAL-Final 12/2/2025 Corrections Issued RUBEN RIVAS
HVAC-Final 12/2/2025 Approved RUBEN RIVAS
PLUMBING-Final 12/2/2025 Corrections Issued RUBEN RIVAS
BUILDING-Rough-Frame 12/17/2025 Approved ANTHONY EGSON
ELECTRICAL-Final 12/17/2025 Approved ANTHONY EGSON
Final 12/17/2025 Corrections Issued ANTHONY EGSON
Footing/Foundation/Slab 12/17/2025 Approved ANTHONY EGSON
Green Building Final 12/17/2025 Approved ANTHONY EGSON
Green Building Rough 12/17/2025 Approved ANTHONY EGSON
PLUMBING-Final 12/17/2025 Approved ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 12/17/2025 SGSOV Not Required ANTHONY EGSON
Smoke Detectors 12/17/2025 Approved ANTHONY EGSON
Final 1/30/2026 OK to Issue CofO DAVID FEILER