3881 S CIMARRON ST 90062

Certificate Information: 3881 S CIMARRON ST 90062

Application / Permit
22014-10000-03565
Plan Check / Job No.
B22LA13848
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan (E) DETACHED GARAGE TO ADU CONVERSION AND ADDITION PER LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 5/26/2023
Issuing Office
Current Status
CofO Issued on 1/13/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/15/2022 APPLICANT
Assigned to Plan Check Engineer 7/22/2022 SELLA BENYAMIN
Corrections Issued 7/22/2022 SELLA BENYAMIN
Applicant returned to address corrections 5/3/2023 SELLA BENYAMIN
Applicant returned to address corrections 5/23/2023 HANS SANTIAGO
Plan Check Approved 5/25/2023 FARSHAD ALIMOHAMADI
Issued 5/26/2023 APPLICANT
CofO in Progress 1/10/2024 SABAS ALONSO
Permit Finaled 1/13/2024 DEROLD HAUFF
CofO Issued 1/13/2024 DEROLD HAUFF
Permit Finaled 1/13/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/14/2022 AMAAN MALIK
Low Impact Development (LID) Cleared 4/11/2023 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 4/25/2023 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 4/29/2023 STEVE MELGAR
Sewer availability Cleared 4/29/2023 STEVE MELGAR

Contact Information

Contractor Owner-Builder       ,

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/26/2023 Partial Approval SABAS ALONSO
Underground Mechanical 6/26/2023 Partial Approval SABAS ALONSO
Footing/Foundation/Slab 7/3/2023 Corrections Issued MICHAEL LEWIS
ELECTRICAL-Rough 7/26/2023 Not Ready for Inspection MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 7/26/2023 Corrections Issued MICHAEL LEWIS
PLUMBING-Rough 7/26/2023 Not Ready for Inspection MICHAEL LEWIS
ELECTRICAL-Rough 8/1/2023 Approved SABAS ALONSO
PLUMBING-Rough 8/1/2023 Approved SABAS ALONSO
Sewer 8/1/2023 Approved SABAS ALONSO
Underground Mechanical 8/1/2023 Partial Approval SABAS ALONSO
BUILDING-Rough-Frame 8/3/2023 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 8/3/2023 Approved SABAS ALONSO
Green Building Rough 8/3/2023 Approved SABAS ALONSO
HVAC-Rough 8/3/2023 Approved SABAS ALONSO
Insulation 8/7/2023 Approved SABAS ALONSO
Drywall Nailing 8/14/2023 Approved CHARLES BOGHOSKHAN
Interior/Exterior Lathing 8/14/2023 Not Ready for Inspection CHARLES BOGHOSKHAN
Interior/Exterior Lathing 8/28/2023 Partial Approval ALIZAH MAYAGOITIA
Interior/Exterior Lathing 8/31/2023 Approved SABAS ALONSO
Shower Pan 9/1/2023 Not Ready for Inspection SABAS ALONSO
Shower Pan 9/7/2023 Approved BRENDAN MORELLI
Interior/Exterior Lathing 9/18/2023 Partial Inspection MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 9/26/2023 No Access for Inspection SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 11/2/2023 SGSOV Not Ready JEFFREY MEAD
Final 12/7/2023 Corrections Issued SABAS ALONSO
Footing/Foundation/Slab 12/7/2023 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 12/7/2023 SGSOV Approved SABAS ALONSO
Smoke Detectors 12/7/2023 Approved SABAS ALONSO
Final 12/12/2023 Corrections Issued SABAS ALONSO
Final 1/5/2024 Conditional Approval SABAS ALONSO
Final 1/9/2024 OK to Issue CofO SABAS ALONSO