7520 N AMIGO AVE 91335

Certificate Information: 7520 N AMIGO AVE 91335

Application / Permit
22014-10000-03574
Plan Check / Job No.
B22LA13910
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHED GARAGE (324 SQFT) TO BE CONVERTED TO AN ADU AND ADD 20.5'X16' AT REAR (1,200 SF max per Ordinance, LAMC 12.22 A.33 (c)-(d))
Permit Issued
Issued on 9/23/2022
Issuing Office
Metro
Current Status
CofO Issued on 4/8/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/15/2022 APPLICANT
Assigned to Plan Check Engineer 7/22/2022 AUNG SOE
Corrections Issued 7/25/2022 AUNG SOE
Building Plans Picked Up 7/29/2022 APPLICANT
Applicant returned to address corrections 8/11/2022 LAWRENCE QUIRANTE
Plan Check Approved 9/23/2022 JOSEPH RAFOLS
Issued 9/23/2022 APPLICANT
CofO in Progress 12/26/2023 JEFFREY BULL
CofO Issued 4/8/2024 JOHN JANSON
Permit Finaled 4/8/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 8/17/2022 MEGAN GODINEZ
Roof/Waste drainage to street Cleared 8/17/2022 MEGAN GODINEZ
Sewer availability Cleared 8/18/2022 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 9/22/2022 MEGAN GODINEZ
Public Works-Highway Ded. Cleared 9/22/2022 MEGAN GODINEZ
Public Works-Open Permits Cleared 9/22/2022 MEGAN GODINEZ
Public Works-Sewers Cleared 9/22/2022 MEGAN GODINEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Truong,, Phong; Lic. No.: C70784 20439 E CRESTLINE DRIVE      WALNUT, CA 91789

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/18/2023 Approved JEFFREY BULL
Insulation 3/13/2023 Partial Approval JEFFREY BULL
BUILDING-Rough-Frame 5/31/2023 Approved JEFFREY BULL
ELECTRICAL-Rough 5/31/2023 Approved JEFFREY BULL
Green Building Rough 5/31/2023 Not Ready for Inspection JEFFREY BULL
HVAC-Rough 5/31/2023 Approved JEFFREY BULL
PLUMBING-Rough 5/31/2023 Approved JEFFREY BULL
Green Building Rough 6/28/2023 Approved JUSTIN HAWLEY
Insulation 6/28/2023 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 6/28/2023 Partial Approval JUSTIN HAWLEY
Drywall Nailing 7/13/2023 Approved JUSTIN HAWLEY
Final 10/2/2023 Corrections Issued JEFFREY BULL
Green Building Final 10/2/2023 Not Ready for Inspection JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 10/2/2023 SGSOV Approved JEFFREY BULL
Smoke Detectors 10/2/2023 Approved JEFFREY BULL
Final 12/26/2023 OK to Issue CofO JEFFREY BULL
Green Building Final 12/26/2023 Approved JEFFREY BULL